Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2016-05-10 Cont ID  
Sent By cthroop Date 2016-05-10 Time 15:50 Rev Time 0.00
Received By cthroop Date 2016-05-10 Time 15:50 Sent To M
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2016-05-02 Cont ID  
Sent By cthroop Date 2016-05-02 Time 15:43 Rev Time 0.00
Received By cthroop Date 2016-05-02 Time 15:13 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2016-04-12 Cont ID  
Sent By cthroop Date 2016-04-12 Time 12:21 Rev Time 0.00
Received By cthroop Date 2016-04-12 Time 11:50 Sent To  
Notes
2016-04-12 12:24:581ST REVIEW: FBC 2014 5TH ED
 CHRISTOPHER S. THROOP, C.B.O.
 BLDG. PLANS EXAMINER ? PX3169
 (561) 805-6718
 [email protected]
  
 1. STRUCTURAL ENGINEER TO SIGN AND SEAL PLAN SHEET
 S-1.0
  
 FBC-107.1 GENERAL. SUBMITTAL DOCUMENTS CONSISTING OF
 CONSTRUCTION DOCUMENTS - THE CONSTRUCTION DOCUMENTS
 SHALL BE PREPARED BY A REGISTERED DESIGN PROFESSIONAL
 WHERE REQUIRED BY CHAPTER 471, FLORIDA STATUTES& 61G15
 FLORIDA ADMINISTRATIVE CODE OR CHAPTER 481, FLORIDA
 STATUTES& 61G1 FLORIDA ADMINISTRATIVE CODE, THEN HE OR
 SHE SHALL AFFIX HIS OR HER OFFICIAL SEAL TO SAID
 DRAWINGS, SPECIFICATIONS AND ACCOMPANYING DATA, AS
 REQUIRED BY FLORIDA STATUTE.
  

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2016-05-02 Cont ID  
Sent By albarran Date 2016-05-02 Time 16:53 Rev Time 0.00
Received By albarran Date 2016-05-02 Time 16:43 Sent To I
Notes
2016-05-02 17:14:25ALL PREVIOUSLY MENTIONED COMMENTS HAVE BEEN
 SATISFACTORILY ADDRESSED.
  
  

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2016-04-01 Cont ID  
Sent By albarran Date 2016-04-01 Time 11:45 Rev Time 0.00
Received By albarran Date 2016-04-01 Time 09:29 Sent To B
Notes
2016-04-01 11:46:10FAILED 1ST ELECTRICAL REVIEW AS INDICATED BELOW
 REVIEWED FOR COMPLIANCE WITH:
 5TH EDITION FBC 2014 AND NFPA 70 2011 (NEC)
  
 CORRECTIONS REQUIRED:
 1. THE MANUFACTURER'S SPECS ON THE PROPOSED UNITS
 INDICATE AN OPERATING VOLTAGE OF 208V/3 PHASE;
 ACCORDING TO THE MARKINGS ON THE PLANS, THE AVAILABLE
 VOLTAGE IS 277/480V/3 PHASE. VERIFY EXISTING CONDITIONS
 TO CONFIRM COMPATIBILITY OF PROPOSED UNITS.
 2. THE SAME MANUFACTURER'S SPEC SHEET SPECIFICALLY
 CALLS FOR THE USE OF COPPER CONDUCTORS W/A 90 DEGREE
 INSULATION. THE PROVIDED RISER DIAGRAM OFFERS THE
 UNACCEPTABLE OPTION OF USING ALUMINUM CONDUCTORS,
 CONTRARY TO MANUFACTURER'S SPECS.
 3. THE RISERS AS SHOWN FAIL TO INCLUDE THE REQUIRED
 115V/20A CIRCUITS FOR THE HEATERS AND CONTROL PANEL
 POWER SUPPLY.
 4. PROVIDE LOAD CALCS TAKING INTO ACCOUNT THE REQUIRED
 DERATION FOR CONDUIT FILL AND AMBIENT TEMPERATURE
 EXPOSURE. MAKE SURE YOU INDICATE THE REQUIRED 90 DEGREE
 CONDUCTOR INSULATION.
 5. ACCORDING TO THE FLOOR PLAN THE EXISTING SERVICE
 OUTLET IS BEYOND THE MAXIMUM 25 FEET MANDATED BY THE
 NEC.
 6. THE NEW OUTLET SHALL COMPLY WITH NEC406.12 WHEREAS
 THE ACTUAL DEVICE IS LISTED WEATHER-RESISTANT.
  
 WHEN RESUBMITTING, FOR A QUICKER RETURN ON YOUR
 RE-SUBMITTAL, PLEASE PROVIDE A RESPONSE LETTER
 (NARRATIVE) ADDRESSING EACH ITEM AND THE PAGE NUMBER
 WHERE THE CORRECTIONS APPEAR ALONG WITH THE STANDARD
 CITY RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT
 CORRECTED PAGES INTO THE SUBMITTAL PACKAGE. MARK VOID
 AND LEAVE THE PREVIOUSLY REVIEWED SHEETS FOR
 COMPARATIVE REVIEW. CLOUDING THE CHANGES WILL BE
 GREATLY APPRECIATED.
  
