Plan Review Details - Permit 14060003
Plan Review Stops For Permit 14060003
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2014-06-13 Cont ID  
Sent By jwitmer Date 2014-06-13 Time 16:07 Rev Time 0.00
Received By jwitmer Date 2014-06-13 Time 15:40 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2014-09-09 Cont ID  
Sent By dhayes Date 2014-09-09 Time 08:20 Rev Time 0.00
Received By dhayes Date 2014-09-09 Time 07:43 Sent To  
Notes
2014-09-09 07:58:03DATE: 9/9/2014
 PROJECT: IDEAL FLOORING
 PERMIT#: 13030161, REVISION#14060003
 CODE: 2008 EDITION OF THE NEC
 2010 EDITION OF THE FBC
 2010 WPB AMENDMENTS TO THE FBC, CHAPTER 1,
 ADMINISTRATION, 2012 FBC SUPPLEMENTS.
  
 2ND ELECTRICAL PLAN REVIEW
 ACTION: PROVISO
  
 1) PANEL SCHEDULE FOR PANEL MDP DOES NOT INCLUDE THE
 CIRCUIT FOR PANEL "A" THE PLAN INDICATES THAT THE LOAD
 FOR PANEL A IS INCLUDED IN THE PANEL SCHEDULE. PLEASE
 ADJUST THE PANEL SCHEDULE TO REFLECT THE LOAD FOR PANEL
 "A" IN THE PANEL SCHEDULE AND THE LOAD CALCULATION.
  
 2) REVISE THE RISER TO INDICATE THE PIPE WIRE SIZES IN
 THE RISER TO THE WEATHERHEAD.
  
 PROVIDE THIS INFORMATION TO THE INSPECTOR IN THE FIELD
 PRIOR TO FINAL INSPECTION.
  
 DAVID HAYES, ELECTRICAL PLANS EXAMINER, PX3421,
 561-805-6717 OR [email protected]
  

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2014-07-02 Cont ID  
Sent By dhayes Date 2014-07-02 Time 09:37 Rev Time 0.00
Received By dhayes Date 2014-07-01 Time 16:57 Sent To  
Notes
2014-07-01 17:03:11DATE: 7/1/2014
 PROJECT: ELIZABETH FOUNTAIN INTERIORS
 PERMIT#: 14060003
 CODE: 2008 EDITION OF THE NEC
 2010 EDITION OF THE FBC
 2010 WPB AMENDMENTS TO THE FBC, CHAPTER 1,
 ADMINISTRATION, 2012 FBC SUPPLEMENTS.
  
 1ST ELECTRICAL PLAN REVIEW
 ACTION: DENIED
  
 1) ELECTRIC SERVICE RISER WITH WIRE SIZES, CONDUIT
 DETAIL AND GROUNDING DETAIL. COMPLETE LOAD
 CALCULATIONS, PANEL SCHEDULES AND SHOW CIRCUITS ON
 FLOOR PLAN. FBC-R 107.3.5.3
 PANEL SCHEDULE FOR PANEL MDP DOES NOT INCLUDE THE
 CIRCUIT OR THE LOAD FOR PANEL "A" PLEASE ADJUST THE
 PANEL SCHEDULE SO THE LOAD FOR PANEL "A" IS INCLUDED IN
 THE PANEL SCHEDULE AND THE LOAD CALCULATION.
  
 2) THERE ARE SEVERAL 120V LOADS INDICATED ON "B" PHASE
 WHICH IS A HIGH LEG RATED AT APPROXIMATELY 208V TO
 GROUND. PLEASE ADJUST THE PANEL SCHEDULE SO THE 120V
 LOADS ARE INDICATED ON THE APPROPRIATE PHASE.
  
 3) ELECTRIC DRINKING FOUNTAINS SHALL BE PROTECTED WITH
 GROUND-FAULT CIRCUIT-INTERRUPTER PROTECTION. NEC 422.52
  
 4)THE PROVISIONS OF PART II ARE INTENDED TO REQUIRE
 DISCONNECTING MEANS CAPABLE OF DISCONNECTING AIR
 CONDITIONING AND REFRIGERATING EQUIPMENT, INCLUDING
 MOTOR COMPRESSORS
 AND CONTROLLERS FROM THE CIRCUIT CONDUCTORS. NEC 440.11
 SEE ALSO 440.12(A) AND 44.12(A)(1) AND (2) THERE IS NO
 CIRCUIT, LOAD DESIGNATION, DISCONNECT OR REQUIRED
 RECEPTACLE OUTLET INDICATED ON THE PLANS FOR THE
 EXISTING CU ON THE SW CORNER OF THE BUILDING.
  
 5) ONE 125VOLT, SINGLE-PHASE, 15 OR 20AMP GFI
 RECEPTACLE OUTLET SHALL BE INSTALLED AT AN ACCESSIBLE
 LOCATION FOR THE SERVICING OF HEATING,
 AIR-CONDITIONING, AND REFRIGERATION EQUIPMENT. THE
 RECEPTACLE SHALL BE LOCATED ON THE SAME LEVEL AND
 WITHIN 25FT OF THE HEATING, AIR-CONDITIONING, AND
 REFRIGERATION EQUIPMENT. THE RECEPTACLE OUTLET SHALL
 NOT BE CONNECTED TO THE LOAD SIDE OF THE EQUIPMENT
 DISCONNECTING MEANS. NEC 210.63 SEE ALSO 210.8(A)(3) .
 ALL 15 AND 20AMP, 125V AND 250V RECEPTACLES INSTALLED
 IN IN A WET LOCATION SHALL HAVE AN ENCLOSURE THAT IS
 WEATHERPROOF WHETHER OR NOT THE ATTACHMENT PLUG CAP IS
 INSERTED. ALL 15- AND 20-AMPERE, 125- AND 250-VOLT
 NON-LOCKING RECEPTACLES SHALL BE LISTED
 WEATHER-RESISTANT TYPE. NEC 406.8(B)(1) THIS IS JUST
 NOTED FOR THE REQUIRED OUTLETS AT THE RTU AND EXISTING
 CU THAT ARE LOCATED OUTDOORS.
  
 DAVID HAYES, ELECTRICAL PLANS EXAMINER, PX3421,
 561-805-6717 OR [email protected]
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2014-06-11 Cont ID  
Sent By pleduc Date 2014-06-11 Time   Rev Time 0.00
Received By pleduc Date 2014-06-11 Time 14:49 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2014-09-09 Cont ID  
Sent By dhayes Date 2014-09-09 Time 08:20 Rev Time 0.00
Received By dhayes Date 2014-09-04 Time 15:22 Sent To  
Notes
2014-09-04 15:23:04TO DAH DESK
  

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2014-07-02 Cont ID  
Sent By dhayes Date 2014-07-02 Time 09:37 Rev Time 0.00
Received By dhayes Date 2014-06-04 Time 17:07 Sent To  
Notes
2014-06-10 17:07:39B17
  
  
2014-06-04 14:05:306/4 PULLED FROM REVIEW UNTIL REVISION FEE IS PAID
  
2014-06-03 12:05:51B17
  

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2014-07-02 Cont ID  
Sent By shill Date 2014-06-04 Time 17:08 Rev Time 0.00
Received By hmoser Date 2014-06-04 Time 17:08 Sent To  
Notes
2014-06-10 17:08:33PASSED PER J SAEZ
  