| Plan Review Stops For Permit 11100456 |
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2011-10-21 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2011-10-21 |
Time |
08:06 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2011-10-20 |
Time |
10:37 |
Sent To |
|
|
| Notes |
| 2011-10-20 10:40:15 | *****************EXPEDITED**************** | | | GAVE TO ROBBIE |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
1 |
Status |
P |
Date |
2011-10-21 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2011-10-21 |
Time |
08:06 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2011-10-21 |
Time |
08:06 |
Sent To |
|
|
| Notes |
| 2011-10-21 08:24:03 | MECHANICAL PROVISO | | | | | | 1) PLENUM AT MECHANICAL CLOSET IS REQUIRED BY FBCM | | | 602.2.1 TO HAVE A PLENUM RATED NON-COMBUSTIBLE DOOR. | | | | | | 2) DUCT SMOKE DETECTORS ARE REQUIRED ON SUPPLY AIR | | | SYSTEMS IN ACCORDANCE WITH FBCM 602. | | | | | | 3) ACCESS SHALL BE PROVIDED TO DUCT SMOKE DETECTORS FOR | | | INSPECTION AND MAINTENANCE PER FBCM 606.3. | | | | | | 4) SUBMIT PRODUCT APPROVALS FOR THE ROOF MOUNTED ACU | | | STANDS. PROVIDE ENGINEERING FOR THE ANCHORING OF THE | | | STANDS INCLUDING THE SUBSTRATE TO WHICH THE STANDS ARE | | | ATTACHED IN COMPLIANCE WITH FBCM 301.12. |
|
|
|