Plan Review Details - Permit 11010474
Plan Review Stops For Permit 11010474
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2011-02-11 Cont ID  
Sent By kconrad Date 2011-02-11 Time 09:42 Rev Time 0.00
Received By kconrad Date 2011-02-11 Time 09:42 Sent To  
Notes
2011-02-11 09:48:06CHUCK JORDAN MET WITH THE CONTRACTOR ON SITE AND
 OBSERVED THAT THERE WILL BE SIGNIFICANT STRUCTURAL
 REPAIRS INVOLVED AND THAT THE INITIAL PROJECT VALUE
 SHALL BE INCREASED TO $20,000. I CONTACTED THE
 QUALIFIER AND ADVISED HIM OF THE SAME AND THAT A NOC
 WILL BE REQUIRED PRIOR TO THE 1ST INSPECTION. A PROVISO
 IS REQUIRED: ****STRUCTURAL REPAIR DETAILS SHALL BE
 SUBMITTED BY THE EOR.*****

Review Stop HIST HISTORICAL
Rev No 1 Status P Date 2011-01-20 Cont ID  
Sent By jpapa Date 2011-01-20 Time 15:33 Rev Time 0.00
Received By jpapa Date 2011-01-20 Time 15:33 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2011-02-11 Cont ID  
Sent By kconrad Date 2011-02-11 Time 09:42 Rev Time 0.00
Received By kconrad Date 2011-01-24 Time 10:20 Sent To  
Notes
2011-01-24 10:21:47ROUTED TO KC DESK
 (APPLICATION INCLUDED A LETTER RE INSPECTIONS, NO PLANS
 SUBMITTED)
  