Plan Review Details - Permit 12070517
| Plan Review Stops For Permit 12070517 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
P |
Date |
2012-07-23 |
|
|
Cont ID |
|
| Sent By |
jgomez |
Date |
2012-07-23 |
Time |
16:06 |
Rev Time |
0.00 |
| Received By |
jgomez |
Date |
2012-07-23 |
Time |
15:58 |
Sent To |
|
|
| Notes |
| 2012-07-23 16:10:18 | CONCRETE TILE PRODUCT APPROVAL. |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
P |
Date |
2012-07-19 |
|
|
Cont ID |
|
| Sent By |
rlecky |
Date |
2012-07-19 |
Time |
10:56 |
Rev Time |
0.00 |
| Received By |
rlecky |
Date |
2012-07-19 |
Time |
09:49 |
Sent To |
M |
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2012-08-07 |
|
|
Cont ID |
|
| Sent By |
jgomez |
Date |
2012-08-07 |
Time |
14:07 |
Rev Time |
0.00 |
| Received By |
jgomez |
Date |
2012-08-07 |
Time |
14:07 |
Sent To |
|
|
| Notes |
| 2012-08-07 14:07:37 | REVISION RE-SUBMITTAL. JG. |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2012-07-24 |
|
|
Cont ID |
|
| Sent By |
jgomez |
Date |
2012-07-24 |
Time |
16:25 |
Rev Time |
0.00 |
| Received By |
jgomez |
Date |
2012-07-17 |
Time |
14:21 |
Sent To |
|
|
| Notes |
| 2012-07-18 14:24:04 | SENT TO ROBERT LECKY'S DESK FOR REVIEW. JG. |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
2 |
Status |
P |
Date |
2012-08-07 |
|
|
Cont ID |
|
| Sent By |
jgomez |
Date |
2012-08-07 |
Time |
14:07 |
Rev Time |
0.00 |
| Received By |
jgomez |
Date |
2012-08-07 |
Time |
14:07 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
1 |
Status |
F |
Date |
2012-07-24 |
|
|
Cont ID |
|
| Sent By |
jgomez |
Date |
2012-07-24 |
Time |
15:49 |
Rev Time |
0.00 |
| Received By |
jgomez |
Date |
2012-07-23 |
Time |
14:27 |
Sent To |
|
|
| Notes |
| 2012-07-24 16:24:58 | REVISION MECHANICAL REVIEW COMMENTS. | | | CODE: 2007 FBC W/ 2009 REVISIONS. | | | | | | 1- INFORMATION ON ENERGY CALCULATIONS, RESIDENTIAL | | | SYSTEM SIZING CALCULATIONS AND EQUIPMENT SIZE | | | INFORMATION ON SHEET M-1 DON'T MATCH. REVISE AS | | | REQUIRED. | | | SEC. 106.1.1 AND SEC. 13-607.AB.1. | | | CHECK TOTAL LOAD CALCULATIONS, SEER, ETC. | | | | | | 2- COOLING EQUIPMENT CAPACITY CAN'T BE MORE THAN 1.15 | | | TIMES GREATER THAN THE TOTAL LOAD CALCULATED. REVISE AS | | | REQUIRED TO COMPLY. SEC. 13-607.AB.1.1. | | | COORDINATE WITH THE ENERGY CALCULATIONS, EQUIPMENT | | | SIZING CALCULATIONS AND PLAN M-1. | | | | | | 3- TRANSFER DUCTS SHOWN ON PLAN M-1 FOR MASTER BEDROOM | | | AND ADJACENT BEDROOM DON'T COMPLY WITH THE BALANCED | | | RETURN AIR SEC. M1602.4. REVISE AS REQUIRED. | | | | | | IF YOU HAVE ANY QUESTIONS, PLEASE CALL | | | JULIO GOMEZ | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561)805-6712 |
|
|
|