| Plan Review Stops For Permit 15040794 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
3 |
Status |
P |
Date |
2015-07-21 |
|
|
Cont ID |
|
| Sent By |
skennedy |
Date |
2015-07-21 |
Time |
14:29 |
Rev Time |
0.00 |
| Received By |
skennedy |
Date |
2015-07-21 |
Time |
14:29 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
2 |
Status |
P |
Date |
2015-06-17 |
|
|
Cont ID |
|
| Sent By |
mmanhong |
Date |
2015-06-17 |
Time |
16:22 |
Rev Time |
0.00 |
| Received By |
mmanhong |
Date |
2015-06-17 |
Time |
16:22 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
F |
Date |
2015-06-17 |
|
|
Cont ID |
|
| Sent By |
mmanhong |
Date |
2015-06-17 |
Time |
16:17 |
Rev Time |
0.00 |
| Received By |
mmanhong |
Date |
2015-06-17 |
Time |
16:17 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
5 |
Status |
P |
Date |
2015-07-13 |
|
|
Cont ID |
|
| Sent By |
albarran |
Date |
2015-07-13 |
Time |
12:33 |
Rev Time |
0.00 |
| Received By |
albarran |
Date |
2015-07-13 |
Time |
12:04 |
Sent To |
B |
|
| Notes |
| 2015-07-13 12:36:01 | BECAUSE A NEW SET OF DRAWINGS HAS BEEN SUBMITTED, THIS | | | HAS TO GO BY EVERY DISCIPLINE FOR RE-STAMP. |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
4 |
Status |
P |
Date |
2015-06-26 |
|
|
Cont ID |
|
| Sent By |
albarran |
Date |
2015-06-26 |
Time |
12:02 |
Rev Time |
0.00 |
| Received By |
albarran |
Date |
2015-06-26 |
Time |
11:57 |
Sent To |
|
|
| Notes |
| 2015-06-26 12:02:45 | ELECTRICAL PROVISO: | | | IN AN EFFORT TO EXPEDITE THE CONTRUCTION OF THIS | | | PROJECT, THE PERMIT WAS ISSUED PENDING AN ELECTRICAL | | | PERMIT. A REVISION TO THESE DRAWINGS, ADDRESSING ALL | | | ELECTRICAL REQUIREMENTS PREVIOUSLY STATED TO BE | | | SUBMITTED AT THE TIME OF ELECTRICAL PERMIT APPLICATION. | | | |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
3 |
Status |
F |
Date |
2015-06-25 |
|
|
Cont ID |
|
| Sent By |
albarran |
Date |
2015-06-25 |
Time |
16:47 |
Rev Time |
0.00 |
| Received By |
albarran |
Date |
2015-06-25 |
Time |
16:00 |
Sent To |
P |
|
| Notes |
| 2015-06-25 16:47:54 | PLEASE NOTE THAT I, MIKE ALBARRAN, ELECTRICAL PLANS | | | EXAMINER HAVE COMPLETED THE REVIEW OF THE ABOVE | | | MENTIONED JOB. BELOW ARE THE COMMENTS WITH REGARDS TO | | | THE CORRECTIONS NOTED. | | | | | | THE FOLLOWING ITEMS SHALL BE CORRECTED AND THE PLANS | | | RESUBMITTED FOR A SECOND REVIEW: | | | | | | 1. AN ELECTRICAL PERMIT SHALL BE REQUIRED FOR THIS | | | FOUNTAIN. | | | 2. AS INDICATED IN NEC 680.50, THIS FOUNTAIN SHARES | | | WATER W/THE POOL. THEREFORE ALL REQUIREMENTS FOR A | | | PERMANENT POOL SHALL APPLY THUS REQUIRING AN | | | EQUIPOTENTIAL BOND AROUND THE FOUNTAIN MEETING THE | | | REQUIREMENTS OF 680.26. | | | 3. THE ELECTRICAL DIAGRAM OF PAGE 2 OF 2 SHALL BE | | | AMENDED TO INDICATE THE EXACT PANEL WHERE FOUNTAIN | | | CONTROL PANEL IS BEING SERVED FROM, FURTHERMORE AS | | | INDICATED IN NEC 