Plan Review Details - Permit 16010132
Plan Review Stops For Permit 16010132
Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2016-02-12 Cont ID  
Sent By lmarchan Date 2016-02-12 Time 09:20 Rev Time 0.00
Received By lmarchan Date 2016-02-10 Time 11:11 Sent To  
Notes
2016-02-12 09:21:03RESUB WAS NEW IRRIGATION PLAN - NEEDS TO RESUBMIT FOR
 LANDSCAPING.
2016-02-10 11:11:30RESUB ROUTED TO RCARANCI VIA ZONING INBOX

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2016-02-10 Cont ID  
Sent By lmarchan Date 2016-02-10 Time 11:10 Rev Time 0.00
Received By lmarchan Date 2016-01-06 Time 13:14 Sent To  
Notes
2016-01-13 13:14:40ROUTED TO ZONING

Review Stop L LANDSCAPING
Rev No 2 Status P Date 2016-02-16 Cont ID  
Sent By rcaranci Date 2016-02-16 Time 11:50 Rev Time 0.00
Received By rcaranci Date 2016-02-16 Time 11:50 Sent To  
Notes
2016-02-16 11:51:47CONTRACTOR ADDED HANDWRITTEN NOTE TO ADD PLANTS AT THE
 NORTH END OF THE BATHROOM BUILDING.

Review Stop L LANDSCAPING
Rev No 1 Status F Date 2016-01-22 Cont ID  
Sent By rcaranci Date 2016-01-22 Time 13:26 Rev Time 0.00
Received By rcaranci Date 2016-01-22 Time 13:26 Sent To  
Notes
2016-01-22 13:29:46SEPARATE PERMIT FOR IRRIGATION, THIS IS ONLY
 LANDSCAPING.
  
 1/22/16 CHANGES TO PLAN COMPARED TO APPROVED PLAN FROM
 PB1171JJ APPROVED 10/2014,
 CONTACTED COTLEUR AND HEARING REGARDING CHANGES.
 LANDSCAPING MISSING FROM BATHROOM BUILDING BETWEEN
 BUILDING AND SIDEWALK.

Review Stop P PLUMBING
Rev No 2 Status N Date 2016-02-12 Cont ID  
Sent By lmarchan Date 2016-02-12 Time 09:19 Rev Time 0.00
Received By lmarchan Date 2016-02-12 Time 09:19 Sent To  
Notes
2016-02-12 09:20:36SEPARATE IRRIGATION PERMIT APPLIED FOR 16010133 PER RC

Review Stop P PLUMBING
Rev No 1 Status F Date 2016-01-09 Cont ID  
Sent By tklarge Date 2016-01-09 Time 05:21 Rev Time 0.00
Received By tklarge Date 2016-01-09 Time 05:21 Sent To  
Notes
2016-01-09 05:21:291) THE PLANS DO NOT SHOW ANY PROVISIONS FOR IRRIGATION.
 WILL A CONNECTION BE MADE TO THE EXISITING IRRIGATION
 SYSTEM TO SERVE THE NEW LANDSCAPING? IF CONNECTING TO
 AN EXISTING SYSTEM, SHOW THE LOCATION, SIZE AND TYPE OF
 THE EXISTING BFP DEVICE AND CONTROLLER AND SHOW THE
 LOCATION OF THE REQUIRED RAIN SENSOR. IF THE IRRIGATION
 SYSTEM WILL HAVE IT'S OWN SEPARATE CONNECTION TO THE
 POTABLE WATER SYSTEM, THEN A BACKFLOW PREVENTION DEVICE
 AND RAIN SENSOR & CONTROLLER SHALL SHALL BE INSTALLED.
 THE BFP DEVICE SHALL COMPLY WITH THE CWPB CROSS
 CONNECTION MANUAL.SHOW THE LOCATION OF THE NEW
 CONTROLLER, BFP DEVICE AND THE RAIN SENSOR IF
 APPLICABLE.
 2) SUBMIT AN IRRIGATION PLAN FOR REVIEW. WPB AMEND. TO
 FBC SEC. 107.2.1.
  
 PLUMBING PLAN REVIEW
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 561-805-6692