Plan Review Details - Permit 15110968
| Plan Review Stops For Permit 15110968 |
| Review Stop |
ENG |
ENGINEERING CSD |
| Rev No |
1 |
Status |
P |
Date |
2015-12-02 |
|
|
Cont ID |
|
| Sent By |
cranford |
Date |
2015-12-02 |
Time |
|
Rev Time |
1.00 |
| Received By |
mgonzale |
Date |
2015-12-02 |
Time |
|
Sent To |
I |
|
| Notes |
| 2015-12-02 16:58:42 | CALL 811 BEFORE DIGGING. |
|
|
| Review Stop |
G |
GAS REVIEW |
| Rev No |
3 |
Status |
P |
Date |
2016-02-16 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2016-02-16 |
Time |
02:40 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2016-02-13 |
Time |
07:08 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
G |
GAS REVIEW |
| Rev No |
2 |
Status |
F |
Date |
2016-02-05 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2016-02-05 |
Time |
05:30 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2016-02-05 |
Time |
04:17 |
Sent To |
|
|
| Notes |
| 2016-02-05 05:26:16 | 1)THE PLANS SHOW A LINE LENGTH OF 30 FT. OF PE PIPE TO | | | THE BUILDING AND ALSO A LINE LENGTH OF 60 FT. TO THE | | | 500 KW FUTURE GENERATOR WHICH IS CLOSER. CLARIFY. | | | 2) THERE IS A SECTION OF PIPE MISSING FROM THE GAS | | | RISER FROM THE 1 1/2" PE PIPE UP TO THE 5 PSI REGULATOR | | | NEAR THE EXTERIOR OF THE BUILDING. CLARIFY. | | | 3) SHT. P-2 - THERE IS A NOTE ON THE GAS RISER THAT | | | CALLS OUT A 5 PSI TO 14" W.C.REGULATOR BUT NOTHING IS | | | SHOWN. CLARIFY. | | | 4) P-1 - DRAWING NOTE #30 IS NOT SHOWN ON SHT.P-1. | | | CLARIFY.WHAT TYPE OF PIPING IS GOING TO THE 100KW | | | GENERATOR? SHOW ON GAS RISER. | | | 5) SHT. P-1 - NOTE #4 - THE PLUMBING DESIGN DATA TABLE | | | NOTES A MINIMUM OF 1 1/2" GAS LINE TO THE 100KW | | | EMERGENCY GENERATOR BUT THE GAS RIISER AND SHT. P-1 | | | SHOWS 1". CLARIFY. | | | | | | PLUMBING PLAN REVIEW | | | TIM LARGE | | | CHIEF PLUMBING INSPECTOR | | | 561-805-6692 | | | [email protected] | | | |
|
|
| Review Stop |
G |
GAS REVIEW |
| Rev No |
1 |
Status |
F |
Date |
2015-11-25 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2015-11-25 |
Time |
06:44 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2015-11-25 |
Time |
04:57 |
Sent To |
|
|
| Notes |
| 2015-11-25 05:39:50 | 1) SHT. P-1 - IF THE LOCATION OF THE METER HAS BEEN | | | CHANGED, SHOW THE NEW DISTANCE FOR THE PE PIPE FROM THE | | | METER TO THE THE FIRST STEP DOWN REGULATOR.ENSURE PIPE | | | SIZE IS ADEQUATE FOR THE LOAD. WPB AMEND. TO FBC SEC. | | | 107.2.1. | | | 2) SHOW THE TYPE OF PIPE, SIZE, PSI OF THE GAS AND THE | | | LENGTH OF ALL PIPE SECTIONS FOR THE UNDERGROUND PE | | | PIPEFROM THE GAS METER TO THE FIRST STEP DOWN | | | REGULATOR. THIS INFO CAN BE FOUND ON THE ORIGINAL GAS | | | PLAN. | | | 3) SHOW THE BTU LOAD AND SIZE THE GAS LINE FOR THE | | | FUTURE STANDBY GENERATOR. THE BTU LOAD SHALL CORRELATE | | | WITH THE BTU LOAD ON P-1. | | | 4) THE BTU LOAD FOR THE EMERGENCY GENERATOR ON SHT. P-2 | | | SHOWS 860 CFH AND SHT. P-1 SHOWS 1,353 CFH. | | | CLARIFY.ENSURE THE PIPE IS SIZED FOR THE MAXIMUM BTU | | | LOAD BASED ON THE TOTAL DEVELOPED LENGTH FROM THE POINT | | | OF DELIVERY. | | | 5) SIZE ALL PIPE SECTIONS FROM THE GAS METER UP TO | | | WHERE THE GAS PIPING PENETRATES THE EXTERIOR WALL OF | | | THE STRUCTURE. ALSO, SIZE ALL PIPE SECTIONS AND | | | INDICATE TYPE OF PIPE AND PSI OF THE GAS TO THE FUTURE | | | STANDBY GENERATOR. SHOW THE LOCATION OF ALL REGULATORS. | | | 6) SHT. C09 - CLEARLY SHOW THE LOCATION OF THE GAS | | | METER. THE PLAN SHOWS "PROPOSED 1 1/2 POLY GAS | | | SERVICE". THIS IS VAGUE. | | | | | | PLUMBING PLAN REVIEW | | | TIM LARGE | | | CHIEF PLUMBING INSPECTOR | | | 561-805-6692 | | | [email protected] | | | | | | | | | | | | |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
3 |
Status |
N |
Date |
2016-02-16 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2016-02-16 |
Time |
02:40 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2016-02-12 |
Time |
14:45 |
Sent To |
|
|
| Notes |
| 2016-02-12 14:45:23 | RESUB ROUTED TO TKLARGE |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2016-02-05 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2016-02-05 |
Time |
05:30 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2016-01-22 |
Time |
09:51 |
Sent To |
|
|
| Notes |
| 2016-01-25 09:51:37 | RESUB ROUTED TO ENGINEERING INBOX |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2015-12-03 |
|
|
Cont ID |
|
| Sent By |
lmarchan |
Date |
2015-12-03 |
Time |
16:04 |
Rev Time |
0.00 |
| Received By |
lmarchan |
Date |
2015-11-24 |
Time |
14:21 |
Sent To |
|
|
| Notes |
| 2015-11-24 14:22:02 | REVISION ROUTED TO TKLARGE |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
1 |
Status |
N |
Date |
2015-11-25 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2015-11-25 |
Time |
06:44 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2015-11-25 |
Time |
06:44 |
Sent To |
|
|
| Notes |
| 2015-11-25 06:44:56 | REVISION IS FOR GAS ONLY. |
|
|
|