| Plan Review Stops For Permit 15090725 |
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
P |
Date |
2015-09-17 |
|
|
Cont ID |
|
| Sent By |
albarran |
Date |
2015-09-17 |
Time |
13:56 |
Rev Time |
0.00 |
| Received By |
albarran |
Date |
2015-09-17 |
Time |
13:20 |
Sent To |
I |
|
| Notes |
| 2015-09-17 13:58:13 | THE SCOPE OF REVISION 2 IS TO DEFER THE ELECTRICAL WORK | | | FOR ELEVATORS 1 & 2 FOR A LATER DATE. |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2015-09-17 |
|
|
Cont ID |
|
| Sent By |
albarran |
Date |
2015-09-17 |
Time |
13:58 |
Rev Time |
0.00 |
| Received By |
albarran |
Date |
2015-09-17 |
Time |
10:55 |
Sent To |
|
|
| Notes |
| 2015-09-17 13:59:08 | 9/17/15 - REVISION 2 APPROVED. CONTRACTOR NOTIFIED VIA | | | EMAIL. SENT TO SMALL READY BIN "F". MA |
|
|
|