| Plan Review Stops For Permit 15080068 |
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
P |
Date |
2015-08-27 |
|
|
Cont ID |
|
| Sent By |
albarran |
Date |
2015-08-27 |
Time |
17:10 |
Rev Time |
0.00 |
| Received By |
albarran |
Date |
2015-08-27 |
Time |
16:01 |
Sent To |
I |
|
| Notes |
| 2015-08-27 17:07:28 | IT APPEARS TO ME THAT ALL THE UNDERGROUND WILL BE | | | THROUGH THE ALREADY BURIED RACEWAYS. ALL I HAVE TO SAY | | | WITH RESPECT TO THAT, IS THAT ANY NEW UNDERGROUND | | | CONDUIT THAT IS PLACED IN THE GROUND SHALL BE | | | INSPECTED. THEREFORE, UNLESS YOU USE DIRECT BORING, AND | | | YOU MAKE PRIOR ARRANGEMENTS WITH THE ELECTRICAL | | | INSPECTOR, ALL TRENCHES SHALL REMAIN OPEN FOR | | | INSPECTION. NO SITE TUBES WILL BE ACCEPTED. | | | | | 2015-08-27 16:08:03 | THIS FILE WAS NOT REVIEWED BUT PUT BACK IN MY TO DO | | | PILE WAITING FOR A RESPONSE FROM BART TO STEVEN | | | KENNEDY'S EMAIL. |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2015-08-27 |
|
|
Cont ID |
|
| Sent By |
albarran |
Date |
2015-08-27 |
Time |
17:17 |
Rev Time |
0.00 |
| Received By |
albarran |
Date |
2015-08-04 |
Time |
10:20 |
Sent To |
|
|
| Notes |
| 2015-08-27 17:17:53 | 8/27/15 - PASSED ELECTRICAL REVIEW AS NOTED. CONTRACTOR | | | NOTIFIED VIA EMAIL. SENT TO SMALL READY BIN "S". MA | | 2015-08-04 10:20:37 | REVISION ROUTED TO SKENNEDY |
|
|
|