Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2013-01-09 Cont ID  
Sent By tgordon Date 2013-01-09 Time 12:05 Rev Time 0.00
Received By tgordon Date 2013-01-07 Time 14:17 Sent To  
Notes
2013-01-07 14:18:25TO MECHANICAL

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2013-01-30 Cont ID  
Sent By hmoser Date 2013-01-30 Time 10:01 Rev Time 0.00
Received By hmoser Date 2013-01-30 Time 09:40 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status F Date 2013-01-09 Cont ID  
Sent By tgordon Date 2013-01-09 Time 12:05 Rev Time 0.00
Received By tgordon Date 2013-01-09 Time 11:49 Sent To  
Notes
2013-01-09 11:56:20*** CORRECTIONS NEED TO MECHANICAL PLANS***
  
 1) ENERGY CALCULATIONS SUBMITTED ARE NOT THE COMPLETE
 SET PLEASE SUBMIT THE COMPLETE PRINTED SET OR MEET THE
 EXCEPTION NOTED BELOW. PER 2010 FBC/ENERGY 503.2
 PROVISIONS APPLICABLE TO ALL MECHANICAL SYSTEMS
 (MANDATORY).
 503.2.1 CALCULATION OF HEATING AND COOLING LOADS.
 DESIGN LOADS SHALL BE DETERMINED IN ACCORDANCE WITH THE
 PROCEDURES DESCRIBED IN THE ASHRAE/ACCA STANDARD 183 OR
 ACCA MANUAL N AND SHALL BE ATTACHED TO THE CODE
 COMPLIANCE FORM SUBMITTED TO THE BUILDING DEPARTMENT
 WHEN THE BUILDING IS PERMITTED OR, IN THE EVENT THE
 MECHANICAL PERMIT IS OBTAINED AT A LATER TIME, THE
 SIZING CALCULATION SHALL BE SUBMITTED WITH THE
 APPLICATION FOR THE MECHANICAL PERMIT. HEATING AND
 COOLING LOADS SHALL BE ADJUSTED TO ACCOUNT FOR LOAD
 REDUCTIONS THAT ARE ACHIEVED WHEN ENERGY RECOVERY
 SYSTEMS ARE UTILIZED IN THE HVAC SYSTEM IN ACCORDANCE
 WITH THE ASHRAE HVAC SYSTEMS AND EQUIPMENT HANDBOOK.
 ALTERNATIVELY, DESIGN LOADS SHALL BE DETERMINED BY AN
 APPROVED EQUIVALENT COMPUTATION PROCEDURE, USING THE
 DESIGN PARAMETERS SPECIFIED IN CHAPTER 3.
  
 EXCEPTION: WHERE MECHANICAL SYSTEMS ARE DESIGNED BY AN
 ENGINEER REGISTERED IN THE STATE OF FLORIDA, THE
 ENGINEER HAS THE OPTION OF SUBMITTING A SIGNED AND
 SEALED SUMMARY SHEET TO THE BUILDING DEPARTMENT IN LIEU
 OF THE COMPLETE SIZING CALCULATION(S). SUCH SUMMARY
 SHEET SHALL INCLUDE THE FOLLOWING (BY ZONE):
 1. PROJECT NAME/OWNER
 2. PROJECT ADDRESS
 3. AREA IN SQUARE FEET
 4. SIZING METHOD USED
 5. OUTDOOR DRY BULB USE
 6. INDOOR DRY BULB
 7. OUTDOOR WET BULB USED
 8. GRAINS WATER (DIFFERENCE)
 9. TOTAL SENSIBLE GAIN
 10. TOTAL LATENT GAIN
 11. RELATIVE HUMIDITY
 12. TOTAL COOLING REQUIRED WITH OUTSIDE AIR
 13. TOTAL HEATING REQUIRED WITH OUTSIDE AIR
  
