Plan Review Details - Permit 15071174
Plan Review Stops For Permit 15071174
Review Stop E ELECTRICAL
Rev No 2 Status P Date 2015-08-19 Cont ID  
Sent By albarran Date 2015-08-19 Time 11:21 Rev Time 0.00
Received By albarran Date 2015-08-19 Time 09:52 Sent To M
Notes
2015-08-19 11:22:04ALL PREVIOUSLY MADE ELECTRICAL COMMENTS HAVE BEEN
 ADDRESSED. ROUTED TO MECHANICAL.

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2015-08-10 Cont ID  
Sent By albarran Date 2015-08-10 Time 14:46 Rev Time 0.00
Received By albarran Date 2015-08-07 Time 11:27 Sent To I
Notes
2015-08-10 14:47:29PLEASE NOTE THAT I, MIKE ALBARRAN, ELECTRICAL PLANS
 EXAMINER HAVE COMPLETED THE REVIEW OF THE ABOVE
 MENTIONED JOB. BELOW ARE THE COMMENTS WITH REGARDS TO
 THE REQUIRED CORRECTIONS. THE FOLLOWING ITEMS SHALL BE
 CORRECTED AND THE PLANS RESUBMITTED FOR ANOTHER REVIEW.
  
 1. YOU SHALL SUBMIT A SERVICE RISER DIAGRAM SHOWING THE
 EXISTING SERVICE AND THE ADDITIONAL LOAD.
 2. YOU SHALL PROVIDE LOAD CALCS TO DETERMINE THE
 ACCEPTABILITY OF THE ADDITIONAL LOADS TO THE EXISTING
 SERVICE.
 3. YOU SHALL PROVIDE WIRING SCHEDULE FOR ALL THE NEW
 LOADS.
 4. A CIRCUIT DIRECTORY SHALL BE PROVIDED.
 5. THERE SHALL BE INDICATED ON THE PLANS THE REQUIRED
 SERVICE OUTLET WITHIN 25? OF EACH CONDENSING UNIT.
  
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT
 CORRECTED PAGES INTO TO SUBMITTAL AND LEAVE THE
 PREVIOUSLY REVIEWED SHEETS.
  
 IF YOU HAVE FURTHER QUESTIONS, PLEASE DON?T HESITATE TO
 CONTACT ME DIRECTLY.
  
 THANK YOU
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2015-08-19 Cont ID  
Sent By ccole Date 2015-08-19 Time 14:17 Rev Time 0.00
Received By ccole Date 2015-08-14 Time 07:57 Sent To  
Notes
2015-08-19 07:57:30RESUB ROUTED TO MALBARRAN'S DESK

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2015-08-10 Cont ID  
Sent By albarran Date 2015-08-10 Time 14:48 Rev Time 0.00
Received By albarran Date 2015-07-30 Time 09:10 Sent To  
Notes
2015-08-10 14:51:048/10/15 - FAILED ELECTRICAL REVIEW AS NOTED. CONTRACTOR
 NOTIFIED VIA EMAIL. SENT TO SMALL DENIED BIN "W". MA
2015-07-30 15:49:01ROUTED TO ELECTRICAL INBOX

Review Stop M MECHANICAL (A/C)
Rev No 3 Status P Date 2015-08-19 Cont ID  
Sent By ccole Date 2015-08-19 Time 12:09 Rev Time 0.00
Received By ccole Date 2015-08-19 Time 12:09 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2015-08-11 Cont ID  
Sent By ccole Date 2015-08-11 Time 09:45 Rev Time 0.00
Received By ccole Date 2015-08-11 Time 09:45 Sent To  
Notes
2015-08-11 09:50:218/11/15
 MECHANICAL PASSED WITH PROVISO FOR REQUIRED
 VENTILATION.
 PRIOR TO 1ST INSPECTION, THE ENGINEER OF RECORD SHALL
 PROVIDE A CALCULATION TO CERTIFY THAT THE AMOUNT OF
 AMMONIA REFRIGERANT IN POUNDS IN THE WET ADDITION DOES
 NOT EXCEED THE ALLOWABLE AMOUNT PER TABLE 1103.1 FBC-14
 MECHANICAL- 0.014 PER 1000CUBIC FT.
  
