Plan Review Details - Permit 15051308
Plan Review Stops For Permit 15051308
Review Stop E ELECTRICAL
Rev No 2 Status P Date 2015-07-01 Cont ID  
Sent By ccole Date 2015-07-07 Time 11:45 Rev Time 0.00
Received By albarran Date 2015-07-01 Time 14:08 Sent To I
Notes
2015-07-01 14:41:59COMPLIANCE WITH ALL REQUIREMENTS OF THE FBC-R & NEC
 2008, SPECIALLY 210.63

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2015-06-09 Cont ID  
Sent By albarran Date 2015-06-09 Time 20:18 Rev Time 0.00
Received By albarran Date 2015-06-09 Time 20:18 Sent To I
Notes
2015-06-09 20:19:44CONDITIONING A PREVIOUSLY UNCONDITIONED SPACE CREATES A
 HABITABLE ROOM AND THEREFORE HAS FURTHER REQUIREMENTS.

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2015-07-01 Cont ID  
Sent By albarran Date 2015-07-01 Time 14:42 Rev Time 0.00
Received By albarran Date 2015-06-30 Time 15:35 Sent To  
Notes
2015-07-01 14:44:467/1/15 - PASSED ELECTRICAL REVIEW BUT FAILED
 MECHANICAL. CONTRACTOR NOTIFIED VIA EMAIL. SENT TO
 SMALL DENIED BIN "S". MA

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2015-06-09 Cont ID  
Sent By albarran Date 2015-06-09 Time 20:24 Rev Time 0.00
Received By albarran Date   Time   Sent To  
Notes
2015-06-09 20:25:37CONTRACTOR NOTIFIED VIA EMAIL. SENT TO SMALL DENIED BIN
 "S"
2015-06-04 11:50:02ROUTED TO ELECTRICAL
2015-05-29 13:38:01ROUTED TO MECHANICAL LESS THAN $5000

Review Stop M MECHANICAL (A/C)
Rev No 2 Status F Date 2015-07-01 Cont ID  
Sent By ccole Date 2015-07-01 Time 08:49 Rev Time 0.00
Received By ccole Date 2015-07-01 Time 08:49 Sent To  
Notes
2015-07-01 08:50:582ND MECHANICAL REVIEW FBC MECHANICAL 2010
  
 1) THE PREVIOUS REVIEW COMMENTS #1, 2, AND 4 HAVE NOT
 BEEN ADDRESSED. PLEASE REVIEW AND SUBMIT THE REQUIRED
 DOCUMENTS, PLANS AND DETAILS.
  
 CHRISTOPHER L. COLE
 MECHANICAL PLANS EXAMINER
 561-805-6719
 [email protected]
  

Review Stop M MECHANICAL (A/C)
Rev No 1 Status F Date 2015-07-07 Cont ID  
Sent By ccole Date 2015-06-05 Time 11:44 Rev Time 0.00
Received By ccole Date 2015-06-04 Time 11:04 Sent To E
Notes
2015-06-04 11:46:241ST REVIEW: FBC 2010 MECHANICAL
  
 1) THE INSTALLATION OF A NEW AC SYSTEM TO CONDITION THE
 PREVIOUSLY UNCONDITIONED GARAGE, RESULTS WITH THE
 GARAGE NOW BEING CLASSIFIED AS AN ADDITION- SEE TABLE
 101.4.1 AND SECTION 202 (DEFINITIONS) FBC-10 ENERGY
 CONSERVATION.
 FULL COMPLIANCE AS A HABITABLE SPACE IS REQUIRED IN
 ACCORDANCE WITH BOTH THE FBC-10 RESIDENTIAL, AND
 CHAPTER 4 OF THE FBC-10 ENERGY. PROVIDE PLANS AND
 SPECIFICATIONS, AND SUBMIT EITHER ENERGY EFFICIENCY
 FORM 402-2010 OR FORM 405-2010. THE NEW PLAN SHALL
 INDICATE THE PROPOSED USE OF THE GARAGE- PLEASE NOTE
 IMPACT FEES MAY APPLY.
 2) AS THE PERRMIT APPLICATION INDICATES THIS IS A NEW
 SYSTEM, PLEASE DISCARD THE AC REPLACEMENT FORM: IT IS
 NOT VALID FOR THIS PROJECT.
 3) PROVIDE AC LOAD CALCULATIONS FOR THE NEW SYSTEM IN
 ACCORDANCE W ACCA MANUAL J- SECTION 403.6.1 FBC-10
 ENERGY.
 4) PROVIDE ON THE NEW AC PLAN THE FOLLOWING: A) THE
 LOCATIONS OF THE AIR HANDLER AND CONDENSER. (SHOW THE
 DISCONNECT LOCATIONS FOR EACH AND PROVIDE ELECTRICAL
 PLANS.) B) CONDENSATE DISPOSAL DETAILS. C) CONDENSER
 PAD AND ANCHORING DETAILS- SEE SECTION M1307.2.1 FBC-10
 RES.
  
 CHRISTOPHER COLE
 MECHANICAL PLANS EXAMINER
 561-805-6719
 [email protected]
  