 2) PER 2010 FBC 107.2.1 INFORMATION ON CONSTRUCTION
 DOCUMENTS.
 CONSTRUCTION DOCUMENTS SHALL BE DIMENSIONED AND DRAWN
 UPON SUITABLE MATERIAL. ELECTRONIC MEDIA DOCUMENTS ARE
 PERMITTED TO BE SUBMITTED WHEN APPROVED BY THE BUILDING
 OFFICIAL. CONSTRUCTION DOCUMENTS SHALL BE OF SUFFICIENT
 CLARITY TO INDICATE THE LOCATION, NATURE AND EXTENT OF
 THE WORK PROPOSED AND SHOW IN DETAIL THAT IT WILL
 CONFORM TO THE PROVISIONS OF THIS CODE AND RELEVANT
 LAWS, ORDINANCES, RULES AND REGULATIONS, AS DETERMINED
 BY THE BUILDING OFFICIAL.
  
 3) PER 2010 FBC/B 107.3.5. MINIMUM PLAN REVIEW CRITERIA
 FOR COMMERCIAL BUILDINGS.
 MECHANICAL
 3. EQUIPMENT
 4. EQUIPMENT LOCATION
 5. MAKE-UP AIR
 6. ROOF-MOUNTED EQUIPMENT
 7. DUCT SYSTEMS
 8. VENTILATION
 16. DESIGN FLOOD ELEVATION
  
 4) EXPLAIN THE USE OF THE BUILDING AND THE FLOOR PLAN
 FOR PROPER PLAN REVIEW.
  
 5) MECHANICAL PLAN SUBMITTED DOES NOT SHOW IF THE AHU'S
 ARE HANGING OR ON STANDS, WHAT SIZE THE DUCTS ARE,
 LOCATION OF RETURN AIR GRILLS, SUPPLY GRILL SIZES,
 WHERE THE CONDENSATE LINES DRAIN TO, IF THE CONDENSER
 UNITS ARE ON THE ROOF OR SIDE OF BUILDING, HOW THE
 FRESH AIR IS CONNECTING TO THE AHU'S, WHAT'S EXISTING
 AND WHATS NEW, MAKE, MODEL, SIZE, SEER, BTU'S TOTAL &
 SENSIBLE, ETC. OF THE A/C SYSTEMS. CONSTRUCTION
 DOCUMENTS SHALL BE OF SUFFICIENT CLARITY TO INDICATE
 THE LOCATION, NATURE AND EXTENT OF THE WORK PROPOSED
 AND SHOW IN DETAIL THAT IT WILL CONFORM TO THE
 PROVISIONS OF THIS CODE AND RELEVANT LAWS, PER 2010
 CITY OF WPB AMEND. 107.2.1.
  
 6) IF CONDENSER UNITS ARE ON THE ROOF SUBMIT AN UP TO
 DATE PRODUCT APPROVAL FOR THE A/C CONDENSER STAND.
 FLORIDA DEPARTMENT OF COMMUNITY AFFAIRS RULE 9B-72 JAN.
 1, 2006. (31) SUB-CATEGORY OF PRODUCTS OR CONSTRUCTION
 SYSTEMS THAT WILL REQUIRE PRODUCT APPROVALS: (G)
 EXTERIOR COOLER, FREEZERS & "PER-ENGINEERED A/C
 STANDS".
  
 7) PROVE OUT DOOR AIR CALCULATIONS AND OUT DOOR AIR,
 PER 2010 FBC/M 403.3.
  
 8) SHOW COMPLIANCE WITH 2010 FBC/ENERGY 503.2.4.4
 SHUTOFF DAMPER CONTROLS (FOR OUT DOOR AIR INTAKE). BOTH
 OUTDOOR AIR SUPPLY AND EXHAUST DUCTS SHALL BE EQUIPPED
 WITH DAMPERS THAT WILL AUTOMATICALLY SHUT WHEN THE
 SYSTEMS OR SPACES SERVED ARE NOT IN USE.
  
 MECHANICAL PLAN REVIEW BY:
 TOM GORDON (HY-BYRD INC.) (561) 805-6732
  
  