| 2015-08-28 15:29:35 | 1ST REVIEW: FBC 2014 MECHANICAL |
| | PERMIT #15080803 |
| | 8/28/15 |
| | |
| | 1) SHEET M-1: PROVIDE DETAILS FOR THE O/A AIR DUCT AND |
| | CHILLED WATER PIPE INSULATIONS- TYPES, THICKNESSES, AND |
| | R-VALUES: REFER TO TABLE C403.2.7.1 AND C403.2.8 FBC-14 |
| | ENERGY CONSERVATION. |
| | 2) M-2 & M-17: THE FLORIDA BUILDING CODE FIFTH EDITION |
| | 2014 WENT INTO EFFECT ON JUNE 30, 2015. PLEASE UPDATE |
| | THE CODE REFERENCES ACCORDINGLY AND VERIFY THE DESIGN |
| | IS IN COMPLIANCE. |
| | 3) M-5- M-10: REVIEW THE NEW WORK SECTIONS AND NOTES. I |
| | AM FINDING MANY NOTES MISSING FROM THE DRAWINGS SUCH AS |
| | NOTE #1, 3, 5, 11 ETC. |
| | 4) M-12 & M21: A DUCT SMOKE DETECTOR IS REQUIRED IN THE |
| | RETURN AIR SYSTEM OF THE NEW OAU-1 PER SECTION 606.2.1 |
| | FBC-14 MECHANICAL. PLEASE NOTE THAT LEVEL 1 ALTERATIONS |
| | SHALL COMPLY WITH THE CURRRENT 2014 FLORIDA BUILDING |
| | CODES- REFER TO SECTION 702.4 FBC-14 EXISTING BUILDING |
| | CODE. |
| | 5) M-15: PROVIDE A SCHEDULE FOR THE PIPE HANGERS |
| | INDICATING THE REQUIRED SPACINGS PER PIPE DIAMETER, AND |
| | ANCHOR TYPES PER SUBSTRATE MATERIAL. |
| | 6) M-16: REFER TO THE SMACNA HVAC DUCT CONSTRUCTION |
| | STANDARDS- 2005, AND SMACNA FIBROUS GLASS DUCT |
| | CONSTRUCTION STANDARDS- 2010. PROVIDE HANGER AND |
| | SUPPORT DETAILS FOR BOTH METAL AND FIBROUS DUCTS. |
| | 7) THE CITY OF WPB CONSTRUCTION SERVICES AC CHANGE-OUT |
| | COMPLIANCE FORM: PROVIDE COPIES OF THE FORM IN |
| | DUPLICATE FOR THE AHU'S AND THE OAU-1. |
| | 8) COMMISSSIONING: REFER TO SECTION C408 FBC-14 ENERGY |
| | COMPLIANCE. PLEASE PROVIDE A COMMISSIONING PLAN IN |
| | ACCORDANCE WITH C408.2.1. REVIEW ALL SUB-SECTIONS THAT |
| | ARE APPLICABLE TO THE PROPOSED PROJECT INCLUDING |
| | SECTION C408.2.4.1 FOR FINAL INSPECTION APPROVAL. |
| | |
| | CHRISTOPHER L. COLE |