Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2015-08-20 Cont ID  
Sent By skennedy Date 2015-08-20 Time 11:24 Rev Time 0.00
Received By skennedy Date 2015-08-20 Time 11:24 Sent To Z
Notes
2015-08-20 11:26:382ND REVIEW: FBC 2014 5TH ED.
  
 PROVIDE THE FOLLOWING AS A SUBMITTAL PRIOR TO
 INSTALLATION OF THE SKY PANELS TO THE SIGN STRUCTURE:
  
 ADDITIONAL DETAIL REGARDING THE ASSEMBLY AND WIND
 RESISTANCE CAPABILITY OF THE SKY PANEL SIGN. PER
 SECTION 6.0 CRITICAL FEATURES ON PAGE 17 OF 33 OF THE
 LISTING INFORMATION PROVIDED THE FIELD ASSEMBLY OF THIS
 SECTIONAL SIGN IS SUBJECT TO THE ACCEPTANCE OF THE
 LOCAL INSPECTION AUTHORITY.
  
 PROVIDE THE MANUFACTURERS INSTALLATION AND ASSEMBLY
 INSTRUCTIONS, PLEASE PROVIDE EVIDENCE THAT THE ENGINEER
 OF RECORD, CHRISTOPHER B. LAFORTE, P.E. HAS REVIEWED
 THE ASSEMBLY AND INSTALLATION INSTRUCTIONS FOR
 CONSISTENCY WITH HIS DESIGN AND THE THE SIGN PANEL HAS
 ADEQUATE WIND RESISTANCE CAPABILITY ITSELF.
  
 ADVISORY COMMENT:
  
 UPON INSTALLATION, A THIRD PARTY SHALL CERTIFY ALL
 BOLTED CONNECTIONS DEPICTED IN THE PLAN.
  
 A SEPARATE PERMIT IS REQUIRED FOR PLUMBING LINE
 RELOCATE AND FOR FLAG POLES RELOCATE.
  
 STEVEN KENNEDY, CBO
 CHIEF PLANS EXAMINER
 (561) 805-6710
 [email protected]
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2015-07-29 Cont ID  
Sent By skennedy Date 2015-07-29 Time 11:27 Rev Time 0.00
Received By skennedy Date 2015-07-29 Time 08:45 Sent To  
Notes
2015-07-29 08:51:301ST REVIEW: FBC 2014 5TH ED.
  
 DENIED AS FOLLOWS:
  
 PROVIDE EVIDENCE THAT THE SOIL ENGINEER HAS REVIEWED
 THE FINAL DESIGN PER HIS REQUIREMENT ON PAGE 3 IN THE
 GEOTECHNICAL STUDY REPORT.
  
 PROVIDE ADDITIONAL DETAIL REGARDING THE ASSEMBLY AND
 WIND RESISTANCE CAPABILITY OF THE SKY PANEL SIGN. PER
 SECTION 6.0 CRITICAL FEATURES ON PAGE 17 OF 33 OF THE
 LISTING INFORMATION PROVIDED THE FIELD ASSEMBLY OF THIS
 SECTIONAL SIGN IS SUBJECT TO THE ACCEPTANCE OF THE
 LOCAL INSPECTION AUTHORITY.
  
 PROVIDE THE MANUFACTURERS INSTALLATION AND ASSEMBLY
 INSTRUCTIONS, PLEASE PROVIDE EVIDENCE THAT THE ENGINEER
 OF RECORD, CHRISTOPHER B. LAFORTE, P.E. HAS REVIEWED
 THE ASSEMBLY AND INSTALLATION INSTRUCTIONS FOR
 CONSISTENCY WITH HIS DESIGN AND THE THE SIGN PANEL HAS
 ADEQUATE WIND RESISTANCE CAPABILITY ITSELF.
  
 A DRAWING FROM ADTI MEDIA INC. WAS PROVIDED. PLEASE
 HAVE CHRISTOPHER B. LAFORTE, P.E. REVIEW NOTES 1-16 ON
 THAT DRAWING AND PROVIDE EVIDENCE OR REVIEW AND
 ACCEPTANCE OF THAT DRAWING OR ADDITIONAL DRAWINGS AND
 SPECIFICATIONS AS HE MAY REQUIRE.
  
  
 ADVISORY COMMENT:
  
 UPON INSTALLATION, A THIRD PARTY SHALL CERTIFY ALL
 BOLTED CONNECTIONS DEPICTED IN THE PLAN.
  
 A SEPARATE PERMIT IS REQUIRED FOR PLUMBING LINE
 RELOCATE AND FOR FLAG POLES RELOCATE.
  
 STEVEN KENNEDY, CBO
 CHIEF PLANS EXAMINER
 (561) 805-6710
 [email protected]
  

Review Stop E ELECTRICAL
Rev No 3 Status P Date 2015-08-21 Cont ID  
Sent By skennedy Date 2015-08-21 Time 08:31 Rev Time 0.00
Received By skennedy Date 2015-08-21 Time 08:31 Sent To Z
Notes
2015-08-21 08:35:372ND REVIEW: FBC 2014 5TH ED. NEC 2011
  
 THE ELECTRICAL FEED TO THE SIGN IS BY SEPARATE. WHEN
 DETAILS ARE DEVELOPED FOR THE CONNECTION THERETO BY THE
 SISGN CONTRACTOR, PLASE SUBMIT FOR REVIEW.
  
