Plan Review Details - Permit 13040311
Plan Review Stops For Permit 13040311
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time 0.00
Received By tmoore Date 2013-04-11 Time 16:26 Sent To  
Notes
2013-04-11 16:34:00REVIEWING DEMO APPLICATION SHOWING PHASE 1 AND PHASE 2.
 CALLED CONTRACTOR WITH QUESTIONS AND SPOKE WITH GREG
 CELENTANO. AFTER DISCUSSING RELEASES NEEDED AND HIS
 CHALLENGE OF KEEPING THE BUSINESS OPEN AT THE SAME TIME
 AS DEMO WIOULD PROCEED, DECIDED THAT HE WILL TALK WITH
 ENGINEERING FIRST. THAT AN ENGINEERING PERMIT MIGHT BE
 MORE BENEFICIAL AT THIS TIME AND POSSIBLY HOLD OFF ON
 THE DEMO PERMIT AND INCLUDE IT WITH THE BUILDING
 PERMIT.
 PUTTING THE APPLICATION IN SMALL FILE CABINET UNDER "A"
 FOR AHRENS COMPANIES.

Review Stop ENG ENGINEERING CSD
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop HIST HISTORICAL
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved