Plan Review Details - Permit 15100868
Plan Review Stops For Permit 15100868
Review Stop B BUILDING (STRUCTURAL)
Rev No 4 Status P Date 2015-12-09 Cont ID  
Sent By tmoore Date 2015-12-09 Time 07:15 Rev Time 0.00
Received By tmoore Date 2015-12-09 Time 07:14 Sent To  
Notes
2015-12-09 07:15:19OK TO ISSUE. RECEIVED ALL NEEDED UTILITY RELEASES.

Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status F Date 2015-11-30 Cont ID  
Sent By tmoore Date 2015-11-30 Time 15:29 Rev Time 0.00
Received By tmoore Date 2015-11-30 Time 15:26 Sent To  
Notes
2015-11-30 15:28:59RECEIVED SILT FENCE LAYOUT BUT NOT MISSING FPL RELEASE
 OR SEWER LATERAL CAPPING INSPECTION AS DISCUSSED WITH
 TOM FREDERICO ON TWO OCCASIONS.
 MOVING BACK TO SMALL PLAN CABINET UNDER "F" FOR
 FREDERICO INC.

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2015-11-21 Cont ID  
Sent By tmoore Date 2015-11-21 Time 09:26 Rev Time 0.00
Received By tmoore Date 2015-11-21 Time 09:23 Sent To  
Notes
2015-11-21 09:26:08MISSING FPL RELEASE CONFIRMATION, SEWER LATERAL FINAL
 REQUESTED ON ISSUED PLUMBING PERMIT, AND N.O.C. MOVING
 TO SMALL PLAN CABINET UNDER "F" FOR FREDERICO.

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2015-11-03 Cont ID  
Sent By tmoore Date 2015-11-03 Time 10:07 Rev Time 0.00
Received By tmoore Date 2015-11-03 Time 10:01 Sent To ENG
Notes
2015-11-03 10:07:29MISSING,
 1) FPL RELEASE
 2 SEWER LATERAL CAPPING PERMIT PULLED AND #703 CALLED
 IN AND PASSED.
 3) WATER METER PULL CONFIRMATION OR BACKFLOW AND METER
 INSTALLED
 4) ENGINEERING REVIEW PASSED
 5) N.O.C.
 6) ALL REVIEW FEES PAID

Review Stop ENG ENGINEERING CSD
Rev No 1 Status P Date 2015-11-16 Cont ID  
Sent By mgonzale Date 2015-11-16 Time   Rev Time 1.00
Received By mgonzale Date 2015-11-16 Time   Sent To Z
Notes
2015-11-16 16:14:26PROVISOS:
  
 PROJECT WILL BE REQUIRED TO UTILIZE APPROVED BEST
 MANAGEMENT PRACTICES (BMP?S) FOR THE DETENTION AND
 TREATMENT OF STORMWATER RUNOFF.
  
 IN ACCORDANCE WITH STATE AND LOCAL STORMWATER
 MANAGEMENT POLICY, THE SITE DEVELOPER IS REQUIRED TO
 PREPARE "THE STORMWATER POLLUTION PREVENTION PLAN".
 THIS PLAN IS REQUIRED TO ADDRESS STORMWATER RELATED
 ISSUES SUCH AS DUST CONTROL, RUNOFF, AND EROSION
 CONTROL DURING THE CONSTRUCTION PHASE OF THE PROJECT.
 REFER TO HTTP://WPB.ORG/ENGINEERING/ENGINEERING-SERVICE
 S/ENGINEERING-STANDARDS/
 POLLUTION PREVENTION DETAILS.
  
 SHOULD YOU HAVE ANY QUESTIONS OR COMMENTS PLEASE
 CONTACT ME AT (561) 494-1085.
  
 MANUEL JULIAN GONZALEZ
 ENGINEERING PROJECT COORDINATOR
 PUBLIC WORKS DEPARTMENT
 401 CLEMATIS STREET, 4TH FLOOR
 WEST PALM BEACH, FL 33401
 (MAILING ADDRESS: P.O. BOX 3366, ZIP 33402)
 MAIN PHONE: (561) 822-1200
 DIRECT: (561) 494-1085
 FAX: (561) 494-1116
 EMAIL: [email protected]
 WWW.WPB.ORG/ENGINEERING
  
  

Review Stop HIST HISTORICAL
Rev No 1 Status P Date 2015-11-02 Cont ID  
Sent By fmittner Date 2015-11-02 Time 10:23 Rev Time 0.00
Received By fmittner Date 2015-11-02 Time 10:23 Sent To B
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2015-12-09 Cont ID  
Sent By tmoore Date 2015-12-09 Time 07:15 Rev Time 0.00
Received By tmoore Date 2015-12-09 Time 07:15 Sent To Z
Notes
***NONE***