| 2015-07-31 17:06:57 | 1ST REVIEW: FBC 2014 MECHANICAL |
| | |
| | 1) SHEET M-3, HOOD SCHEDULE: LIST THE MAKE-UP AIR DATA |
| | FOR GH-1 AND GH-2. REFER TO SECTION 508.1 (MAKEUP AIR) |
| | AND 508.1.1 (MAKEUP AIR TEMPERATURE) FBC-14 MECHANICAL |
| | 508.1 MAKEUP AIR. |
| | MAKEUP AIR SHALL BE SUPPLIED DURING THE OPERATION OF |
| | COMMERCIAL KITCHEN EXHAUST SYSTEMS THAT ARE PROVIDED |
| | FOR COMMERCIAL COOKING APPLIANCES. THE AMOUNT OF MAKEUP |
| | AIR SUPPLIED TO THE BUILDING FROM ALL SOURCES SHALL BE |
| | APPROXIMATELY EQUAL TO THE AMOUNT OF EXHAUST AIR FOR |
| | ALL EXHAUST SYSTEMS FOR THE BUILDING. THE MAKEUP AIR |
| | SHALL NOT REDUCE THE EFFECTIVENESS OF THE EXHAUST |
| | SYSTEM. MAKEUP AIR SHALL BE PROVIDED BY GRAVITY OR |
| | MECHANICAL MEANS OR BOTH- PLEASE PROVIDE CALCULATIONS |
| | AND LIST THE DATA TO VERIFY COMPLIANCE WITH THIS |
| | SECTION. |
| | 508.1.1 MAKEUP AIR TEMPERATURE. |
| | THE TEMPERATURE DIFFERENTIAL BETWEEN MAKEUP AIR AND THE |
| | AIR IN THE CONDITIONED SPACE SHALL NOT EXCEED 10 |
| | DEGREES F (6 DEGREES C) EXCEPT WHERE THE ADDED HEATING |
| | AND COOLING LOADS OF THE MAKEUP AIR DO NOT EXCEED THE |
| | CAPACITY OF THE HVAC SYSTEM- CLARIFY HOW THE SYSTEM |
| | SHOWN ON THE PLAN IS MEETING COMPLIANCE. |
| | 2) PROVIDE THE WIND LOAD DESIGN CRITERIA AND ENGINEERED |
| | DETAILS FOR INSTALLATION OF THE GREENHECK ROOF FANS AND |
| | FAN CURBS- PLEASE NOTE THAT THE DETAILS ON SHEET M-2 |
| | REFERENCE STRUCTURAL DRAWINGS THAT HAVE NOT BEEN |
| | SUBMITTED WITH THE PLAN SETS. |
| | 3) INDICATE COMPLIANCE WITH SECTION 507.9 EXCEPTION |
| | (STAINLESS STEEL HOOD BACKING SHALL EXTEND NOT LESS |
| | THAN 18 INCHES IN ALL DIRECTIONS FROM THE HOOD). |
| | 4) THE SUBMITTED PLAN SHEETS WERE NOT BOUND TOGETHER- |
| | PLEASE RE-SUBMUIT PLANS THAT ARE BOUND TOGETHER- |
| | SECTION 107 WPB AMENDMENTS TO THE FBC-14 BUILDING CODE. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |
| | [email protected] |
| | |
| | |
| | |