| 2012-03-16 13:25:40 | RE-ROOF BUILDING REVIEW COMMENTS. |
| | 2007 FBC WITH 2009 REVISIONS. |
| | |
| | 1- PROVIDE MOISTURE TESTING RESULTS AS REQUIRED BY RAS |
| | 109 (SEE SURFACE PREPARATION REQUIREMENTS ON SELECTED |
| | APPROVED ASSEMBLY) AND RECOVER SYSTEM LIMITATION #1 ON |
| | NOA 09-0610.06 SUBMITTED. |
| | |
| | 2- PROVIDE UPLIFT RESISTANCE TEST RESULTS AS REQUIRED |
| | BY TAS 124 AND RECOVER SYSTEM LIMITATION #2 ON NOA |
| | 09-0610.06 SUBMITTED. |
| | |
| | 3- PROVIDE PRODUCT APPROVAL (2 COPIES) OF PROTECTED |
| | ROOF COATING AS REQUIRED PROTECTIVE COATING APPLICATION |
| | ON SELECTED APPROVED ASSEMBLY OF NOA 09-0610.06 |
| | SUBMITTED. |
| | |
| | 4- CLEARLY IDENTIFY WHICH APPROVED ASSEMBLY (PAGE 4 OR |
| | PAGE 5) OF NOA SUBMITTED IS GOING TO BE INSTALLED. SEC. |
| | 106.1.1 OF CITY AMENDMENTS TO FBC. |
| | |
| | 5- PROVIDE RECORDED NOTICE OF COMMENCEMENT AS REQUIRED |
| | BY SEC. 713.13 FLORIDA STATUTES. THIS SCOPE OF WORK IS |
| | NOT REFERENCED IN THE MASTER PERMIT 12030342. |
| | |
| | ***NOTE; FOR YOUR INFORMATION: |
| | A) ROOF WASHING IS NOT PERMITTED. |
| | B) CONTRACTOR REQUIRED TO MAINTAIN JOB LOG IN |
| | COMPLIANCE WITH RAS 109. |
| | C) ANY ROOF EQUIPMENT REMOVAL REQUIRES SEPARATE PERMIT. |
| | D) ANY RETROFIT ROOF DRAINS REQUIRE PLUMBING REVIEW. |
| | |
| | IF YOU HAVE ANY QUESTIONS PLEASE CALL |
| | JULIO GOMEZ |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | (561)805-6712 |