Plan Review Details - Permit 14011362
| Plan Review Stops For Permit 14011362 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
2 |
Status |
P |
Date |
2014-03-05 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2014-03-05 |
Time |
13:15 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2014-03-05 |
Time |
11:24 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
F |
Date |
2014-01-24 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2014-01-24 |
Time |
14:34 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2014-01-24 |
Time |
14:34 |
Sent To |
Z |
|
| Notes |
| 2014-01-24 15:08:33 | 2010 FBC | | | | | | DENIED BY BUILDING | | | | | | 1) SPECIFY THE DESIGN DATA ON THE PLANS. THE STRUCTURE | | | IS LOCATED IN A 170 MPH VULT WIND-SPEED AND THE | | | EXPOSURE CATEGORY IS C. FBCR 301.2.1.1 | | | | | | 2) SPECIFY THE REQUIRED DESIGN PRESSURES FOR THE NEW | | | EXTERIOR DOOR OPENING. FBC R301.2.1 | | | | | | 3) SUBMIT TWO COPIES OF PRODUCT APPROVALS FOR THE NEW | | | EXTERIOR DOOR. DCA RULE 9N-3 | | | | | | 4) SHOW COMPLIANCE WITH FBC R318 FOR TERMITE PROTECTION | | | AT NEW SLAB. | | | | | | 5) PROVIDE A DETAIL OF THE TIE BEAMS AT THE NEW CBS | | | WALLS. SPECIFY THE SIZE OF THE BEAM, THE SIZE AND | | | NUMBER OF HORIZONTAL REINFORCING BARS. CITY AMENDMENTS | | | 107.2.1. | | | | | | ROBERT MCDOUGAL | | | BLDG. PLAN REVIEW | | | (561)805-6714 | | | [email protected] |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
N |
Date |
2014-01-24 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2014-01-24 |
Time |
13:58 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2014-01-24 |
Time |
13:58 |
Sent To |
|
|
| Notes |
| 2014-01-24 14:06:25 | NO ELECTRICAL WORK IS SHOWN ON THE PLANS. A SEPARATE | | | PERMIT APPLICATION, PLANS AND REVIEW IS REQUIRED FOR | | | ELECTRIC. |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2014-03-05 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2014-03-05 |
Time |
13:15 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2014-02-12 |
Time |
09:54 |
Sent To |
|
|
| Notes |
| 2014-02-13 09:55:00 | RESUBMITTAL SENT TO R. MCDOUGAL'S DESK FOR REVIEW. JG. |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2014-01-30 |
|
|
Cont ID |
|
| Sent By |
llouie |
Date |
2014-01-30 |
Time |
10:18 |
Rev Time |
0.00 |
| Received By |
llouie |
Date |
2014-01-24 |
Time |
13:46 |
Sent To |
|
|
| Notes |
| 2014-01-24 13:47:17 | SENT TO ZONING |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
1 |
Status |
N |
Date |
2014-03-05 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2014-03-05 |
Time |
13:30 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2014-03-05 |
Time |
13:30 |
Sent To |
|
|
| Notes |
| 2014-03-05 13:32:13 | NO MECHANICAL PLANS WERE SUBMITTED. A SEPARATE | | | APPLICATION, PERMIT AND REVIEWS ARE REQUIRED FOR | | | MECHANICAL. |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
1 |
Status |
P |
Date |
2014-01-24 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2014-01-24 |
Time |
14:06 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2014-01-24 |
Time |
14:06 |
Sent To |
|
|
| Notes |
| 2014-01-24 14:34:41 | A PLUMBING SUB-PERMIT IS REQUIRED TO DEMO AND CAP THE | | | PLUMBING IN THE BATHROOM AND INSTALL NEW FIXTURES IN | | | THE KITCHEN. |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
N |
Date |
2014-01-30 |
|
|
Cont ID |
|
| Sent By |
llouie |
Date |
2014-01-30 |
Time |
10:14 |
Rev Time |
0.00 |
| Received By |
llouie |
Date |
2014-01-30 |
Time |
10:14 |
Sent To |
|
|
| Notes |
| 2014-01-30 10:17:46 | ZONING REVIEW NOT REQUIRED AT THIS TIME. SCOPE OF WORK | | | DOES NOT EXCEED 50 PERCENT OF THE VALUE OF STRUCTURE. |
|
|
|