| 2016-04-28 14:27:08 | 1ST REVIEW: FBC 2014 MECHANICAL |
| | PERMIT #16041113 |
| | 4/28/16 |
| | |
| | 1) CONCERNING THE ARCHITECT'S NOTE ON SHEET A-1 THAT |
| | STATES "ALL MECHANICAL WORK SHALL BE DONE UNDER A |
| | SEPARATE PERMIT AND SHOWN ON SEPARATE PERMIT DRAWINGS |
| | PREPARED BY OTHERS", PLEASE REFER TO SECTION 107.3.4 |
| | DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE. |
| | |
| | 107.3.4.2 DEFERRED SUBMITTALS. FOR THE PURPOSES OF THIS |
| | SECTION, DEFERRED SUBMITTALS ARE DEFINED AS THOSE |
| | PORTIONS OF THE DESIGN THAT ARE NOT SUBMITTED AT THE |
| | TIME OF THE APPLICATION AND THAT ARE TO BE SUBMITTED TO |
| | THE BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD. |
| | DEFERRAL OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR |
| | APPROVAL OF THE BUILDING OFFICIAL. THE REGISTERED |
| | DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST |
| | THE DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS |
| | FOR REVIEW BY THE BUILDING OFFICIAL. DOCUMENTS FOR |
| | DEFERRED SUBMITTAL ITEMS SHALL BE SUBMITTED TO THE |
| | REGISTERED DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE |
| | WHO SHALL REVIEW THEM AND FORWARD THEM TO THE BUILDING |
| | OFFICIAL WITH A NOTATION INDICATING THAT THE DEFERRED |
| | SUBMITTAL DOCUMENTS HAVE BEEN REVIEWED AND FOUND TO BE |
| | IN GENERAL CONFORMANCE TO THE DESIGN OF THE BUILDING. |
| | THE DEFERRED SUBMITTAL ITEMS SHALL NOT BE INSTALLED |
| | UNTIL THE DEFERRED SUBMITTAL DOCUMENTS HAVE BEEN |
| | APPROVED BY THE BUILDING OFFICIAL. |
| | |
| | IT APPEARS THAT ACCORDING TO THE ABOVE SECTION THAT THE |
| | ARCHITECT OF RECORD SHALL, AT A MINIMUM, REVIEW AND |
| | APPROVE THE DEFERRED MECHANICAL PLANS, OR THOSE PANS |
| | SHALL BE SUBMITTED WITH UNDER THIS PERMIT APPLICATION. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |
| | [email protected] |
| | |