Plan Review Details - Permit 13100869
Plan Review Stops For Permit 13100869
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2013-10-26 Cont ID  
Sent By jwitmer Date 2013-10-26 Time 10:00 Rev Time 0.00
Received By jwitmer Date 2013-10-26 Time 09:01 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2013-12-04 Cont ID  
Sent By dharvey Date 2013-12-04 Time 06:47 Rev Time 0.00
Received By dharvey Date 2013-12-04 Time 06:48 Sent To  
Notes
2013-12-27 09:09:25DH HAD NOT STAMPED THE FILE SO I DID IT TODAY

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2013-11-14 Cont ID  
Sent By albarran Date 2013-11-14 Time 08:31 Rev Time 0.00
Received By albarran Date 2013-11-14 Time 08:27 Sent To I
Notes
2013-11-14 08:40:48THE FOLLOWING ITEMS NEED TO BE CORRECTED ON THE
 SUBMITTED DRAWINGS:
 1. THE ELECTRICAL PLANS DO NOT SHOW THE SCOPE OF WORK
 2. THE SINGLE LINE DIAGRAM TERMINATES AT THE NEW
 TRANSFORMER, BUT NO LOAD IS INCLUDED
 3. KEY NOTE 3 ON PAGE E200 ADDRESS A FEEDER TO A NEW
 MCC WHICH IS NOT SHOWN ON THE LINE DIAGRAM.
 4. IF ADDITIONAL WORK BEYOND THE MCC IS TO BE PART OF
 THE SCOPE OF THIS PERMIT, IT TOO HAS TO BE SHOWN ON THE
 SUBMITTED DRAWINGS.
 5. PROVIDE LOAD CALC FOR THE NEW MCC IF ANY LOADS WILL
 BE ATTACHED THERETO.
 6.. PLEASE HAVE THE DESIGN PROFESSIONAL INDICATE WHAT
 AREAS IF ANY ARE TO BE HAZARDOUS LOCATIONS, AND IF SO,
 PROVIDE PROPER SUPPORTING DOCUMENTS FOR THE LIGHT
 FIXTURES AND ALL ELECTRICAL APPARATUS BEING INSTALLED
 WITHIN THIS LOCATION.
  
 IF YOU HAVE ANY QUESTIONS, PLEASE DO NOT HESITATE TO
 CONTACT THIS OFFICE.
  
 SENT TO SH DESK

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2013-11-19 Cont ID  
Sent By wjolin Date 2013-11-19 Time 11:49 Rev Time 0.00
Received By wjolin Date 2013-11-19 Time 11:40 Sent To B
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2013-12-04 Cont ID  
Sent By dharvey Date 2013-12-04 Time 06:47 Rev Time 0.00
Received By dharvey Date 2013-11-20 Time 16:40 Sent To  
Notes
2013-12-27 09:10:10SENT TO SH DESK
  
2013-11-21 16:48:26SENT TO DOUG'S DESK FOR REVIEW. JG.

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2013-11-19 Cont ID  
Sent By shill Date 2013-11-19 Time 18:03 Rev Time 0.00
Received By shill Date 2013-10-23 Time 13:44 Sent To  
Notes
2013-11-15 11:46:1411/15/13 ROUTED TO FIRE BOX.
2013-10-31 18:41:28B09
 ADDED ELEC SHEETS AND APPLICATION SUBMITTED
  
  
2013-10-24 13:46:56B09
  

Review Stop Z ZONING
Rev No 1 Status N Date 2013-11-05 Cont ID  
Sent By eschneid Date 2013-11-05 Time 14:03 Rev Time 0.25
Received By eschneid Date 2013-11-05 Time 14:03 Sent To  
Notes
2013-10-30 14:30:5610/29/13