Plan Review Details - Permit 15030025
Plan Review Stops For Permit 15030025
Review Stop ENG ENGINEERING CSD
Rev No 2 Status P Date   Cont ID  
Sent By   Date   Time   Rev Time 0.00
Received By cranford Date 2015-04-08 Time 07:37 Sent To P
Notes
2015-04-08 09:57:24REPEAT OF ORIGINAL COMMENTS. SIZING/DESIGN FOR THIS
 TYPE OF SEPARATOR MUST BE BASED ON ANTICIPATED
 OIL/GREASE LOADING FROM RESTAURANT. LOADING IS USUALLY
 DETERMINED FROM NUMBER AND TYPE OF MEALS SERVED.

Review Stop ENG ENGINEERING CSD
Rev No 1 Status F Date 2015-03-10 Cont ID  
Sent By cranford Date 2015-03-10 Time 14:35 Rev Time 0.00
Received By cranford Date 2015-03-10 Time 14:27 Sent To I
Notes
2015-03-10 14:35:32PER SECTION 90-127 OF THE CODE OF ORDINANCES:
  
 1. PLEASE SUBMIT SIZING CALCULATIONS FOR THE PROPOSED
 GREASE TRAP.
  
 2. INDICATE WHERE THE SAMPLING PORT FOR THE GREASE TRAP
 WILL BE LOCATED. ALL INTERCEPTION UNITS SHALL BE OF
 TYPE AND CAPACITY APPROVED IN WRITING BY THE CITY AND
 SHALL BE INSTALLED AT A LOCATION ON THE PREMISES TO BE
 EASILY ACCESSIBLE FOR CLEANING AND INSPECTION.
  
 KELLY CRANFORD, PE
 CITY LAND DEVELOPMENT ENGINEER
 [email protected]
 561-494-1098 (OFFICE)
  
  

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2015-04-21 Cont ID  
Sent By tklarge Date 2015-04-21 Time 13:05 Rev Time 0.00
Received By tklarge Date 2015-04-21 Time 13:05 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2015-04-21 Cont ID  
Sent By tklarge Date 2015-04-21 Time 04:46 Rev Time 0.00
Received By tklarge Date 2015-04-20 Time   Sent To  
Notes
2015-04-20 16:25:57INCOMING SENT TO <$5K PLUMBING BOX.

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2015-04-14 Cont ID  
Sent By   Date 2015-04-14 Time   Rev Time 0.00
Received By shill Date 2015-03-26 Time 13:28 Sent To  
Notes
2015-04-08 18:01:174/8 FOUND IN MISC 2; PUT IN PLUMBING BOX
 SH
  
  
  
2015-03-26 13:28:52TO ENGINEERING
  

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2015-03-10 Cont ID  
Sent By cranford Date 2015-03-10 Time 14:36 Rev Time 0.00
Received By cranford Date 2015-03-04 Time 06:06 Sent To  
Notes
2015-03-04 06:07:41SENT TO ENGINEERING.3/4/15. TKL.
2015-03-02 12:45:45ROUTED TP PLUMBING LESS THAN 5K

