Plan Review Details - Permit 14060883
| Plan Review Stops For Permit 14060883 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
3 |
Status |
P |
Date |
2014-08-28 |
|
|
Cont ID |
|
| Sent By |
shill |
Date |
2014-08-28 |
Time |
16:03 |
Rev Time |
0.00 |
| Received By |
shill |
Date |
2014-08-28 |
Time |
16:03 |
Sent To |
|
|
| Notes |
| 2014-08-28 16:04:33 | PROVISO - PER ROHN, COMPANY WILL APPLY FOR CERTIFICATE | | | OF AUTHORIZATION. C OF A NUMBER WILL BE EMAILED UPON | | | ISSUANCE FROM FBPE | | | |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
2 |
Status |
F |
Date |
2014-08-15 |
|
|
Cont ID |
|
| Sent By |
shill |
Date |
2014-08-15 |
Time |
18:43 |
Rev Time |
0.00 |
| Received By |
shill |
Date |
2014-08-15 |
Time |
18:42 |
Sent To |
|
|
| Notes |
| 2014-08-15 18:49:14 | ****CORRECTIONS**** | | | | | | SAMANTHA HILL | | | BUILDING PLANS EXAMINER | | | [email protected] | | | 561-805-6724 | | | | | | FROM PREVIOUS LIST: | | | | | | 1. FS 471 AND FAC61G15-23, TITLE BLOCK FOR ENGINEER IS | | | NOT CLEAR. IS ENGINEER PRACTICING THROUGH ROHN PRODUCTS | | | LLC? CERTIFICATE OF AUTHORIZATION REQUIRED. IF ENGINEER | | | IS NOT PRACTICING THROUGH ROHN PRODUCTS LLC, IT IS NOT | | | CLEAR WHY THE ENGINEER DOES NOT HAVE A TITLE BLOCK ON | | | ANY OF THE SHEETS HE'S TAKING RESPONSIBILITY FOR. | | | | | | EITHER EACH SHEET IS TO BE SIGNED AND SEALED, OR AN | | | INDEX SHEET IS REQUIRED. THE LAWS AND RULES CAN BE | | | FOUND AT WWW.FBPE.ORG. | | | | | | 2ND REVIEW: | | | | | | EACH SHEET IS NOW SIGNED, SEALED AND DATED BY DAVID G. | | | BRINKER WITH WHAT APPEARS TO BE A TITLE BLOCK OF "ROHN | | | PRODUCTS LLC". | | | | | | PREVIOUS SET INCLUDED ENGINEERING SIGNED AND SEALED BY | | | HABIB JIRJI AZOURI ON ROHN PRODUCTS LLC LETTERHEAD. | | | | | | WHO IS THE ENGINEER OF RECORD? DELEGATED ENGINEERING | | | REQUIRES A REVIEW BY ENGINEER OF RECORD, SEE | | | FAC61G15-23. | | | | | | THE TITLE BLOCK ISSUE REMAINS UNRESOLVED. PLEASE SEE | | | FLORIDA STATUTE 471 AND FLORIDA ADMINISTRATIVE CODE | | | 61G15-23.002. IF ENGINEERS ARE PRACTICING ENGINEERING | | | THROUGH THE COMPANY ROHN PRODUCTS LLC, A CERTIFICATE OF | | | AUTHORIZATION IS REQUIRED. IF ENGINEER IS PRACTICING AS | | | AN INDIVIDUAL, ENGINEERS NEED THEIR OWN TITLE BLOCKS. | | | | | | IT APPEARS THAT BOTH ENGINEERS ARE PRACTICING | | | ENGINEERING THROUGH THE COMPANY ROHN PRODUCTS LLC. IF | | | THIS IS THE CASE, ROHN NEEDS AN ENGINEERING BUSINESS | | | LICENSE NUMBER. | | | | | | IF YOU NEED CLARIFICATION, PLEASE CONTACT ME AT YOUR | | | CONVENIENCE. ALTERNATIVELY, YOU CAN CONTACT FBPE AT | | | 850-521-0500. | | | | | | |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
F |
Date |
2014-07-07 |
|
|
Cont ID |
|
| Sent By |
shill |
Date |
2014-07-07 |
Time |
13:35 |
Rev Time |
0.00 |
| Received By |
shill |
Date |
2014-07-07 |
Time |
13:35 |
Sent To |
E |
|
| Notes |
| 2014-07-07 13:42:01 | ****CORRECTIONS**** | | | | | | SAMANTHA HILL | | | BUILDING PLANS EXAMINER | | | [email protected] | | | 561-805-6724 | | | | | | 1. FS 471 AND FAC61G15-23, TITLE BLOCK FOR ENGINEER IS | | | NOT CLEAR. IS ENGINEER PRACTICING THROUGH ROHN PRODUCTS | | | LLC? CERTIFICATE OF AUTHORIZATION REQUIRED. IF ENGINEER | | | IS NOT PRACTICING THROUGH ROHN PRODUCTS LLC, IT IS NOT | | | CLEAR WHY THE ENGINEER DOES NOT HAVE A TITLE BLOCK ON | | | ANY OF THE SHEETS HE'S TAKING RESPONSIBILITY FOR. | | | | | | EITHER EACH SHEET IS TO BE SIGNED AND SEALED, OR AN | | | INDEX SHEET IS REQUIRED. THE LAWS AND RULES CAN BE | | | FOUND AT WWW.FBPE.ORG. | | | | | | |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
