Plan Review Details - Permit 14070323
Plan Review Stops For Permit 14070323
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2014-07-12 Cont ID  
Sent By tmoore Date 2014-07-12 Time 09:18 Rev Time 0.00
Received By tmoore Date 2014-07-12 Time 08:36 Sent To B
Notes
2014-07-12 09:18:12SPOKE WITH NANCY CUSHING ON DEMO APPLICATION
 DEFICIENCIES. THERE IS NO PLUMBING PERMIT PULLED FOR
 CAPPING THE SEWER LATERAL AT THIS TIME. THAT PERMIT
 SHOULD ALSO LIST FIRE MAIN CAPPING TO LINE FEEDING
 SPRINKLERS. THE BUILDING IS COMMERCAIL AND WILL REQUIRE
 AN ASBESTOS ABATEMENT SURVEY. NANCY C. WILL CONTACT
 ALEX ORTEGA FOR THE REQUIRED HEALTH DEPARTMENT
 NOTIFICATION AND CONFIRMATION ON ASBESTOS ABATEMENT. AT
 THIS TIME THERE IS SOME QUESTION ON WHO WILL HIRE THE
 PLUMBING CONTRACTOR, BUT THAT IS BEING WORKED OUT.
 MOVING APPLICATION ON TO ENGINEERING FOR THEIR REVIEW.
 TM

Review Stop B1 BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2014-09-16 Cont ID  
Sent By tmoore Date 2014-09-16 Time 09:27 Rev Time 0.00
Received By tmoore Date 2014-09-16 Time 09:26 Sent To  
Notes
2014-09-16 09:27:44OK TO ISSUE. FINALY RECEIVED ASBESTOS ABATEMENT SURVEY.
 CALLING NANCY C. TO LET HER KNOW IT IS READY WHEN FEE
 ARE PAID.

Review Stop ENG ENGINEERING CSD
Rev No 2 Status P Date 2014-09-10 Cont ID  
Sent By cranford Date 2014-09-10 Time 16:23 Rev Time 0.50
Received By cranford Date 2014-09-10 Time 16:22 Sent To B
Notes
2014-09-10 16:23:10APPLICATION IS TO DEMOLISH ALL ABOVE GROUND
 INFRASTRUCTURE. TRAILERS TO BE REMOVED.

Review Stop ENG ENGINEERING CSD
Rev No 1 Status F Date 2014-07-15 Cont ID  
Sent By cranford Date 2014-07-15 Time 14:04 Rev Time 2.00
Received By cranford Date 2014-07-15 Time 14:00 Sent To B
Notes
2014-07-15 14:04:24IT IS NOT CLEAR FROM THE APPLICATION EXACTLY WHAT WAS
 GOING TO BE REMOVED (BUILDING AND ATTACHED STRUCTURES,
 ALL IMPROVEMENTS, ETC.) OR HOW THE LAND WAS GOING TO BE
 STABILIZED ONCE THE DEMOLITION WAS COMPLETE. IF OVER
 4,500 SF OF LAND DISTURBING ACTIVITIES ARE PROPOSED, WE
 WILL NEED AN EROSION CONTROL BOND.
  
 I NEED A DEMOLITION PLAN (A SKETCH ON AN AERIAL IS OK)
 AND A STORMWATER POLLUTION PREVENTION PLAN (SWPPP).
  
 GUIDELINES FOR PREPARING THE SWPPP ARE UNDER:
 HTTP://WPB.ORG/WP-CONTENT/UPLOADS/SITES/7/2012/05/2011-
 12-21-15-00-29-SWPPPGUIDE.PDF
 HTTP://CFPUB.EPA.GOV/NPDES/STORMWATER/CONST.CFM
 HTTP://WWW.DEP.STATE.FL.US/WATER/STORMWATER/NPDES/SWPPP
 .HTM
  
 THE DEMOLITION PLAN NEEDS TO SHOW THE FOLLOWING:
 - DEMOLITION AND CLEARING LIMITS OF WORK
 - IDENTIFY EXISTING STRUCTURES, UTILITIES AND
 VEGETATION TO BE CLEARED
 - IDENTIFY TEMPORARY DEMOLITION SITE WORK SITE ACCESS
 - IDENTIFY UTILITY DISCONNECTS ASSOCIATED WITH
 DEMOLITION WORK
 - IDENTIFY POSSIBLE HAZARDOUS WASTE MATERIAL EXPOSED
 DURING WORK
  
 DETAILS OF THE SWPPP, SITE RESTORATION REQUIREMENTS,
 AND BONDING ARE LISTED IN SECTION 94-450 OF OUR CODE OF
 ORDINANCES.
  
 HTTPS://LIBRARY.MUNICODE.COM/INDEX.ASPX?CLIENTID=10017&
 STATEID=9&STATENAME=FLORIDA

Review Stop HIST HISTORICAL
Rev No 1 Status P Date 2014-07-10 Cont ID  
Sent By fmittner Date 2014-07-10 Time 11:54 Rev Time 0.00
Received By fmittner Date 2014-07-10 Time 11:54 Sent To  
Notes
***NONE***