Plan Review Details - Permit 15080879
Plan Review Stops For Permit 15080879
Review Stop G GAS REVIEW
Rev No 3 Status P Date 2015-09-16 Cont ID  
Sent By tklarge Date 2015-09-16 Time 11:32 Rev Time 0.00
Received By tklarge Date 2015-09-16 Time 11:32 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 2 Status F Date 2015-09-15 Cont ID  
Sent By tklarge Date 2015-09-15 Time 05:54 Rev Time 0.00
Received By tklarge Date 2015-09-15 Time 03:55 Sent To  
Notes
2015-09-15 05:08:201) THE GAS LINE TO THE FIRE PIT IS SHOWN AS PE PIPE AND
 ALSO AS CSST. I CANNOT TELL ON THE DRAWING WHERE THE
 TRANSITION TAKES PLACE. CLARIFY.
 2) INDICATE ON THE PLANS THE SIZE OF THE CONDUIT SLEEVE
 AND THE TYPE OF PIPING AND THAT THE INSTALLATION
 COMPLIES WITH 2014 FBC-FUEL GAS SEC.404.14.1, 404.14.2,
 404.14.PLEASE NOTE: PIPING UNDERGROUND BENEATH
 BUILDINGS IS PROHIBITED UNLESS THERE IS NO OTHER WAY TO
 INSTALL THE PIPING. FGC SEC.404.14.
 3) SUBMIT MANUF. SPECS FOR THE GAS HOSE TO THE BBQ
 GRILL. THE HOSE SHALL BE LISTED FOR USE WITH LP GAS.
 4) SHOW THE SIZE OF THE LINE DOWNSTREAM OF THE PRESSURE
 REGULATOR FOR THE POOL HEATER.THE FUTURE LINE FOR THE
 POOL HEATER SHALL BE VALVED AND CAPPED.
 5) INDICATE THE SIZE AND TYPE OF PIPE FROM THE
 REGULATOR AT THE TANK TO THE REGULATOR FOR THE FIRE PIT
 & BBQ AND FROM THE TANK REGULATOR TO THE GENERATOR.

Review Stop G GAS REVIEW
Rev No 1 Status F Date 2015-08-27 Cont ID  
Sent By tklarge Date 2015-08-27 Time 13:34 Rev Time 0.00
Received By tklarge Date 2015-08-27 Time 13:03 Sent To  
Notes
2015-08-27 13:34:211) THE HIGH PRESSURE THAT WAS SUBMITTED IS FROM AN
 OUTDATED EDITION OF THE GAS CODE AND IS NOT
 ACCEPTABLE.SUBMIT A COPY OF A CURRENT SIZING TABLE FOR
 THE HIGH PRESSURE SIDE. WPB AMEND. TO FBC SEC. 107.2.1.
 2) SUBMIT 2 COPIES OF MANUFACTURER'S SPECIFICATION
 SHEETS FOR ALL GAS APPLIANCES. APPLIANCES SHALL BE
 LISTED AND LABELED PER THE 2014 FBC-R, SEC. G2404.3.
 3) REGULATORS INSTALLED ON THE EXTERIOR OF THE BUILDING
 SHALL BE APPROVED FOR OUTDOOR INSTALLATION. 2014 FBC-R
 SEC.G2421.1.
 4) SHOW THE LENGTH OF EACH SECTION OF PIPE FOR THE LOW
 PRESSURE SYSTEM FROM THE REGULATOR TO THE APPLIANCE AND
 THE TYPE OF PIPE.
 5) CLEARLY SHOW THE BTU LOAD OF EACH APPLIANCE. SOME OF
 THE VALUES ARE VERY HARD TO READ.
 6) THE TANK ANCHORING DETAIL FORM PLAN CITY STEEL CO.
 IS ILLEGIBLE. SUBMIT 2 CLEAR COPIES FOR REVIEW.
  
 PLUMBING PLAN REVIEW
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 561-805-6692
 [email protected]
  
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2015-09-15 Cont ID  
Sent By tklarge Date 2015-09-15 Time 05:54 Rev Time 0.00
Received By tklarge Date 2015-09-11 Time 09:34 Sent To  
Notes
2015-09-14 09:35:11RESUB ROUTED TO TKLARGE

Review Stop I INCOMING/PROCESSING
Rev No 1 Status   Date 2015-08-27 Cont ID  
Sent By tklarge Date 2015-08-27 Time 13:34 Rev Time 0.00
Received By tklarge Date 2015-08-24 Time 07:51 Sent To  
Notes
2015-08-25 07:51:51PLUMBING INBOX