| 2013-01-09 11:56:20 | *** CORRECTIONS NEED TO MECHANICAL PLANS*** |
| | |
| | 1) ENERGY CALCULATIONS SUBMITTED ARE NOT THE COMPLETE |
| | SET PLEASE SUBMIT THE COMPLETE PRINTED SET OR MEET THE |
| | EXCEPTION NOTED BELOW. PER 2010 FBC/ENERGY 503.2 |
| | PROVISIONS APPLICABLE TO ALL MECHANICAL SYSTEMS |
| | (MANDATORY). |
| | 503.2.1 CALCULATION OF HEATING AND COOLING LOADS. |
| | DESIGN LOADS SHALL BE DETERMINED IN ACCORDANCE WITH THE |
| | PROCEDURES DESCRIBED IN THE ASHRAE/ACCA STANDARD 183 OR |
| | ACCA MANUAL N AND SHALL BE ATTACHED TO THE CODE |
| | COMPLIANCE FORM SUBMITTED TO THE BUILDING DEPARTMENT |
| | WHEN THE BUILDING IS PERMITTED OR, IN THE EVENT THE |
| | MECHANICAL PERMIT IS OBTAINED AT A LATER TIME, THE |
| | SIZING CALCULATION SHALL BE SUBMITTED WITH THE |
| | APPLICATION FOR THE MECHANICAL PERMIT. HEATING AND |
| | COOLING LOADS SHALL BE ADJUSTED TO ACCOUNT FOR LOAD |
| | REDUCTIONS THAT ARE ACHIEVED WHEN ENERGY RECOVERY |
| | SYSTEMS ARE UTILIZED IN THE HVAC SYSTEM IN ACCORDANCE |
| | WITH THE ASHRAE HVAC SYSTEMS AND EQUIPMENT HANDBOOK. |
| | ALTERNATIVELY, DESIGN LOADS SHALL BE DETERMINED BY AN |
| | APPROVED EQUIVALENT COMPUTATION PROCEDURE, USING THE |
| | DESIGN PARAMETERS SPECIFIED IN CHAPTER 3. |
| | |
| | EXCEPTION: WHERE MECHANICAL SYSTEMS ARE DESIGNED BY AN |
| | ENGINEER REGISTERED IN THE STATE OF FLORIDA, THE |
| | ENGINEER HAS THE OPTION OF SUBMITTING A SIGNED AND |
| | SEALED SUMMARY SHEET TO THE BUILDING DEPARTMENT IN LIEU |
| | OF THE COMPLETE SIZING CALCULATION(S). SUCH SUMMARY |
| | SHEET SHALL INCLUDE THE FOLLOWING (BY ZONE): |
| | 1. PROJECT NAME/OWNER |
| | 2. PROJECT ADDRESS |
| | 3. AREA IN SQUARE FEET |
| | 4. SIZING METHOD USED |
| | 5. OUTDOOR DRY BULB USE |
| | 6. INDOOR DRY BULB |
| | 7. OUTDOOR WET BULB USED |
| | 8. GRAINS WATER (DIFFERENCE) |
| | 9. TOTAL SENSIBLE GAIN |
| | 10. TOTAL LATENT GAIN |
| | 11. RELATIVE HUMIDITY |
| | 12. TOTAL COOLING REQUIRED WITH OUTSIDE AIR |
| | 13. TOTAL HEATING REQUIRED WITH OUTSIDE AIR |
| | |
| | 2) PER 2010 FBC 107.2.1 INFORMATION ON CONSTRUCTION |
| | DOCUMENTS. |
| | CONSTRUCTION DOCUMENTS SHALL BE DIMENSIONED AND DRAWN |
| | UPON SUITABLE MATERIAL. ELECTRONIC MEDIA DOCUMENTS ARE |
| | PERMITTED TO BE SUBMITTED WHEN APPROVED BY THE BUILDING |
