Plan Review Details - Permit 15080142
Plan Review Stops For Permit 15080142
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2015-08-18 Cont ID  
Sent By rmcdouga Date 2015-08-18 Time 18:28 Rev Time 0.00
Received By rmcdouga Date 2015-08-18 Time 18:07 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2015-08-18 Cont ID  
Sent By rmcdouga Date 2015-08-18 Time 18:28 Rev Time 0.00
Received By rmcdouga Date 2015-08-18 Time 18:07 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 1 Status N Date 2015-08-11 Cont ID  
Sent By tklarge Date 2015-08-11 Time 06:57 Rev Time 0.00
Received By tklarge Date 2015-08-11 Time 06:56 Sent To  
Notes
2015-08-11 06:57:51GAS PLAN REVIEW
 A GAS PLAN HAS NOT BEEN INCLUDED IN THIS SUBMITTAL
 PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN PERFORMED AT
 THIS TIME. A SEPARATE GAS PERMIT AND PLANS WILL BE
 REQUIRED FOR A CONTRACTOR TO PERFORM THE RELATED WORK.
 PROVIDE COMPLETE PLANS AND GAS RISER THAT REFLECTS THE
 ENTIRE SCOPE OF GAS WORK TO BE DONE. WPB AMEND. TO FBC
 SEC. 107.2.1
  

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2015-08-18 Cont ID  
Sent By rmcdouga Date 2015-08-18 Time 18:28 Rev Time 0.00
Received By rmcdouga Date 2015-08-05 Time 13:32 Sent To  
Notes
2015-08-05 13:32:49ROUTED TO ZONING

Review Stop P PLUMBING
Rev No 1 Status P Date 2015-08-11 Cont ID  
Sent By tklarge Date 2015-08-11 Time 06:56 Rev Time 0.00
Received By tklarge Date 2015-08-11 Time 05:43 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2015-08-07 Cont ID  
Sent By sgraham Date 2015-08-07 Time 12:09 Rev Time 0.00
Received By sgraham Date 2015-08-07 Time 12:09 Sent To B
Notes
***NONE***