230.70 A PLAQUE INDICATING THE | | | LOCATION OF SUCH DISCONNECT SHALL BE PLACED ON THAT | | | SOURCE. | | | 4. INDICATE ON FLOOR OR SITE PLAN THE LOCATION OF THE | | | GENERAL PURPOSE RECEPTACLE SHOWN ON THE RISER. IT SHALL | | | COMPLY W/NEC 210.8, 406.8 & 680.58 | | | 5. PROVIDE PANEL SCHEDULE AND LOAD CALCS FOR THE | | | CONTROL PANEL | | | 6. THIS IS AN OUTDOOR FOUNTAIN, PROVIDE CUT SHEETS ON | | | LUMINARIES. CONFIRM COMPLIANCE W/NEC 680.23, 680.51 & | | | W/FBC-E ?505. | | | | | | ALL THIS CAN BE ACCOMPLISHED WITH IDENTIFYING NOTES ON | | | THE DRAWINGS. YOU DON?T HAVE TO DRAW THE ENTIRE RISER | | | DIAGRAM ALL YOU DO HAVE TO INCLUDE A RISER DIAGRAM | | | SHOWING THE POWER SOURCE FOR THE CONTROL PANEL. | | | INDICATE ITS LOCATION AND ADD THE NOTES INDICATED | | | ABOVE. | | | | | | IF YOU HAVE ANY QUESTIONS, PLEASE DO NOT HESITATE TO | | | CONTACT ME. | | | | | | RESPECTFULLY SUBMITTED, | | | | | | MIKE ALBARRAN | | | | | | |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
2 |
Status |
F |
Date |
2015-06-18 |
|
|
Cont ID |
|
| Sent By |
albarran |
Date |
2015-06-18 |
Time |
10:23 |
Rev Time |
0.00 |
| Received By |
albarran |
Date |
2015-06-18 |
Time |
09:54 |
Sent To |
P |
|
| Notes |
| 2015-06-18 10:50:12 | THE SECOND REVIEW FAILED DUE TO FAILURE TO PROVIDE THE | | | PREVIOUSLY REQUESTED ITEMS AS INDICATED BELOW FOR | | | CLARITY: | | | 1. FBC- 107.3.5.3 ? ELECTRIC SERVICE RISER WITH WIRE | | | SIZES, CONDUIT DETAIL AND GROUNDING DETAIL. COMPLETE | | | LOAD CALCULATIONS, PANEL SCHEDULES AND SHOW CIRCUITS ON | | | FLOOR PLAN. WHICH WAS INITIALLY REQUESTED WITH | | | REFERENCE TO NEC 215.5 | | | 2. NEC 230.70 - YOU SHALL INDICATE THE LOCATION OF THE | | | DISCONNECTING MEANS FOR THIS PANEL | | | 3. NEC 225.34(A) - THE DISCONNECT SHALL BE LABELED TO | | | INDICATE LOAD SERVED. | | | 4. NEC 680.22 - THE CIRCULATING PUMPS SHALL BE | | | PROTECTED WITH A GFI CIRCUIT. | | | | | | YOU CAN VIEW ANY OTHER COMMENTS BY SELECTING THE PLAN | | | REVIEWS TAB AT: HTTP://ONESTOPSHOP.WPBGOV.COM/EGOVPLUS/ | | | PERMIT/PERM_STATUS.ASPX . | | | | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | | RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT | | | CORRECTED PAGES INTO TO SUBMITTAL AND LEAVE THE | | | PREVIOUSLY REVIEWED SHEETS. | | | | | | IF YOU HAVE FURTHER QUESTIONS, PLEASE DON?T HESITATE TO | | | CONTACT ME DIRECTLY. | | | | | | THANK YOU, | | | |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
F |
Date |
2015-05-04 |
|
|
Cont ID |
|
| Sent By |
rlecky |
Date |
2015-05-04 |
Time |
11:45 |
Rev Time |
0.00 |
| Received By |
rlecky |
Date |
2015-05-04 |
Time |
11:36 |
Sent To |
|
|
| Notes |
