| Plan Review Stops For Permit 15030025 |
| Review Stop |
ENG |
ENGINEERING CSD |
| Rev No |
2 |
Status |
P |
Date |
|
|
|
Cont ID |
|
| Sent By |
|
Date |
|
Time |
|
Rev Time |
0.00 |
| Received By |
cranford |
Date |
2015-04-08 |
Time |
07:37 |
Sent To |
P |
|
| Notes |
| 2015-04-08 09:57:24 | REPEAT OF ORIGINAL COMMENTS. SIZING/DESIGN FOR THIS | | | TYPE OF SEPARATOR MUST BE BASED ON ANTICIPATED | | | OIL/GREASE LOADING FROM RESTAURANT. LOADING IS USUALLY | | | DETERMINED FROM NUMBER AND TYPE OF MEALS SERVED. |
|
|
| Review Stop |
ENG |
ENGINEERING CSD |
| Rev No |
1 |
Status |
F |
Date |
2015-03-10 |
|
|
Cont ID |
|
| Sent By |
cranford |
Date |
2015-03-10 |
Time |
14:35 |
Rev Time |
0.00 |
| Received By |
cranford |
Date |
2015-03-10 |
Time |
14:27 |
Sent To |
I |
|
| Notes |
| 2015-03-10 14:35:32 | PER SECTION 90-127 OF THE CODE OF ORDINANCES: | | | | | | 1. PLEASE SUBMIT SIZING CALCULATIONS FOR THE PROPOSED | | | GREASE TRAP. | | | | | | 2. INDICATE WHERE THE SAMPLING PORT FOR THE GREASE TRAP | | | WILL BE LOCATED. ALL INTERCEPTION UNITS SHALL BE OF | | | TYPE AND CAPACITY APPROVED IN WRITING BY THE CITY AND | | | SHALL BE INSTALLED AT A LOCATION ON THE PREMISES TO BE | | | EASILY ACCESSIBLE FOR CLEANING AND INSPECTION. | | | | | | KELLY CRANFORD, PE | | | CITY LAND DEVELOPMENT ENGINEER | | | [email protected] | | | 561-494-1098 (OFFICE) | | | | | | |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
4 |
Status |
N |
Date |
2015-04-21 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2015-04-21 |
Time |
13:05 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2015-04-21 |
Time |
13:05 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
3 |
Status |
N |
Date |
2015-04-21 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2015-04-21 |
Time |
04:46 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2015-04-20 |
Time |
|
Sent To |
|
|
| Notes |
| 2015-04-20 16:25:57 | INCOMING SENT TO <$5K PLUMBING BOX. |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2015-04-14 |
|
|
Cont ID |
|
| Sent By |
|
Date |
2015-04-14 |
Time |
|
Rev Time |
0.00 |
| Received By |
shill |
Date |
2015-03-26 |
Time |
13:28 |
Sent To |
|
|
| Notes |
| 2015-04-08 18:01:17 | 4/8 FOUND IN MISC 2; PUT IN PLUMBING BOX | | | SH | | | | | | | | | | | 2015-03-26 13:28:52 | TO ENGINEERING | | | |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2015-03-10 |
|
|
Cont ID |
|
| Sent By |
cranford |
Date |
2015-03-10 |
Time |
14:36 |
Rev Time |
0.00 |
| Received By |
cranford |
Date |
2015-03-04 |
Time |
06:06 |
Sent To |
|
|
| Notes |
| 2015-03-04 06:07:41 | SENT TO ENGINEERING.3/4/15. TKL. | | 2015-03-02 12:45:45 | ROUTED TP PLUMBING LESS THAN 5K |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
4 |
Status |
P |
Date |
2015-04-21 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2015-04-21 |
Time |
13:05 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2015-04-21 |
Time |
13:05 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
3 |
Status |
F |
Date |
2015-04-21 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2015-04-21 |
Time |
04:46 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2015-04-21 |
Time |
03:59 |
Sent To |
|
|
| Notes |
