| Plan Review Stops For Permit 11040708 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
P |
Date |
2011-05-10 |
|
|
Cont ID |
|
| Sent By |
shill |
Date |
2011-05-10 |
Time |
14:44 |
Rev Time |
0.00 |
| Received By |
shill |
Date |
2011-05-10 |
Time |
14:44 |
Sent To |
|
|
| Notes |
| 2011-04-27 15:33:53 | SENT TO ZONING BOX. JW |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2011-05-10 |
|
|
Cont ID |
|
| Sent By |
shill |
Date |
2011-05-10 |
Time |
14:44 |
Rev Time |
0.00 |
| Received By |
shill |
Date |
2011-04-27 |
Time |
15:33 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
2 |
Status |
P |
Date |
2011-06-09 |
|
|
Cont ID |
|
| Sent By |
ajones |
Date |
2011-06-09 |
Time |
14:34 |
Rev Time |
0.00 |
| Received By |
ajones |
Date |
2011-06-09 |
Time |
14:34 |
Sent To |
|
|
| Notes |
| 2011-06-09 14:34:53 | THE ZONING APPROVAL DOES NOT INCLUDE THE 4 PILINGS FO | | | RTHE FUTURE BOAT LIFT | | | |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
F |
Date |
2011-04-29 |
|
|
Cont ID |
|
| Sent By |
ajones |
Date |
2011-04-29 |
Time |
11:46 |
Rev Time |
0.00 |
| Received By |
ajones |
Date |
2011-04-28 |
Time |
16:24 |
Sent To |
|
|
| Notes |
| 2011-04-29 11:52:22 | THE CLASS A SPECIAL PERMIT THAT WAS APPROVED TO | | | CONSTRUCTED THE DOCK EXPIRED IN MAY OF 2010 AND NO | | | EXTENSION WAS REQUESTED AT THAT TIME. THEREFORE A NEW | | | CLASS A SPECIAL USE PERMIT WILL BE REQUIRED TO | | | CONSTRUCT THIS DOCK. | | | | | | ANGELLA VANN, AICP | | | PLANNING AND ZONING ADMINISTRATOR | | | 561-822-1441 | | | [email protected] | | | |
|
|
|