N |
Date |
2014-07-09 |
|
|
Cont ID |
|
| Sent By |
dhayes |
Date |
2014-07-09 |
Time |
11:18 |
Rev Time |
0.00 |
| Received By |
dhayes |
Date |
2014-07-09 |
Time |
11:18 |
Sent To |
|
|
| Notes |
| 2014-07-09 11:30:58 | DATE: 7/9/2014 | | | PROJECT: 50' RADIO TOWER | | | PERMIT#: 14060883 | | | CODE: 2008 EDITION OF THE NEC | | | 2010 EDITION OF THE FBC | | | 2010 WPB AMENDMENTS TO THE FBC, CHAPTER 1, | | | ADMINISTRATION, 2012 FBC SUPPLEMENTS. | | | | | | 1ST ELECTRICAL PLAN REVIEW | | | | | | ACTION: PROVISO | | | | | | NO ELECTRICAL PLANS ARE INCLUDED IN THIS SUBMITTAL. IF | | | ELECTRICAL WORK IS PROPOSED, A SEPARATE ELECTRICAL | | | PERMIT APPLICATION ACCOMPANIED BY PLANS SHALL BE | | | REQUIRED FOR ANY AND ALL ELECTRICAL POWER AND ANTENNA | | | CABLE INSTALLATION. | | | | | | DAVID HAYES, ELECTRICAL PLANS EXAMINER, PX3421, | | | 561-805-6717 OR [email protected] |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2014-08-15 |
|
|
Cont ID |
|
| Sent By |
shill |
Date |
2014-08-15 |
Time |
18:49 |
Rev Time |
0.00 |
| Received By |
shill |
Date |
2014-07-28 |
Time |
15:09 |
Sent To |
Z |
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2014-07-09 |
|
|
Cont ID |
|
| Sent By |
dhayes |
Date |
2014-07-09 |
Time |
11:31 |
Rev Time |
0.00 |
| Received By |
dhayes |
Date |
2014-06-20 |
Time |
12:30 |
Sent To |
Z |
|
| Notes |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
2 |
Status |
P |
Date |
2014-08-11 |
|
|
Cont ID |
|
| Sent By |
eschneid |
Date |
2014-08-11 |
Time |
10:00 |
Rev Time |
0.25 |
| Received By |
eschneid |
Date |
2014-08-11 |
Time |
10:00 |
Sent To |
B |
|
| Notes |
| 2014-08-11 10:01:35 | TOWER IS AN EXEMPT FACILITY UNDER THE CITY'S WIRELESS | | | COMMUNICATIONS ORDINANCE - GOVERNMENT FOR PUBLIC | | | HEALTH. |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
F |
Date |
2014-06-25 |
|
|
Cont ID |
|
| Sent By |
dhayes |
Date |
2014-07-09 |
Time |
11:31 |
Rev Time |
0.75 |
| Received By |
eschneid |
Date |
2014-06-25 |
Time |
08:43 |
Sent To |
B1 |
|
| Notes |
| 2014-06-25 08:53:27 | FAILED | | | | | | 1) THIS TOWER AND THE SUBSEQUENT ANTENNA ATTACHEMENT | | | FALL UNDER THE REVIEW OF THE CITY'S WIRELESS | | | COMMUNICATION FACILITY REGULATIONS. STAFF IS SENDING | | | EDWIN WINKER, CONTRACTOR, A SEPARATE E-MAIL DESCRIBING | | | THE PROCESS AND A COPY OF THE APPLICATION. THE WIRELESS | | | COMMUNICATION APPLICATION SHALL BE APPROVED PRIOR TO | | | THE ZONING APPROVAL OF THIS PERMIT. | | | | | | 2) PROVIDE A SURVEY WHICH INCLUDES THE DISTANCE FROM | | | THE TOWER TO THE PROPERTY LINE ALONG N. JOG ROAD. THE | | | SURVEY DOES NOT NEED TO INCLUDE THE ENTIRE SWAYYY | | | FACILITY, JUST THE AREA COVERED BY THE SCOPE OF WORK. | | | PLEASE NOTE THAT THE SWA HAS THIS BASE INFORMATION | | | SINCE STAFF HAS PREVIOUSLY SEEN IT ON OTHER SWA | | | PROJECTS. THE SURVEY DOES NOT NEED TO BE SIGNED AND | | | SEALED, BUT IT DOES NEED TO BE TO SCALE WITH ACCURATE | | | DIMENSIONS. | | | | | | 3) WILL THE EQUIPMENT CABINETS BE PERMITTED WITH THE | | | ANTENNA INSTALLATION? | | | | | | CONTACT ERIC SCHNEIDER @ (561) 822-1446. | | 2014-06-23 15:07:17 | 6/24/14 ZONING SENT TO JR. SG |
|
|
|