| 2015-04-21 04:45:29 | 1) THE HAND SINK SHALL BE ADDED ONTO THE PERMIT | | | APPLICATION UNDER "DESCRIPTION OF WORK" SECTION. THE | | | VALUE OF THE JOB WAS ADJUSTED BUT THE SINK HAS NOT BEEN | | | ADDED TO THE DESCRIPTION. WPB AMEND. TO 2010 FBC SEC. | | | 107.2.1.2ND REQUEST. | | | 2) SUBMIT SIZING CALCULATIONS FOR THE GREASE | | | INTERCEPTOR IN ACCORDANCE WITH THE 2010 FL. PLUMBING | | | CODE SEC. 1003.3.4 AND SEC.1003.3.4.1. 3RD REQUEST. YOU | | | HAVE PROVIDED A MODEL NUMBER OF A UNIT THAT WILL BE | | | USED BUT HOW DID YOU DETERMINE THAT THE UNIT YOU ARE | | | SPECIFYING IS OF ADEQUATE CAPACITY? | | | 3) SUBMIT A FLOOR PLAN AND WATER AND SANITARY RISER FOR | | | THE INSTALLATION OF ALL APPLIANCES & EQUIPMENT.THESE | | | FIXTURES APPEAR TO BE NEW AND NOT REPLACEMENTS. SHOW | | | THE PIPE SIZES, LOCATION AND TERMINATION OF ALL VENTS, | | | AND THE CONNECTION POINT OF THE NEW PIPING TO THE | | | EXISTING SYSTEM. 3RD REQUEST.WPB AMEND. TO 2010 FBC | | | SEC. 107.2.1. | | | | | | PLUMBING PLAN REVIEW | | | TIM LARGE | | | CHIEF PLUMBING INSPECTOR | | | 561-805-6692 | | | [email protected] | | | |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
2 |
Status |
F |
Date |
2015-04-14 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2015-04-14 |
Time |
06:41 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2015-04-14 |
Time |
06:22 |
Sent To |
|
|
| Notes |
| 2015-04-14 06:40:59 | 1) COMPLY WITH ALL COMMENTS FROM PREVIOUS REVIEW DATED | | | 3/4/15. | | | 2) YOU HAVE SUBMITTED PICTURES OF A HAND SINK. IF THIS | | | IS ALSO NEW IT MUST BE ADDED TO THE DESCRIPTION OF WORK | | | ON THE APPLICATION AND ALSO TO THE COST OF THE JOB, WPB | | | AMEND. TO 2010 FBC SEC. 107.2.1. | | | | | | TIM LARGE | | | CHIEF PLUMBING INSPECTOR | | | CITY OF WEST PALM BEACH BUILDING DIVISION | | | 561-805-6692 | | | [email protected] | | | |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
1 |
Status |
F |
Date |
2015-03-04 |
|
|
Cont ID |
|
| Sent By |
tklarge |
Date |
2015-03-04 |
Time |
06:06 |
Rev Time |
0.00 |
| Received By |
tklarge |
Date |
2015-03-04 |
Time |
05:35 |
Sent To |
|
|
| Notes |
| 2015-03-04 06:06:14 | 1) SUBMIT A FLOOR PLAN DRAWING SHOWING THE LOCATION OF | | | THE 3 COMPARTMENT SINK. WPB AMEND. TO 2010 FBC | | | SEC.107.2.1. | | | 2) SUBMIT A PLUMBING RISER DIAGRAM FOR THE | | | INSTALLATION. SHOW THE PIPE SIZES, LOCATION & | | | TERMINATION POINTS OF THE VENT, AND THE CONNECTION TO | | | THE PLUMBING SYSTEM. WPB AMEND. TO 2010 FBC SEC. | | | 107.3.5.1.3. | | | 3) INDICATE ON THE PLAN IF THE 3 COMPARTMENT SINK IS | | | NEW OR EXISTING. WPB AMEND. TO 201 FBC SEC. 107.2.1. | | | 4) SUBMIT 2 COPIES OF THE INSTALLATION INSTRUCTIONS FOR | | | THE TANKLESS WATER HEATER PER WPB AMEND. TO 201 FBC | | | SEC. 107.2.1, FPC SEC.502.1. | | | 5) INDICATE ON THE PLANS IF THE 3 COMPARTMENT SINK IS | | | NEW OR EXISTING. IF NEW, SUBMIT A WATER PIPING | | | RISER.WPB AMEND. TO 2010 FBC SEC.107.5.1.3. | | | 6) A SEPARATE ELECTRIC PERMIT WILL BE REQUIRED FOR THE | | | GREASE INTERCEPTOR. | | | 7) SUBMIT SIZING CALCULATIONS FOR THE GREASE | | | INTERCEPTOR PER THE 2010 FPC SEC. 1003.3.4., 103.3.4.1. | | | | | | PLUMBING PLAN REVIEW | | | TIM LARGE | | | CHIEF PLUMBING INSPECTOR | | | 561-805-6692 | | | [email protected] | | | | | | | | | |
|
|