Plan Review Details - Permit 11100500
| Plan Review Stops For Permit 11100500 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
N |
Date |
2011-11-28 |
|
|
Cont ID |
|
| Sent By |
jwitmer |
Date |
2011-11-16 |
Time |
08:11 |
Rev Time |
0.00 |
| Received By |
jwitmer |
Date |
2011-11-16 |
Time |
08:11 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
P |
Date |
2011-10-27 |
|
|
Cont ID |
|
| Sent By |
rlecky |
Date |
2011-10-27 |
Time |
08:56 |
Rev Time |
0.00 |
| Received By |
rlecky |
Date |
2011-10-27 |
Time |
08:29 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
ENG |
ENGINEERING CSD |
| Rev No |
1 |
Status |
P |
Date |
2011-11-03 |
|
|
Cont ID |
|
| Sent By |
|
Date |
2011-11-03 |
Time |
|
Rev Time |
0.50 |
| Received By |
|
Date |
2011-11-03 |
Time |
|
Sent To |
|
|
| Notes |
| 2011-11-03 16:16:03 | PASSED WITH PROVISOS: | | | | | | #1 ALL ROW IRRIGATION OR PIPING SHOULD BE INSTALLED IN | | | ROW FOR THE PURPOSE | | | OF MAINTENANCE AN ACCESSABILITY. (2 1/2" CONDUIT GIVES | | | DIRECTION TO INSTALL IN ROW HOWEVER IT IS NOT SHOWN AS | | | SUCH.) | | | FOR EXAMPLE IN L14 | | | | | | #2 POLES INCLUDED WILL NEED SEPARATE STRUCTURAL PERMIT | | | WITH ADDRESSING STRUCTURAL ASPECT AND HURRICANE RATING. | | | | | | #3 PAVERS AND STAMPED CONCRETE ARE NO IDENTIFIED. | | | | | | #4 CONCRETE IN THE ROW IS SPECIFIED AS 2500PSI AND 4" | | | THINK. OUR CITY STANDARD IS 6" THICK 3000PSI PORTLAND. | | | | | | #5 SET SUBMITTED IS NOT SIGNED AND SEALED. UPON | | | SUBMITTING SIGNED AND SEALED PLANS THEN CSD ENGINEERING | | | WILL STAMP AND SIGN. | | | | | | MANUEL JULIAN GONZALEZ | | | CSD ENGNIEERING REVIEW | | | 401 CLEMATIS STREET, | | | WEST PALM BEACH, FL 33401 | | | (MAILING ADDRESS: P.O. BOX 3366, ZIP 33402) | | | MAIN PHONE: (561) 822-1200 | | | DIRECT: (561) 494-1085 | | | FAX: (561) 494-1116 | | | MOBILE: (561) 644-7301 | | | EMAIL: [email protected] | | | WWW.WPB.ORG/ENGINEERING | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
| Review Stop |
FIRE |
FIRE DEPARTMENT |
| Rev No |
1 |
Status |
P |
Date |
2011-10-26 |
|
|
Cont ID |
|
| Sent By |
wjolin |
Date |
2011-10-26 |
Time |
11:21 |
Rev Time |
0.00 |
| Received By |
wjolin |
Date |
2011-10-26 |
Time |
11:09 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2011-12-06 |
|
|
Cont ID |
|
| Sent By |
shill |
Date |
2011-12-06 |
Time |
16:22 |
Rev Time |
0.00 |
| Received By |
shill |
Date |
2011-10-21 |
Time |
10:21 |
Sent To |
|
|
| Notes |
| 2011-10-24 15:33:09 | SENT TO C2 SHELF FOR REVIEW. JG. |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
1 |
Status |
P |
Date |
2011-11-04 |
|
|
Cont ID |
|
| Sent By |
lwagner |
Date |
2011-11-04 |
Time |
10:35 |
Rev Time |
0.00 |
| Received By |
lwagner |
Date |
2011-11-04 |
Time |
09:25 |
Sent To |
|
|
| Notes |
| 2011-11-04 10:18:11 | IRRIGATION PERMIT REQUIRED | | | | | | DRAWINGS REQUIRE SEAL BEFORE ISSUANCE. | | | | | | ****PROVISO**** | | | 1. RAIN SENSOR IS REQUIRED PER F.S. 373.62 WATER | | | CONSERVATION; AUTOMATIC SPRINKLER SYSTEMS. | | | | | | 2. PLUMBING PERMIT WILL BE REQUIRED IF INSTALLING A NEW | | | BACKFLOW PREVENTION DEVICE. | | | |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
2 |
Status |
|
Date |
|
|
|
Cont ID |
|
| Sent By |
|
Date |
|
Time |
|
Rev Time |
0.00 |
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
F |
Date |
2011-12-06 |
|
|
Cont ID |
|
| Sent By |
aaponte |
Date |
2011-12-06 |
Time |
15:22 |
Rev Time |
0.00 |
| Received By |
aaponte |
Date |
2011-12-06 |
Time |
15:22 |
Sent To |
|
|
| Notes |
| 2011-12-06 15:22:57 | A. THERE ARE SOME OF THE PEDESTRIAN LIGHT POLES LOCATED | | | IN THE MIDDLE OF THE SIDEWALK. PLEASE RELOCATE AS MUCH | | | AS POSSIBLE TO THE EDGES (EG. POLE #14CKT). | | | B. DETAIL NOTES ABOUT THE INSTALLATION OF PERENNIAL | | | PEANUT SHALL BE INCLUDED. DO WE NEED NOTES ABOUT THE | | | SOD? IT IS NOT INCLUDED IN PROJECT. | | | C. SHEET L-8. CAN WE ADD 2 MORE OAKS IN THE MIDDLE | | | SECTION? | | | D. THE WIDTH OF THE PEDESTRIAN CROSSINGS WITHIN THE | | | MEDIAN IS NOT CONSISTENT WITH THE CROSSWALK. CAN WE | | | WIDEN THE MEDIAN CROSSING? | | | E. CROSSWALK AT HIBISCUS SHOWS PAVERS IN THE MIDDLE | | | PORTION. THE OTHERS DON'T. | | | F. COVER PAGE IN FDOT FORMAT. FM NUMBER? | | | G. IRRIGATION COMMENTS SUBMITTED EARLIER BY TIM | | | KRISCHE. | | | H. L-2. CAN WE LEAVE PEDESTRIAN CROSSING CLOSER TO THE | | | INTERSECTION? | | | I. L-2. LAYOUT STARTS FROM HIBISCUS. SOUTH PORTION | | | OMITTED. IT IS CONFUSING NOT TO HAVE THE ENTIRE | | | PROJECT. | | | J. CAN WE INCLUDE THE MISSING ROYAL PALM ON THE EAST | | | SIDE BETWEEN LAKEVIEW AND OKEECHOBEE? |
|
|
|
Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved |
 |
 |