| 2015-05-04 11:46:07 | 15040794 | | | 600 OKEECHOBEE BLVD. | | | COMMERCIAL FOUNTAIN | | | | | | PLEASE REVISE THE PLANS IN RESPONSE TO THE FOLLOWING | | | REVIEW COMMENTS | | | | | | PROVIDE FEEDER DETAILS FOR THE NEW ELECTRICAL | | | PANELBOARD FOR THE FOUNTAIN. NEC 215.5 | | | | | | VERIFY THAT ALL FEEDERS FROM THE ELECTRICAL SERVICE | | | SOURCE INCLUDE A FULL SIZE INSULATED COPPER EQUIPMENT | | | GROUNDING CONDUCTOR SIZED IN ACCORDANCE WITH NEC | | | 250.22, 680.21, 680.25 | | | | | | SHOW THE LOCATION AND SAFETY CLEARANCES REQUIRED FOR | | | THE NEW PANEL BOARD SERVING THE FOUNTAIN EQUIPMENT. NEC | | | 110.26 | | | | | | | | | ROBERT LECKY | | | ELECTRICAL PLANS REVIEW | | | | | | | | | |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
5 |
Status |
N |
Date |
2015-07-21 |
|
|
Cont ID |
|
| Sent By |
skennedy |
Date |
2015-07-21 |
Time |
14:29 |
Rev Time |
0.00 |
| Received By |
skennedy |
Date |
2015-07-02 |
Time |
14:51 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
4 |
Status |
N |
Date |
2015-07-01 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2015-07-01 |
Time |
05:20 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2015-07-01 |
Time |
05:20 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
3 |
Status |
N |
Date |
2015-06-26 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2015-06-26 |
Time |
06:55 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2015-06-25 |
Time |
15:10 |
Sent To |
|
|
| Notes |
| 2015-06-25 15:11:14 | SENT TO MALBARRAN. |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2015-06-25 |
|
|
Cont ID |
|
| Sent By |
mmanhong |
Date |
2015-06-19 |
Time |
15:10 |
Rev Time |
0.00 |
| Received By |
skennedy |
Date |
2015-06-17 |
Time |
16:20 |
Sent To |
Z |
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2015-06-17 |
|
|
Cont ID |
|
| Sent By |
mmanhong |
Date |
2015-06-17 |
Time |
16:17 |
Rev Time |
0.00 |
| Received By |
mmanhong |
Date |
2015-04-22 |
Time |
05:18 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
6 |
Status |
P |
Date |
2015-07-13 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2015-07-13 |
Time |
11:02 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2015-07-13 |
Time |
11:01 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
5 |
Status |
F |
Date |
2015-07-09 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2015-07-09 |
Time |
08:46 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2015-07-09 |
Time |
07:44 |
Sent To |
|
|
| Notes |
| 2015-07-09 08:46:44 | 1) THE FOUNTAIN PLANS SHOW THE EQUIPMENT ROOM AS BEING | | | ON GRADE. THE EQUIPMENT ROOM IS ACTUALLY BELOW GROUND. | | | THERE IS NO LOUVERED DOOR ON THIS ROOM AND THERE IS NO | | | WAY TO INSTALL A VENT ON THE OPPOSITE WAL AS NOTED ON | | | THE PLANSL. SUBMIT REVISE PLANS SHOWING THE EQUIPMENT | | | ROOM BELOW GRADE & LOCATION OF THE EQUIPMENT WITHIN THE | | | ROOM. THE LOCATION OF THE EQUIPMENT BELOW GRADE WILL | | | ALSO AFFECT THE TOTAL DYNAMIC HEAD.RECHECK THE FLOW | | | CALCULATIONS TO CONFIRM COMPLIANCE AND CONFIRM | | | COMPLIANCE ON THE PLANS.THE SWIMMING POOL AND THE SPA | | | WILL REQUIRE REVISIONS