 IF YOU HAVE FURTHER QUESTIONS, PLEASE DON'T HESITATE TO
 CONTACT ME DIRECTLY.
  
 THANK YOU,
 MIKE ALBARRAN
 ELECTRICAL PLANS EXAMINER
 PH: 561-805-6746
 EMAIL: [email protected]
  
  

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2016-05-11 Cont ID  
Sent By ccole Date 2016-05-11 Time 06:59 Rev Time 0.00
Received By ccole Date 2016-05-10 Time 11:22 Sent To  
Notes
2016-05-10 11:22:51RESUB ROUTED TO CTHROOP

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2016-05-02 Cont ID  
Sent By albarran Date 2016-05-02 Time 17:31 Rev Time 0.00
Received By albarran Date 2016-04-20 Time 13:13 Sent To  
Notes
2016-05-02 17:38:215/2/16 PASSED ELECTRICAL REVIEW BUT FAILED MECHANICAL.
 CONTRACTOR NOTIFIED VIA EMAIL. FILE SENT TO LARGE
 DENIED DRAWER "S". MA
2016-04-20 13:14:49B12

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2016-04-12 Cont ID  
Sent By cthroop Date 2016-04-12 Time 12:20 Rev Time 0.00
Received By cthroop Date 2016-03-31 Time 15:11 Sent To  
Notes
2016-03-31 15:11:51ROUTED TO MECHANICAL

Review Stop M MECHANICAL (A/C)
Rev No 4 Status P Date 2016-05-11 Cont ID  
Sent By ccole Date 2016-05-11 Time 06:57 Rev Time 0.00
Received By ccole Date 2016-05-11 Time 06:57 Sent To  
Notes
2016-05-11 06:59:07MECHANICAL PROVISOS:
  
 1) WELDER'S CERTIFICATE AND WELDING PROCEDURE
 SECIFICATION MUST BE ON-SITE AT TIME OF INSPECTION.
  
 CHRISTOPHER L. COLE
 MECHANICAL PLANS EXAMINER
 561-805-6719
 [email protected]
  
  

Review Stop M MECHANICAL (A/C)
Rev No 3 Status N Date 2016-05-02 Cont ID  
Sent By cthroop Date 2016-05-02 Time 15:42 Rev Time 0.00
Received By cthroop Date 2016-05-02 Time 15:42 Sent To  
Notes
2016-05-02 15:42:54OPENED M-STOP BY MISTAKE. CST

Review Stop M MECHANICAL (A/C)
Rev No 2 Status F Date 2016-04-26 Cont ID  
Sent By ccole Date 2016-04-26 Time 11:02 Rev Time 0.00
Received By ccole Date 2016-04-26 Time 11:02 Sent To  
Notes
2016-04-26 11:06:431ST REVIEW: FBC 2014 MECHANICAL
 PERMIT #16031458
 4/26/16
  
 1) PROVIDE A COMMISSIONING PLAN IN COMPLIANCE WITH
 SECTION C408.2 AND C408.2.3.1 FBC-14 ENERGY
 CONSERVATION
 2) INDICATE THE CLEARANCE HEIGHT FROM THE FINISHED ROOF
 SURFACE TO THE BOTTOM OF THE SUPPORT STRUCTURE- TABLE
 1509.6.5 FBC-14 BUILDING.
 3) PROVIDE ENGINEERED ATTACHMENT DETAILS FOR MOUNTING
 THE CHILLERS TO THE NEW AND RE-FURBISHED SUPPORT
 PLATFORM- SECTION 301.15 FBC-14 MECHANICAL.
 4) PROVIDE GUARD AND HANDRAIL DETAILS FOR THE EQUIPMENT
 PLATFORMS- SECTIONS 1012 & 1013 FBC-14 BUILDING.
 4) PROVIDE A SITE PLAN SHOWING THE TEMPORARY LOCATION
 OF OF THE CHILLER ON THE NORTH GRADE AND INCLUDE
 DETAILS FOR PROTECTION OF THE EQUIPMENT AND COMPONENTS
 FROM VEHICULAR IMPACT, AND SAFE GUARDS TO PROTECT THE
 PUBLIC- SECTIONS 303.4 FBC-14 MECHANICAL, AND 3301.2
 FBC-14 BUILDING.
 5) PROVIDE A TEMPORARY HYDRONIC PIPING PLAN INDICATING
 THE PIPING RUNS, PIPE ANCHORAGE AND SUPPORT, AND
 PROTECTIONS.
  
 CHRISTOPHER L. COLE
 MECHANICAL PLANS EXAMINER
 561-805-6719
 [email protected]
  

Review Stop M MECHANICAL (A/C)
Rev No 1 Status F Date 2016-03-31 Cont ID  
Sent By jvalido Date 2016-03-31 Time 19:18 Rev Time 0.00
Received By jvalido Date 2016-03-31 Time 18:58 Sent To E
Notes
2016-03-31 19:18:31107.1 - PROVIDE OFFICIAL SEAL AND SIGNATURE TO
 STRUCTURAL PLANS.