Plan Review Details - Permit 15020156
| Plan Review Stops For Permit 15020156 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
3 |
Status |
P |
Date |
2015-04-01 |
|
|
Cont ID |
|
| Sent By |
skennedy |
Date |
2015-04-01 |
Time |
16:42 |
Rev Time |
0.00 |
| Received By |
skennedy |
Date |
|
Time |
|
Sent To |
|
|
| Notes |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
2 |
Status |
F |
Date |
2015-03-19 |
|
|
Cont ID |
|
| Sent By |
skennedy |
Date |
2015-03-19 |
Time |
17:25 |
Rev Time |
0.00 |
| Received By |
skennedy |
Date |
2015-03-19 |
Time |
17:25 |
Sent To |
|
|
| Notes |
| 2015-03-19 17:26:16 | SEE PREVIOUS COMMENT. NOT ADRESSED. |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
F |
Date |
2015-02-13 |
|
|
Cont ID |
|
| Sent By |
skennedy |
Date |
2015-02-13 |
Time |
09:30 |
Rev Time |
0.00 |
| Received By |
skennedy |
Date |
2015-02-13 |
Time |
09:30 |
Sent To |
|
|
| Notes |
| 2015-02-13 09:39:57 | 1ST REVIEW: FBC 2010 | | | | | | PLEASE SPECIFY ON SHEET A-2 SECTION A/A2, WEDGE ANCHOR | | | DEPTH INTO BEAM, IE: LENGTH OF ANCHOR AND ANY PROPOSED | | | EPOXY NEEDED TO HANDLED THE FORCE IMPOSED. | | | FBC 107.3.5.3 5. STRUCTURAL REQUIREMENTS SHALL INCLUDE: | | | WALL SECTION FROM FOUNDATION THROUGH ROOF, INCLUDING | | | ASSEMBLY AND MATERIALS CONNECTOR | | | TABLES | | | | | | | | | IMPORTANT NOTICE EFFECTIVE MARCH 2, 2015, ALL PERMIT | | | APPLICATION PLAN REVIEWS WILL BE PERFORMED | | | ELECTRONICALLY | | | UPON APPLICATION AND FEE PAYMENT DESIGN DOCUMENTS | | | SUBMISSION OPTIONS ARE AS FOLLOWS: | | | 1. UPLOAD VIA THE PROJECTDOX PORTAL WITH DIGITAL | | | SIGNATURES OF DESIGN PROFESSIONALS AS APPLICABLE; USE | | | THE REQUIRED NAMING CONVENTION FOR EACH DOCUMENT | | | 2. INCLUDE ON A CD IF DESIGN PROFESSIONAL DIGITAL | | | SIGNATURES ARE PROVIDED AS REQUIRED; USE THE REQUIRED | | | NAMING CONVENTION FOR EACH DOCUMENT | | | 3. INCLUDE ON A CD WITH ONE SET OF TRADITIONAL PAPER | | | DESIGN DOCUMENTS SIGNED AND SEALED AS REQUIRED; USE THE | | | REQUIRED NAMING CONVENTION FOR EACH DOCUMENT | | | 4. ONE SET OF TRADITIONAL PAPER DESIGN DOCUMENTS | | | SUBJECT TO ADMINISTRATIVE FEES TO DIGITIZE THE | | | DOCUMENTS | | | | | | STEVEN KENNEDY, CBO | | | CHIEF PLANS EXAMINER | | | (561) 805-6710 | | | [email protected] | | | |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
N |
Date |
2015-03-19 |
|
|
Cont ID |
|
| Sent By |
skennedy |
Date |
2015-03-19 |
Time |
17:28 |
Rev Time |
0.00 |
| Received By |
skennedy |
Date |
|
Time |
|
Sent To |
|
|
| Notes |
| 2015-02-19 17:48:27 | NEW SHEET SUBMITTED. JG. |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2015-03-19 |
|
|
Cont ID |
|
| Sent By |
skennedy |
Date |
2015-03-19 |
Time |
17:28 |
Rev Time |
0.00 |
| Received By |
skennedy |
Date |
2015-02-19 |
Time |
12:45 |
Sent To |
|
|
| Notes |
| 2015-02-24 12:46:26 | REVISION SENT TO STEVE KENNEDY FOR REVIEW. JG. |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2015-02-13 |
|
|
Cont ID |
|
| Sent By |
skennedy |
Date |
2015-02-13 |
Time |
09:34 |
Rev Time |
0.00 |
| Received By |
skennedy |
Date |
2015-02-05 |
Time |
18:51 |
Sent To |
|
|
| Notes |
| 2015-02-05 18:51:37 | SENT TO S KENNEDY |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
2 |
Status |
P |
Date |
2015-03-19 |
|
|
Cont ID |
|
| Sent By |
skennedy |
Date |
2015-03-19 |
Time |
17:26 |
Rev Time |
0.00 |
| Received By |
skennedy |
Date |
2015-03-19 |
Time |
17:26 |
Sent To |
E |
|
| Notes |
| 2015-02-19 17:49:03 | NEW SHEET SUBMITTED. JG. |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
1 |
Status |
P |
Date |
2015-02-13 |
|
|
Cont ID |
|
| Sent By |
skennedy |
Date |
2015-02-13 |
Time |
09:34 |
Rev Time |
0.00 |
| Received By |
skennedy |
Date |
2015-02-13 |
Time |
09:34 |
Sent To |
|
|
| Notes |
|
|
|
Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved |
 |
 |