 1104.2 MACHINERY ROOM.
 EXCEPT AS PROVIDED IN SECTIONS 1104.2.1 AND 1104.2.2,
 ALL COMPONENTS CONTAINING THE REFRIGERANT SHALL BE
 LOCATED EITHER OUTDOORS OR IN A MACHINERY ROOM WHERE
 THE QUANTITY OF REFRIGERANT IN AN INDEPENDENT CIRCUIT
 OF A SYSTEM EXCEEDS THE AMOUNTS SHOWN IN TABLE 1103.1.
 FOR REFRIGERANT BLENDS NOT LISTED IN TABLE 1103.1, THE
 SAME REQUIREMENT SHALL APPLY WHEN THE AMOUNT FOR ANY
 BLEND COMPONENT EXCEEDS THAT INDICATED IN TABLE 1103.1
 FOR THAT COMPONENT. THIS REQUIREMENT SHALL ALSO APPLY
 WHEN THE COMBINED AMOUNT OF THE BLEND COMPONENTS
 EXCEEDS A LIMIT OF 69,100 PARTS PER MILLION (PPM) BY
 VOLUME. MACHINERY ROOMS REQUIRED BY THIS SECTION SHALL
 BE CONSTRUCTED AND MAINTAINED IN ACCORDANCE WITH
 SECTION 1105 FOR GROUP A1 AND B1 REFRIGERANTS AND IN
 ACCORDANCE WITH SECTIONS 1105 AND 1106 FOR GROUP A2,
 B2, A3 AND B3 REFRIGERANTS.
  
 1106.3 AMMONIA ROOM VENTILATION.
 VENTILATION SYSTEMS IN AMMONIA MACHINERY ROOMS SHALL BE
 OPERATED CONTINUOUSLY AT THE EMERGENCY VENTILATION RATE
 DETERMINED IN ACCORDANCE WITH SECTION 1105.6.3.2.
  
 PLEASE NOTE THAT A REVISION TO THIS PERMIT WILL BE
 REQUIRED FOR ANY MODIFICATIONS TO THE THE WET ADDITION
 OR EXISTING MACHINERY ROOM.
  
 CHRISTOPHER L. COLE
 MECHANICAL PLANS EXAMINER
 561-805-6719
 [email protected]
  
  

Review Stop M MECHANICAL (A/C)
Rev No 1 Status F Date 2015-08-05 Cont ID  
Sent By ccole Date 2015-08-05 Time 09:28 Rev Time 0.00
Received By ccole Date 2015-08-05 Time 09:27 Sent To  
Notes
2015-08-05 09:28:461ST REVIEW: FBC 2014 MECHANICAL
 PERMIT #15071174
 8/4/15
  
 1) VENTILATION FOR THE REFRIGERATION IN THE WET
 BUILDING ADDITION IS REQUIRED IN ACCORDANCE WITH
 SECTIONS 1104 & 1105 FBC-14 MECHANICAL. THE PLANS DO
 NOT INDICATE ANY EXISTING OR PROPOSED VENTILATION
 SYSTEM, HOWEVER THE NOTE ON SHEET R1.1 INDICATES A
 PERMIT HAS BEEN ISSUED FOR THAT PORTION OF THE PROJECT.
 I HAVE NOT BEEN ABLE TO LOCATE ANY DRAWINGS OR
 CALCULATIONS FOR THE SYSTEM UNDER ANY ISSUED PERMIT.
 PLEASE PROVIDE THE PERMIT NUMBER THE DRAWINGS WERE
 SUBMITTED AND APPROVED UNDER.
  
 CHRISTOPHER L. COLE
 MECHANICAL PLANS EXAMINER
 561-805-6719
 [email protected]
  
  