| | OFFICIAL. CONSTRUCTION DOCUMENTS SHALL BE OF SUFFICIENT |
| | CLARITY TO INDICATE THE LOCATION, NATURE AND EXTENT OF |
| | THE WORK PROPOSED AND SHOW IN DETAIL THAT IT WILL |
| | CONFORM TO THE PROVISIONS OF THIS CODE AND RELEVANT |
| | LAWS, ORDINANCES, RULES AND REGULATIONS, AS DETERMINED |
| | BY THE BUILDING OFFICIAL. |
| | |
| | 3) PER 2010 FBC/B 107.3.5. MINIMUM PLAN REVIEW CRITERIA |
| | FOR COMMERCIAL BUILDINGS. |
| | MECHANICAL |
| | 3. EQUIPMENT |
| | 4. EQUIPMENT LOCATION |
| | 5. MAKE-UP AIR |
| | 6. ROOF-MOUNTED EQUIPMENT |
| | 7. DUCT SYSTEMS |
| | 8. VENTILATION |
| | 16. DESIGN FLOOD ELEVATION |
| | |
| | 4) EXPLAIN THE USE OF THE BUILDING AND THE FLOOR PLAN |
| | FOR PROPER PLAN REVIEW. |
| | |
| | 5) MECHANICAL PLAN SUBMITTED DOES NOT SHOW IF THE AHU'S |
| | ARE HANGING OR ON STANDS, WHAT SIZE THE DUCTS ARE, |
| | LOCATION OF RETURN AIR GRILLS, SUPPLY GRILL SIZES, |
| | WHERE THE CONDENSATE LINES DRAIN TO, IF THE CONDENSER |
| | UNITS ARE ON THE ROOF OR SIDE OF BUILDING, HOW THE |
| | FRESH AIR IS CONNECTING TO THE AHU'S, WHAT'S EXISTING |
| | AND WHATS NEW, MAKE, MODEL, SIZE, SEER, BTU'S TOTAL & |
| | SENSIBLE, ETC. OF THE A/C SYSTEMS. CONSTRUCTION |
| | DOCUMENTS SHALL BE OF SUFFICIENT CLARITY TO INDICATE |
| | THE LOCATION, NATURE AND EXTENT OF THE WORK PROPOSED |
| | AND SHOW IN DETAIL THAT IT WILL CONFORM TO THE |
| | PROVISIONS OF THIS CODE AND RELEVANT LAWS, PER 2010 |
| | CITY OF WPB AMEND. 107.2.1. |
| | |
| | 6) IF CONDENSER UNITS ARE ON THE ROOF SUBMIT AN UP TO |
| | DATE PRODUCT APPROVAL FOR THE A/C CONDENSER STAND. |
| | FLORIDA DEPARTMENT OF COMMUNITY AFFAIRS RULE 9B-72 JAN. |
| | 1, 2006. (31) SUB-CATEGORY OF PRODUCTS OR CONSTRUCTION |
| | SYSTEMS THAT WILL REQUIRE PRODUCT APPROVALS: (G) |
| | EXTERIOR COOLER, FREEZERS & "PER-ENGINEERED A/C |
| | STANDS". |
| | |
| | 7) PROVE OUT DOOR AIR CALCULATIONS AND OUT DOOR AIR, |
| | PER 2010 FBC/M 403.3. |
| | |
| | 8) SHOW COMPLIANCE WITH 2010 FBC/ENERGY 503.2.4.4 |
| | SHUTOFF DAMPER CONTROLS (FOR OUT DOOR AIR INTAKE). BOTH |
| | OUTDOOR AIR SUPPLY AND EXHAUST DUCTS SHALL BE EQUIPPED |
| | WITH DAMPERS THAT WILL AUTOMATICALLY SHUT WHEN THE |
| | SYSTEMS OR SPACES SERVED ARE NOT IN USE. |
| | |
| | MECHANICAL PLAN REVIEW BY: |
| | TOM GORDON (HY-BYRD INC.) (561) 805-6732 |
| | |
| | |