Plan Review Details - Permit 16010415
Plan Review Stops For Permit 16010415
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2016-01-26 Cont ID  
Sent By rmcdouga Date 2016-01-26 Time 17:53 Rev Time 0.00
Received By rmcdouga Date 2016-01-26 Time 17:10 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2016-02-08 Cont ID  
Sent By mvaldes Date 2016-02-08 Time 08:42 Rev Time 0.00
Received By mvaldes Date 2016-02-08 Time 08:42 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2016-01-26 Cont ID  
Sent By rmcdouga Date 2016-01-26 Time 17:53 Rev Time 0.00
Received By rmcdouga Date 2016-01-26 Time 17:10 Sent To  
Notes
2016-01-26 17:53:48PLAN
 REVIEW COMMENTS
  
 1ST REVIEW: FBC FIFTH EDITION (2014)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY ELECTRICAL
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) SUBMIT TWO SETS OF ELECTRICAL LOAD CALCULATIONS TO
 SHOW THAT THE EXISTING SERVICE IS ADEQUATE FOR THE
 ADDITION OF THE ELECTRIC POOL HEATER. FBCR-E3602.2 AND
 E4206.12
  
 2) PLANS SPECIFY A GULFSTREAM HE-125RA 125K BTU HEAT
 PUMP AND THE SPECS THAT WERE SUBMITTED ARE FOR A
 HAYWARD HEAT PUMP. FBC 107.2.1
  
  

Review Stop G GAS REVIEW
Rev No 1 Status N Date 2016-01-25 Cont ID  
Sent By tklarge Date 2016-01-25 Time 05:32 Rev Time 0.00
Received By tklarge Date 2016-01-25 Time 05:30 Sent To  
Notes
2016-01-25 05:32:09GAS PLAN REVIEW
 A GAS PLAN HAS NOT BEEN INCLUDED IN THIS SUBMITTAL
 PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN PERFORMED AT
 THIS TIME. A SEPARATE GAS PERMIT AND PLANS WILL BE
 REQUIRED FOR A CONTRACTOR TO PERFORM THE RELATED WORK.
 PROVIDE COMPLETE PLANS, APPLIANCE/ EQUIPMENT
 SPECIFICATIONS AND GAS RISER THAT REFLECT THE ENTIRE
 SCOPE OF GAS WORK TO BE DONE. WPB AMEND. TO FBC SEC.
 107.2.1.
  
 PLUMBING PLAN REVIEW
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 561-805-6692
 [email protected]
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2016-02-08 Cont ID  
Sent By lmarchan Date 2016-02-08 Time 10:04 Rev Time 0.00
Received By lmarchan Date 2016-02-02 Time 14:11 Sent To  
Notes
2016-02-02 14:12:01RESUB ROUTED TO RMCDOUGAL

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2016-01-26 Cont ID  
Sent By rmcdouga Date 2016-01-26 Time 17:54 Rev Time 0.00
Received By rmcdouga Date 2016-01-14 Time 13:38 Sent To  
Notes
2016-01-19 13:38:36ROUTED TO ZONING

Review Stop P PLUMBING
Rev No 1 Status P Date 2016-01-25 Cont ID  
Sent By tklarge Date 2016-01-25 Time 05:30 Rev Time 0.00
Received By tklarge Date 2016-01-25 Time 05:12 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2016-01-20 Cont ID  
Sent By   Date 2016-01-20 Time   Rev Time 0.00
Received By sgraham Date 2016-01-20 Time 12:49 Sent To B
Notes
***NONE***