Plan Review Details - Permit 13120835
Plan Review Stops For Permit 13120835
Review Stop G GAS REVIEW
Rev No 3 Status P Date 2014-07-22 Cont ID  
Sent By rmcdouga Date 2014-07-22 Time 12:52 Rev Time 0.00
Received By rmcdouga Date 2014-07-22 Time 12:52 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 2 Status F Date 2014-06-30 Cont ID  
Sent By rmcdouga Date 2014-06-30 Time 09:22 Rev Time 0.00
Received By rmcdouga Date 2014-06-30 Time 08:15 Sent To  
Notes
2014-06-30 10:03:252010 FBC
  
 GAS PLAN IS DENIED
  
 1) BASED ON THE GAS RISER PLAN THAT WAS SUBMITTED, THE
 LONGEST PIPE RUN FROM THE POINT OF DELIVERY TO THE MOST
 REMOTE OUTLET IS 165 FEET AND THE TOTAL LOAD ON THE
 SYSTEM IS 1,221,000 BTU. THE 3/4" PE PIPE THAT IS
 SPECIFIED IS TOO SMALL. IT IS RATED FOR 791,000 BTU 175
 FEET PER FBCR TABLE G2413.4(8) & TABLE 402.4(20). 1" PE
 PIPE WILL BE REQUIRED FROM THE POINT OF DELIVERY TO THE
 POINT WHERE TO LOAD IS REDUCED TO 791,000 BTU FROM THAT
 POINT IT CAN BE REDUCED TO 3/4" PE PIPE. PLEASE
 CORRECT.
  
 2) THE LENGTH OF THE BRANCH PIPE SECTION, SIZE AND PIPE
 MATERIAL IS NOT SPECIFIED ON THE PLAN FOR THE BBQ. FBCR
 G2413 (402)
  
 3) THE LENGTH OF THE BRANCH PIPE SECTION, AND PIPE
 MATERIAL IS NOT SPECIFIED ON THE PLAN FOR THE POOL
 HEATER. FBCR G2413 (402)
  
 4) THE LENGTH OF THE BRANCH PIPE SECTION AND PIPE
 MATERIAL IS NOT SPECIFIED ON THE PLAN FOR THE FUTURE
 DRYER. FBCR G2413 (402)
  
 5) THE NAME, SIGNATURE AND LICENSE NUMBER OF THE PERSON
 RESPONSIBLE FOR THE DESIGN IS REQUIRED ON THE GAS RISER
 PLANS. CITY AMENDMENTS 107.2.1
  
 ROBERT MCDOUGAL
 BLDG. PLAN REVIEW
 (561)805-6714
 [email protected]

Review Stop G GAS REVIEW
Rev No 1 Status F Date 2014-01-14 Cont ID  
Sent By rmcdouga Date 2014-01-14 Time 10:45 Rev Time 0.00
Received By rmcdouga Date 2014-01-14 Time 06:41 Sent To  
Notes
2014-01-14 08:21:252010 FBC
  
 DENIED
  
 1) SUBMIT TWO LEGIBLE SETS OF A GAS RISER DIAGRAM. THE
 ONES THAT WERE SUBMITTED ARE NOT CLEAR ENOUGH TO BE
 FILED FOR PUBLIC RECORD. CITY AMENDMENTS 107.2.1.4
  
 2) SPECIFY THE DISTANCE FROM EACH SECOND STAGE
 REGULATOR TO THE APPLIANCE, THE PIPING MATERIAL AND
 SIZE PER .5 PSI TABLES. FBCFG 401.8
  
 3) SUBMIT THE SPEC. SHEET FOR THE GAS FIRE PLACE
 EQUIPMENT SHOWING THAT ONLY THE 25,000 BTUS THAT ARE
 SPECIFIED ON THE GAS PLAN IS REQUIRED. OTHERWISE THE
 80,000 BTUS SPECIFIED IN FBC FUEL GAS TABLE 402.2 FOR
 GAS LOGS SHALL BE USED. FBCFG 402.2
  
 4) SUBMIT THE MANUFACTURER'S SPECIFICATIONS THAT
 INDICATE THE REQUIRED BTUS FOR THE GENERATOR. THE
 INFORMATION I GOT ON LINE IS 240,000 BTUS FOR NATURAL
 GAS. 225.000 BTUS IS WHAT IS SPECIFIED ON THE GAS
 DRAWING.
  
 ROBERT MCDOUGAL
 BLDG. PLAN REVIEW
 (561)805-6714
 [email protected]

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2014-07-22 Cont ID  
Sent By rmcdouga Date 2014-07-22 Time 12:52 Rev Time 0.00
Received By rmcdouga Date 2014-07-19 Time 09:12 Sent To  
Notes
2014-07-19 09:13:24SENT TO R MCDOUGAL

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2014-06-30 Cont ID  
Sent By RM Date 2014-06-30 Time 09:22 Rev Time 0.00
Received By rmcdouga Date 2014-06-20 Time 13:43 Sent To G
Notes
***NONE***