  
 STEVEN KENNEDY, CBO
 CHIEF PLANS EXAMINER
 (561) 805-6710
 [email protected]
  

Review Stop E ELECTRICAL
Rev No 2 Status N Date 2015-08-18 Cont ID  
Sent By albarran Date 2015-08-18 Time 19:16 Rev Time 0.00
Received By albarran Date   Time   Sent To  
Notes
2015-08-18 19:17:22SEE ELECTRICAL PERMIT #15080170

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2015-07-29 Cont ID  
Sent By albarran Date 2015-07-29 Time 13:09 Rev Time 0.00
Received By albarran Date 2015-07-29 Time 11:05 Sent To Z
Notes
2015-07-29 13:14:11PLEASE NOTE THAT I, MIKE ALBARRAN, ELECTRICAL PLANS
 EXAMINER HAVE COMPLETED THE REVIEW OF THE ABOVE
 MENTIONED JOB. BELOW ARE THE COMMENTS WITH REGARDS TO
 THE REQUIRED CORRECTIONS. THE FOLLOWING ITEMS SHALL BE
 CORRECTED AND THE PLANS RESUBMITTED FOR ANOTHER REVIEW.
  
 1. YOU SHALL PROVIDE A COMPLETE RISER DIAGRAM
 INDICATING THE LOCATION OF THE POWER SOURCE.
 2. YOU SHALL INDICATE A PANEL SCHEDULE FOR THE SOURCE
 POWER.
 3. REGARDLESS OF WHAT IT IS USED FOR, THIS IS
 CONSIDERED A SIGN AND SHALL COMPLY WITH ALL THE
 REQUIREMENTS OF ARTICLE 600 OF THE 2011 EDITION OF THE
 NEC.
 4. ON THE SITE PLAN INDICATE THE LOCATION OF BOTH THE
 SOURCE OF POWER AN WELL AS THE SIGN. AND THE WIRING
 METHOD TO GET FROM POINT A TO B.
 5. IN ADDITION TO THE REQUIREMENTS OF THE NEC,
 FBC-ENERGY CONSERVATION HAS SPECIFIC REQUIREMENTS WHICH
 SHALL BE MET AS WELL.
  
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT
 CORRECTED PAGES INTO TO SUBMITTAL AND LEAVE THE
 PREVIOUSLY REVIEWED SHEETS.
  
 IF YOU HAVE FURTHER QUESTIONS, PLEASE DON?T HESITATE TO
 CONTACT ME DIRECTLY.
  

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2015-08-24 Cont ID  
Sent By skennedy Date 2015-08-24 Time 08:18 Rev Time 0.00
Received By skennedy Date 2015-08-20 Time 11:24 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2015-08-02 Cont ID  
Sent By skennedy Date 2015-08-02 Time 09:55 Rev Time 0.00
Received By skennedy Date 2015-07-31 Time 10:01 Sent To  
Notes
2015-08-02 10:00:41A PARTIAL RE-SUB OF A SECOND SOIL REPORT ONLY WAS
 SUBMITTED. THE FIRST REVIIEW CYCLE IS COMPLETE AND THIS
 RE-SUBMITTAL DOES NOT ANSWER THE 1ST CYCLE DENIED
 COMMENTS SUBSTANTIALLY ENOUGH TO JUSTIFY A SECOND ROUND
 OF REVIEWS.
2015-07-31 10:01:22PARTIAL RESUB ROUTED TO SKENNEDY

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2015-07-31 Cont ID  
Sent By lmarchan Date 2015-07-30 Time 10:00 Rev Time 0.00
Received By lmarchan Date 2015-07-29 Time 08:45 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 2 Status P Date 2015-08-21 Cont ID  
Sent By Hansen Date 2015-08-21 Time   Rev Time 0.00
Received By   Date 2015-08-21 Time   Sent To B
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status F Date 2015-08-03 Cont ID  
Sent By ahansen Date 2015-07-30 Time 08:57 Rev Time 0.00
Received By ahansen Date 2015-07-30 Time 08:56 Sent To  
Notes
2015-07-30 13:54:15THE APPROVAL LETTER FOR THE OXBRIDGE ACADEMY SITE PLAN
 AMENDMENT INCLUDES A CONDITION OF APPROVAL INDICATING
 THAT THE PROPOSED SCOREBOARD "SHALL NOT HAVE TEXT ON
 THE BACKFACE". FROM THE BUILDING PLANS PROVIDED WITH
 THE APPLICATION IT IS NOT POSSIBLE TO DETERMINE WHETHER
 THE PROPOSED SCOREBOARD COMPLIES WITH THIS CONDITION OF
 APPROVAL. PLEASE PROVIDE WITH THE BUILDING PERMIT
 APPLICATION AN ELEVATION RENDERING OF THE SCOREBOARD
 WITH ITS BACKFACE TO CONFIRM WHETHER IT MEETS THE
 CONDITION OF APPROVAL REFERENCED ABOVE.
  
 ALEX HANSEN, AICP
 SENIOR PLANNER
 CITY OF WEST PALM BEACH
 [email protected]
 (561) 822-1463


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved