| 2015-04-22 18:25:49 | RESIDENTIAL (R2) FLOORING SECOND BUILDING REVIEW |
| | COMMENTS. |
| | CODE: 2010 FBC. |
| | |
| | NOTE: THE COMMENTS BELOW ARE THE SAME COMMENTS FROM THE |
| | FIRST CHECKLIST: |
| | |
| | 1- SOUND INSULATION: PROVIDE TWO COPIES OF ASTM E84 OR |
| | UL 723 TEST SHOWING COMPLIANCE WITH THE FLAME SPREAD |
| | INDEX AND SMOKE-DEVELOPED INDEX AS REQUIRED BY SEC. . |
| | 719.1 OF 2010 FBC-BUILDING. (REPEAT COMMENT. NOT |
| | ADDRESSED). |
| | |
| | 2- SOUND INSULATION: PROVIDE TWO COPIES OF ASTM E 90 |
| | TEST SHOWING COMPLIANCE WITH THE SOUND TRANSMISSION |
| | CLASS (STC) AS REQUIRED BY SEC. 1207.2 OF 2010 |
| | FBC-BUILDING. (REPEAT COMMENT. NOT ADDRESSED). |
| | NEED TO VERIFY IF TESTING SAMPLE AND PROPOSED |
| | INSTALLATION ARE EQUIVALENT. CONCRETE SLAB THICKNESS |
| | AND IF ACOUSTICAL SUSPENDED CEILING WAS USED TO OBTAIN |
| | THE VALUES SPECIFIED ON THE ECB 75 PRODUCT DATA SHEET |
| | SUBMITTED. |
| | |
| | 3- SOUND INSULATION: PROVIDE TWO COPIES OF ASTM E 492 |
| | TEST SHOWING COMPLIANCE WITH THE IMPACT INSULATION |
| | CLASS (IIC) AS REQUIRED BY SEC. 1207.3 OF 2010 |
| | FBC-BUILDING. (REPEAT COMMENT. NOT ADDRESSED). |
| | NEED TO VERIFY IF TESTING SAMPLE AND PROPOSED |
| | INSTALLATION ARE EQUIVALENT. CONCRETE SLAB THICKNESS |
| | AND IF ACOUSTICAL SUSPENDED CEILING WAS USED TO OBTAIN |
| | THE VALUES SPECIFIED ON THE ECB 75 PRODUCT DATA SHEET |
| | SUBMITTED. |
| | |
| | |
| | IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT |
| | JULIO GOMEZ |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | DEVELOPMENT SERVICES DEPARTMENT. |
| | (561)805-6712 |
| | [email protected] |