| 2014-10-30 08:37:36 | 10/30/2014 |
| | PROJECT: JAMBA JUICE |
| | PERMIT#: 14100910 |
| | CODE: 2008 EDITION OF THE NEC, 2010 EDITION OF THE FBC |
| | ,2010 WPB AMENDMENTS TO THE FBC, CHAPTER 1, |
| | ADMINISTRATION, 2012 FBC SUPPLEMENTS. |
| | 1ST ELECTRICAL PLAN REVIEW |
| | ACTION: DENIED |
| | |
| | 1) WPB AMENDMENTS TO THE FBC 107.3.5.1.6 ENERGY |
| | CALCULATIONS - PROVIDE AN ENERGY SUBMITTAL COMPLIANT |
| | WITH FBC-E 103 |
| | PROVIDE A MORE ACCURATE LOAD CALCULATION. THE PROPOSED |
| | LOAD FOR THE NEW JUMBA JUICE IS INDICATED AS 0 KWD, |
| | ADDITIONALLY, THE DEMAND LOAD INDICATED FOR SEVERAL OF |
| | THE EXISTING LOADS ARE ESITIMATED ONLY, NOT ACTUAL. |
| | PLEASE PREPARE AN ACTUAL COMMERCIAL LOAD CALCULATION |
| | INCLUDING THE NEW JAMBA JUICE BASED ON THE NEC ARTICLE |
| | 220. OR 12 MONTHS OF ACTUAL DEMAND LOAD FROM FPL. |
| | |
| | 2) PROVIDE THE ACTUAL LENGTH OF RUN FROM THE ELECTRICAL |
| | ROOM TO THE NEW JAMBA JUICE PANEL AND ADJUST THE |
| | FEEDERS AS NEEDED TO COMPENSATE FOR ANY VOLTAGE DROP |
| | LOSSES. |
| | WPB AMENDMENTS TO THE FBC,107.3.2 |
| | |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. SEE LINK: |
| | HTTP://WPB.ORG/DEVELOPMENT/WP-CONTENT/UPLOADS/SITES/33/ |
| | 2013/09/APPLICATION_RESUBMITTAL_FORM_04132010.PDF |
| | |
| | ADDITIONALLY, PLEASE INSERT CORRECTED PAGES INTO |
| | SUBMITTAL PACKAGE AND LEAVE THE PREVIOUSLY REVIEWED |
| | SHEETS FOR COMPARATIVE REVIEW. |
| | |
| | DAVID HAYES, ELECTRICAL PLANS EXAMINER, PX3421, |
| | 561-805-6717 OR [email protected] |
| | |