Review Stop P PLUMBING
Rev No 4 Status P Date 2015-04-21 Cont ID  
Sent By tklarge Date 2015-04-21 Time 13:05 Rev Time 0.00
Received By tklarge Date 2015-04-21 Time 13:05 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 3 Status F Date 2015-04-21 Cont ID  
Sent By tklarge Date 2015-04-21 Time 04:46 Rev Time 0.00
Received By tklarge Date 2015-04-21 Time 03:59 Sent To  
Notes
2015-04-21 04:45:291) THE HAND SINK SHALL BE ADDED ONTO THE PERMIT
 APPLICATION UNDER "DESCRIPTION OF WORK" SECTION. THE
 VALUE OF THE JOB WAS ADJUSTED BUT THE SINK HAS NOT BEEN
 ADDED TO THE DESCRIPTION. WPB AMEND. TO 2010 FBC SEC.
 107.2.1.2ND REQUEST.
 2) SUBMIT SIZING CALCULATIONS FOR THE GREASE
 INTERCEPTOR IN ACCORDANCE WITH THE 2010 FL. PLUMBING
 CODE SEC. 1003.3.4 AND SEC.1003.3.4.1. 3RD REQUEST. YOU
 HAVE PROVIDED A MODEL NUMBER OF A UNIT THAT WILL BE
 USED BUT HOW DID YOU DETERMINE THAT THE UNIT YOU ARE
 SPECIFYING IS OF ADEQUATE CAPACITY?
 3) SUBMIT A FLOOR PLAN AND WATER AND SANITARY RISER FOR
 THE INSTALLATION OF ALL APPLIANCES & EQUIPMENT.THESE
 FIXTURES APPEAR TO BE NEW AND NOT REPLACEMENTS. SHOW
 THE PIPE SIZES, LOCATION AND TERMINATION OF ALL VENTS,
 AND THE CONNECTION POINT OF THE NEW PIPING TO THE
 EXISTING SYSTEM. 3RD REQUEST.WPB AMEND. TO 2010 FBC
 SEC. 107.2.1.
  
 PLUMBING PLAN REVIEW
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 561-805-6692
 [email protected]
  

Review Stop P PLUMBING
Rev No 2 Status F Date 2015-04-14 Cont ID  
Sent By tklarge Date 2015-04-14 Time 06:41 Rev Time 0.00
Received By tklarge Date 2015-04-14 Time 06:22 Sent To  
Notes
2015-04-14 06:40:591) COMPLY WITH ALL COMMENTS FROM PREVIOUS REVIEW DATED
 3/4/15.
 2) YOU HAVE SUBMITTED PICTURES OF A HAND SINK. IF THIS
 IS ALSO NEW IT MUST BE ADDED TO THE DESCRIPTION OF WORK
 ON THE APPLICATION AND ALSO TO THE COST OF THE JOB, WPB
 AMEND. TO 2010 FBC SEC. 107.2.1.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 CITY OF WEST PALM BEACH BUILDING DIVISION
 561-805-6692
 [email protected]
  

Review Stop P PLUMBING
Rev No 1 Status F Date 2015-03-04 Cont ID  
Sent By tklarge Date 2015-03-04 Time 06:06 Rev Time 0.00
Received By tklarge Date 2015-03-04 Time 05:35 Sent To  
Notes
2015-03-04 06:06:141) SUBMIT A FLOOR PLAN DRAWING SHOWING THE LOCATION OF
 THE 3 COMPARTMENT SINK. WPB AMEND. TO 2010 FBC
 SEC.107.2.1.
 2) SUBMIT A PLUMBING RISER DIAGRAM FOR THE
 INSTALLATION. SHOW THE PIPE SIZES, LOCATION &
 TERMINATION POINTS OF THE VENT, AND THE CONNECTION TO
 THE PLUMBING SYSTEM. WPB AMEND. TO 2010 FBC SEC.
 107.3.5.1.3.
 3) INDICATE ON THE PLAN IF THE 3 COMPARTMENT SINK IS
 NEW OR EXISTING. WPB AMEND. TO 201 FBC SEC. 107.2.1.
 4) SUBMIT 2 COPIES OF THE INSTALLATION INSTRUCTIONS FOR
 THE TANKLESS WATER HEATER PER WPB AMEND. TO 201 FBC
 SEC. 107.2.1, FPC SEC.502.1.
 5) INDICATE ON THE PLANS IF THE 3 COMPARTMENT SINK IS
 NEW OR EXISTING. IF NEW, SUBMIT A WATER PIPING
 RISER.WPB AMEND. TO 2010 FBC SEC.107.5.1.3.
 6) A SEPARATE ELECTRIC PERMIT WILL BE REQUIRED FOR THE
 GREASE INTERCEPTOR.
 7) SUBMIT SIZING CALCULATIONS FOR THE GREASE
 INTERCEPTOR PER THE 2010 FPC SEC. 1003.3.4., 103.3.4.1.
  
 PLUMBING PLAN REVIEW
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 561-805-6692
 [email protected]
  
  
  