| 2014-09-09 15:51:22 | THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE |
| | MARSHAL, WITH THE FOLLOWING COMMENTS: |
| | |
| | THE NATURE OF THE PROPOSED SKATEBOARD RAMP REQUIRES AN |
| | EVALUATION OF THE FIRE ALARM AND SPRINKLER SYSTEM FOR |
| | CODE COVERAGE AND COMPLIANCE. |
| | |
| | THE PROPOSED RAMP IS MADE OF WOOD WITH HOLLOW VOIDS |
| | UNDERNEATH. THE NOISE LEVEL CREATED DURING USE MAY |
| | RENDER THE EXISTING FIRE ALARM NOTIFICATION VOLUMES |
| | INEFFECTIVE. ADDITIONAL NOTIFICATION DEVICES WITH |
| | HIGHER VOLUMES MAY BE REQUIRED. AN EVALAUTION AND |
| | TESTING IS REQUIRED BY A CERTIFIED FIRE ALARM |
| | CONTRACTOR. |
| | |
| | THE PROPOSED WOOD RAMP ADDS A SIGNIFICANT CONCENTRATED |
| | FIRE LOAD TO THE INSTALLED AREA. AN EVALUATION OF THE |
| | SPRINKLER SYSTEM AND SPRINKLER HEAD COVERAGE OF THE |
| | AREA BY A CERTIFIED FIRE SPRINKLER CONTRACTOR IS |
| | REQUIRED. |
| | |
| | ANY AND ALL WORK ON THE FIRE ALARM AND FIRE SPRINKLER |
| | SYSTEMS SHALL BE DONE UNDER SEPARATE SHOP DRAWINGS AND |
| | BY CERTIFIED LIFE SAFETY CONTRACTORS. |
| | |
| | ANY TIME THAT WORK ON THE LIFE SAFETY SYSTEMS, |
| | SPRINKLER AND/OR FIRE ALARM, EXCEEDS 4 HOURS, A FIRE |
| | WATCH SHALL BE IMPLEMENTED AND MAINTAINED UNTIL FULL |
| | AND COMPLETE PROTECTION IS RETURNED. |
| | |
| | A SITE PLAN IS NEEDED TO SHOW THE LOCATION OF THE |
| | PROPOSED RAMP IN THE PROPOSED ROOM OF INSTALLATION |
| | INCLUDING FLOOR DIMENSIONS AND EXITS. |
| | |
| | A LIFE SAFETY PLAN IS REQUIRED TO SHOW THE AREA OF |
| | INSTALLATION INCLUDING THE TOTAL BUILDING FOOTPRINT, |
| | OCCUPANY LOADS, EXIT PATHS, EXITS, AND EXIT DISCHARGES. |
| | |
| | |