FOR THIS SAME REASON. | | | 2) SHT. 2 SHOWS THE RETURN LINE AS 2" ON THE ISOMETRIC | | | BUT THE FOUNTAIN CROSS SECTION SHOWS IT AS 2 1/2" . | | | CLARIFY. | | | 3) VENTILATION SHALL BE PROVIDED IN ACCORDANCE WITH | | | 2010 FBC SEC.424.1.5.4. SUBMIT CALCULATIONS. | | | 4) THE OPENING TO THE EQUIPMENT ROOM SHALL COMPLY WITH | | | 2010 FBC SEC.424.1.5.5. | | | | | | | | | I SUGGEST SOMEONE CALL ME TO DISCUSS THESE COMMENTS SO | | | I CAN PROVIDE THE PROPER DIRECTION. | | | | | | | | | PLUMBING PLAN REVIEW | | | TIM LARGE | | | CHIEF PLUMBING INSPECTOR | | | 561-805-6692 | | | [email protected] | | | | | | | | | |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
4 |
Status |
F |
Date |
2015-06-30 |
|
|
Cont ID |
|
| Sent By |
andrian |
Date |
2015-07-01 |
Time |
15:11 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2015-07-01 |
Time |
05:07 |
Sent To |
|
|
| Notes |
| 2015-07-01 05:08:31 | 1) PLUMBING IS FAILED, SO IS THE SUB-PERMIT. | | | 2) PLEASE CLARIFY WHY THERE IS A DRAWING DONE BY HAND | | | FOR THE POOL EQUIPMENT IN THE BASEMENT. | | | 2) I HAVE ABSOLUELY NO IDEA WHAT RELEVANCE THE | | | RESUBMITTED PLANS HAVE IN REGARDS TO THE FOUNTAIN. YOU | | | HAVE SUBMITTED ONE SET THAT APPEARS TO BE FOR THE SPA | | | AND THE PLANS ARE ONLY SHEETS 1 & 2 OF 3. WHERE IS | | | SHEET #3? THE OTHER SET APPEARS TO BE FOR THE SWIMMING | | | POOL WHICH ARE SHEETS 1 & 3 OF 4. THE SPA AND POOL ARE | | | TWO ENTIRELY DIFFERENT PERMIT NUMBERS. THE RESUBMITTED | | | PLANS AGAIN, FOR THE FOURTH TIME REVIEWED, DO NOT | | | ANSWER MY COMMENTS. PLEASE DO NOT RESUBMIT CORRECTIONS | | | UNTIL SOMEONE CAN FIGURE OUT HOW TO ADDRESS MY PLAN | | | REVIEW COMMENTS. FOUR TIMES THE PLAN REVIEW FEE SHALL | | | BE CHARGED AGAIN FOR A RESUBMITTAL PER F.S. 553.80 (2) | | | (B). | | | | | | PLUMBING PLAN REVIEW | | | TIM LARGE | | | CHIEF PLUMBING INSPECTOR | | | 561-805-6692 | | | [email protected] | | | | | 2015-06-30 15:12:07 | SEE SUB PERMIT FOR PASSED REVIEW |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
3 |
Status |
F |
Date |
2015-06-26 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2015-06-26 |
Time |
06:55 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2015-06-26 |
Time |
06:39 |
Sent To |
|
|
| Notes |
| 2015-06-26 06:44:03 | NONE OF MY PREVIOUS 7 COMMENTS HAVE BEEN ADDRESSED. | | | THIS IS THE THIRD REVIEW I HAVE DONE ASKING FOR THE | | | SAME THINGS AND NOTHING HAS BEEN DONE. THESE COMMENTS | | | ARE NOT GOING AWAY SO I SUGGEST SOMEONE CONTACT ME TO | | | SET UP A MEETING TO DISCUSS WHAT IT IS THAT IS NOT | | | CLEAR. | | | THE NEXT RESUBMITTAL IS SUBJECT TO 4 TIMES THE PLAN | | | REVIEW FEE PER F.S. 553.80 (2) (B). | | | | | | PLUMBING PLAN REVIEW | | | TIM LARGE | | | CHIEF PLUMBING INSPECTOR | | | 561-805-6692 | | | [email protected] | | | |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
2 |
Status |
F |
Date |
