Plan Review Details - Permit 11040776
| Plan Review Stops For Permit 11040776 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
2 |
Status |
P |
Date |
2011-05-10 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2011-05-10 |
Time |
11:30 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2011-05-10 |
Time |
11:30 |
Sent To |
|
|
| Notes |
| 2011-05-10 11:34:08 | CHANGED FROM SPRAY FOAM TO R-30 BATT INSULATION. |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
P |
Date |
2011-05-05 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2011-05-05 |
Time |
08:48 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2011-05-05 |
Time |
07:48 |
Sent To |
|
|
| Notes |
| 2011-05-05 08:45:43 | PROVISO | | | | | | SUBMIT SPECIFICATIONS FOR THE SPRAY FOAM INSULATION. IF | | | WOOD ROOF DECK IS COVERED WITH PEEL AND STICK | | | UNDERLAYMENT, THEN SEE APA TECHNICAL BULLETIN TT-111. |
|
|
| Review Stop |
E |
ELECTRICAL |
| Rev No |
1 |
Status |
P |
Date |
2011-05-05 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2011-05-05 |
Time |
11:31 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2011-05-05 |
Time |
09:00 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2011-05-05 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2011-05-05 |
Time |
11:31 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2011-05-02 |
Time |
09:44 |
Sent To |
|
|
| Notes |
| 2011-05-02 09:45:09 | SENT TO R9. |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
2 |
Status |
N |
Date |
2011-05-10 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2011-05-10 |
Time |
11:09 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2011-05-10 |
Time |
11:09 |
Sent To |
|
|
| Notes |
| 2011-05-10 11:16:28 | PER ROGER THOMAS, THE MECHANICAL CONTRACTOR WILL SUBMIT | | | SEPARATELY. A SEPARATE PERMIT APPLICATION, PLANS AND | | | ENERGY CALCULATIONS WILL BE REQUIRED. |
|
|
| Review Stop |
M |
MECHANICAL (A/C) |
| Rev No |
1 |
Status |
F |
Date |
2011-05-05 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2011-05-05 |
Time |
07:06 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2011-05-05 |
Time |
07:06 |
Sent To |
|
|
| Notes |
| 2011-05-05 07:39:20 | 2007 FBC W/2009 REVISIONS | | | | | | DENIED BY MECHANICAL | | | | | | 1) SUBMIT TWO SETS OF MECHANICAL PLANS SPECIFYING THE | | | LOCATION AND SIZES OF THE NEW SUPPLY AND RETURN DUCTS, | | | TRANSFER DUCTS, TRANSFER GRILLS, ETC. SPECIFY THE GRILL | | | SIZES, LOCATIONS AND CFMS ON THE PLANS. CITY AMENDMENTS | | | 106.3.5.4 | | | | | | 2) THE NAME, SIGNATURE AND LICENSE NUMBER OF THE HVAC | | | CONTRACTOR OR TITLE BLOCK, SIGNATURE AND SEALED OF THE | | | DESIGN PROFESSIONAL IS REQUIRED ON THE MECHANICAL | | | PLANS. CITY AMENDMENTS 106.1.3 | | | | | | 3) SUBMIT ENERGY CALCULATIONS AND EQUIPMENT SIZING | | | CALCULATIONS TO VERIFY THAT THE EXISTING HVAC SYSTEM | | | WILL BE ADEQUATE FOR THE ADDITIONAL LOAD. CITY | | | AMENDMENTS 106.3.5.4 | | | | | | ROBERT MCDOUGAL | | | BLDG. PLAN REVIEW | | | (561)805-6714 | | | [email protected] |
|
|
| Review Stop |
P |
PLUMBING |
| Rev No |
1 |
Status |
P |
Date |
2011-05-05 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2011-05-05 |
Time |
07:06 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2011-05-05 |
Time |
07:06 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
N |
Date |
2011-05-05 |
|
|
Cont ID |
|
| Sent By |
rmcdouga |
Date |
2011-05-05 |
Time |
08:49 |
Rev Time |
0.00 |
| Received By |
rmcdouga |
Date |
2011-05-05 |
Time |
08:49 |
Sent To |
|
|
| Notes |
|
|
|
Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved |
 |
 |