| Plan Review Stops For Permit 11030256 |
| Review Stop |
ENG-APP |
ENGINEERING APP. REVIEW |
| Rev No |
1 |
Status |
P |
Date |
2011-03-30 |
|
|
Cont ID |
|
| Sent By |
dlauderm |
Date |
2011-03-30 |
Time |
08:03 |
Rev Time |
1.00 |
| Received By |
dlauderm |
Date |
|
Time |
|
Sent To |
|
|
| Notes |
|
|
| Review Stop |
ENG-MOT |
ENGINEERING MOT REVIEW |
| Rev No |
1 |
Status |
P |
Date |
2011-03-30 |
|
|
Cont ID |
|
| Sent By |
dlauderm |
Date |
2011-03-30 |
Time |
08:18 |
Rev Time |
3.00 |
| Received By |
dlauderm |
Date |
2011-03-30 |
Time |
08:03 |
Sent To |
|
|
| Notes |
| 2011-03-30 08:18:33 | PASSED WITH PROVISOS: | | | | | | 1. VMS BOARDS WILL GO IN ONE WEEK PRIOR TO BLOCKING THE | | | ROAD AND WILL STATE; | | | "WATER MAIN CONSTRUCTION ON HIBISCUS FROM 04/11 TO | | | 04/26 FROM QUADRILLE TO OLIVE" | | | | | | 2. VMS WILL STATE DURING CONSTRUCTION; | | | "WEST BOUND TRAFFIC CLOSED ON HIBISCUS, FOLLOW DETOUR" | | | | | | 3. CONES WILL NOT BE USED AS SHOWN ON MOT SUBMITTAL, | | | BUT WILL BE WATER FILLED BARRIERS AS WORKED OUT BETWEEN | | | CONTRACTOR AND CONSTRUCTION COORDINATOR. | | | | | | 4. ALL CONSTRUCTION WILL STOP AND THE TRAVEL LANES WILL | | | BE OPENED FOR SUNFEST (APRIL 27TH THRU MAY 2ND) | | | | | | 5. ALL CLOSED PARKING SPACES WILL NEED TO BE PAID FOR | | | THRU THE PARKING SYSTEMS OFFICE. THEY CAN BE CONTACTED | | | AT 822-1500. APPOXIMATELY 11 BETWEEN OLIVE AND DIXIE ON | | | THE NORTH SIDE AND 14 SPACES BETWEEN QUADRILLE AND | | | DIXIE. | | | | | | 6. QUADRILLE TO DIXIE WILL BE COMPLETED, PRIOR TO THE | | | START OF CONSTRUCTION BETWEEN DIXIE AND OLIVE. | | | | | | | | | |
|
|
|