| 2015-09-09 09:12:12 | 9/9/15 MET WITH JIM PAINE TO GO OVER COMMENTS. TOLD HIM |
| | ALL THE COMMENTS BELOW NEED TO BE ADDRESSED. REVISED |
| | PLANS ARE REQUIRED. JG. |
| | |
| | |
| | |
| | |
| | **** BUILDING REVIEW COMMENTS FOR SUBMITTAL ADDRESSING |
| | PROVISO COMMENTS: |
| | |
| | 1- REVISE BUILDING EXPOSURE AND ALL DESIGN PRESSURES. |
| | REVISE PLANS ACCORDINGLY. CLEARLY MARK THE DESIGN |
| | PRESSURES FOR ALL WINDOWS AND DOORS ON PLANS. |
| | |
| | 2- PROVIDE COMPLETE DETAILS & SPECIFICATIONS FOR THE |
| | OPENING PROTECTION OF WINDOW LOCATED BETWEEN GARAGE AND |
| | OFFICE. SEC. R302.5. (ACCORDING TO ARCHITECT, IT WILL |
| | BE SUBMITTED LATER). |
| | |
| | 3- PROVIDE PRODUCT APPROVAL (2 COPIES) FOR: |
| | |
| | A) CUSTOM MADE MADE ENTRY DOOR ASSEMBLY AS SPECIFIED ON |
| | THE DOOR SCHEDULE (3-4" X 8'-0"). THERMA-TRU FLORIDA |
| | PRODUCT APPROVAL FL5891-R3 DOESN'T COVER THIS SIZE. |
| | ALSO, THE ENTRY DOOR ASSEMBLY SHOWS A SINGLE DOOR WITH |
| | TWO SIDELITES. PROVIDE PRODUCT APPROVAL FOR ENTIRE |
| | ASSEMBLY. IF THERE IS NOT PRODUCT APPROVAL, THEN |
| | PROVIDE COMPLETE ENGINEER PACKAGE FOR BUILDING OFFICIAL |
| | REVIEW/APPROVAL. CONTACT ROBERT BROWN (BUILDING |
| | OFFICIAL) AT [email protected]. |
| | |
| | B) FIXED WINDOW SIZE SPECIFIED FOR WINDOW "F" ON THE |
| | WINDOW SCHEDULE. NOA 11-1031.06 SUBMITTED DOESN'T COVER |
| | THAT SIZE. ( NOA 11-1031.06 DOESN'T COVER SIZE |
| | SPECIFIED ON THE WINDOW SCHEDULE (53" X 96"). |
| | |
| | C) OUTSWING GLAZED DOOR WITH SIDELITES: NEED TO PROVIDE |
| | PRODUCT APPROVAL THAT COVERS SIZE FOR DOOR #4. (NOA |
| | 13-0226.06 DOESN'T COVER SIZE SPECIFIED ON THE DOOR |
| | SCHEDULE (3'-4" X 8'-0"). |
| | |
| | D) SLIDING GLASS DOORS WITH 3 PANELS SIZE AS SPECIFIED |
| | FOR DOOR #3. (REVISE PLANS AND DOOR SCHEDULE TO SHOW 4 |
| | PANEL DOOR AS SPECIFIED ON THE LETTER SUBMITTED). |
| | |
| | E) PRECAST LINTELS AS SPECIFIED ON PLANS. NOA |
| | 13-0321.07 SUBMITTED IS FOR 4", 6" & 12" LINTELS. |
| | (ACCORDING TO ARCHITECT IT WILL BE SUBMITTED LATER). |
| | |
| | 4- DESIGNER OF RECORD TO APPROVE ALL PRODUCT APPROVALS. |
| | |
| | 5- GEO-TECHNICAL ENGINEERING REPORT SUBMITTED NEED THE |
| | ENGINEER'S ORIGINAL SEAL AND SIGNATURE AS REQUIRED BY |
| | CHAPTER 471 F.S. (ACCORDING TO ARCHITECT, IT WILL BE |
| | SUBMITTED LATER). |
| | |
| | 6- OWES $155.50 REVISION FEES FOR THIS SUBMITTAL. |
| | |
| | NOTE: FLOOD ZONE A5. ELEVATION CERTIFICATES WILL BE |
| | REQUIRED DURING CONSTRUCTION. |
| | |
| | IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT |
| | JULIO GOMEZ |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | DEVELOPMENT SERVICES DEPARTMENT |
| | (561)805-6712 |
| | [email protected] |