Plan Review Details - Permit 14020960
Plan Review Stops For Permit 14020960
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2014-02-28 Cont ID  
Sent By shill Date 2014-02-28 Time 12:34 Rev Time 0.00
Received By shill Date 2014-02-28 Time 12:34 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2014-02-25 Cont ID  
Sent By shill Date 2014-02-25 Time 18:52 Rev Time 0.00
Received By shill Date 2014-02-25 Time 18:52 Sent To  
Notes
2014-02-25 18:52:50****CORRECTIONS****
  
 SAMANTHA HILL, BUILDING PLANS EXAMINER
 561-805-6724
 [email protected]
  
 1. SEE PAGE 9 OF 19, GEOTECHNICAL REPORT PREPARED BY
 GFA:
  
 "THE GROUND IMPROVEMENT PLAN SHOULD BE REVIEWED IN
 CONCERT BY THE GEOTECHNICAL ENGINEER AND STRUCTURAL
 ENGINEER FOR CONFORMANCE WITH THE INTENT OF THE
 FOUNDATION DESIGN. IN ADDITION, THE INSTALLATION OF THE
 PIERS SHOULD BE MONITORED CONTINUOUSLY BY GFA TO VERIFY
 DEPTH OF PIER AND THAT THE PIER IS CONTINUOUS TO THE
 GROUND SURFACE."
  
 THE PLAN HAS BEEN REVIEWED BY THE EOR, BUT NOT BY THE
 GEOTECHNICAL ENGINEER. PLEASE HAVE REVIEWED AND ALSO
 INDICATE INTENT TO HAVE INSTALLATION MONITORED BY GFA.
 THIS MAY BE DONE VIA LETTER.
  
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2014-02-28 Cont ID  
Sent By shill Date 2014-02-28 Time 12:34 Rev Time 0.00
Received By shill Date 2014-02-27 Time 06:32 Sent To  
Notes
2014-02-28 06:32:54INCOMING SENT TO S. HILL DESK. JW

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2014-02-25 Cont ID  
Sent By shill Date 2014-02-25 Time 18:53 Rev Time 0.00
Received By shill Date 2014-02-25 Time 18:53 Sent To  
Notes
***NONE***