2015-06-19 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2015-06-19 |
Time |
08:26 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2015-06-19 |
Time |
06:36 |
Sent To |
|
|
| Notes |
| 2015-06-19 08:26:04 | 1) SUBMIT MANUFACTURER SPECS. ON THE MAIN DRAINS BEING | | | USED. WPB AMEND. TO 2010 FBC SEC. 107.2.1.2ND REQUEST. | | | 2) SHOW THE DISTANCE BETWEEN THE TWO MAIN DRAINS.WPB | | | AMEND. TO 2010 FBC SEC. 107.2.1.2ND REQUEST. | | | 3) SUBMIT PUMP CURVE INFO.2ND REQUEST. | | | 4) SUBMIT SPECS. FOR THE PUMP, SKIMMER AND TABLET | | | FEEDER.2ND REQUEST. | | | 5) THE POTABLE WATER SUPPLY SHALL BE PROTECTED WITH A | | | RPZ BACKFLOW PREVENTION DEVICE PER THE CITY OF WPB | | | CROSS CONNECTION MANUAL. 2ND REQUEST. | | | 6) THE PLANS AND ISOMETRIC SHOW A 4" MAIN DRAIN BUT THE | | | FOUNTAIN CROSS SECTION SHOWS A 6" MAIN DRAIN. CLARIFY. | | | 2ND REQUEST. | | | 7) THE PLAN SHOWS 2" OVERFLOW TO ON-SITE STORM DRAIN. | | | CLARIFY "ON-SITE STORM DRAIN. THE OVERDLOW SHALL NOT | | | DISCHARGE TO THE STORMWATER SYSTEM PER CITY ORDINANCE | | | 90-203. | | | | | | PLUMBING PLAN REVIEW | | | TIM LARGE | | | CHIEF PLUMBING INSPECTOR | | | 561-805-6692 | | | [email protected] | | | | | | |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
1 |
Status |
F |
Date |
2015-06-02 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2015-06-02 |
Time |
05:35 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2015-06-02 |
Time |
04:46 |
Sent To |
|
|
| Notes |
| 2015-06-08 05:13:06 | 1) SUBMIT MANUFACTURER SPECS. ON THE MAIN DRAINS BEING | | | USED. WPB AMEND. TO 2010 FBC SEC. 107.2.1. | | | 2) SHOW THE DISTANCE BETWEEN THE TWO MAIN DRAINS.WPB | | | AMEND. TO 2010 FBC SEC. 107.2.1. | | | 3) SUBMIT PUMP CURVE INFO. | | | 4) SUBMIT SPECS. FOR THE PUMP, SKIMMER AND TABLET | | | FEEDER. | | | 5) THE POTABLE WATER SUPPLY SHALL BE PROTECTED WITH A | | | RPZ BACKFLOW PREVENTION DEVICE PER THE CITY OF WPB | | | CROSS CONNECTION MANUAL. | | | 6) THE PLANS AND ISSOMETRIC SHOW A 4" MAIN DRAIN BUT | | | THE FOUNTAIN CROSS SECTION SHOWS A 6" MAIN DRAIN. | | | CLARIFY. | | | 7) THE PLAN SHOWS 2" OVERFLOW TO WASTE. CLARIFY | | | TERMINATION POINT. THE OVERDLOW SHALL NOT DISCHARGE TO | | | THE STORMWATER SYSTEM PER CITY ORDINANCE 90-203. | | | | | | PLUMBING PLAN REVIEW | | | TIM LARGE | | | CHIEF PLUMBING INSPECTOR | | | 561-805-6692 | | | [email protected] | | | | | | |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
2 |
Status |
P |
Date |
2015-06-19 |
|
|
Cont ID |
|
| Sent By |
skennedy |
Date |
2015-06-25 |
Time |
15:10 |
Rev Time |
0.25 |
| Received By |
eschneid |
Date |
2015-06-19 |
Time |
14:13 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
P |
Date |
2015-05-29 |
|
|
Cont ID |
|
| Sent By |
eschneid |
Date |
2015-05-29 |
Time |
16:48 |
Rev Time |
0.25 |
| Received By |
eschneid |
Date |
2015-05-29 |
Time |
16:48 |
Sent To |
P |
|
| Notes |
|
|