Plan Review Details - Permit 11010187
Plan Review Stops For Permit 11010187
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2011-02-02 Cont ID  
Sent By shill Date 2011-02-02 Time 16:08 Rev Time 0.00
Received By shill Date 2011-02-02 Time 16:08 Sent To  
Notes
2011-02-02 16:10:28****PROVISO****
 ****REVISION REQUIRED****
 SAMANTHA HILL, BUILDING PLANS EXAMINER
 561-805-6724 [email protected]
 FBC FLORIDA BUILDING CODE 2007
 FBC R FLORIDA BUILDING CODE 2007 RESIDENTIAL
  
 1. SEE FEMA NFIP REQUIREMENTS, IF THE GARAGE IS NOT
 ELEVATED TO DFE, FLOOD OPENINGS REQUIRED FOR
 SUBSTANTIAL IMPROVEMENTS. SEE CFR TITLE 44, SEC.
 60.3(5). THIS INFORMATION IS TO BE INCLUDED ON THE
 ELEVATION CERTIFICATE, A9. ALTERNATIVELY, FLOOR CAN BE
 RAISED TO DFE (7'?6"). SEE FEMA/NFIP WEBSITE FOR
 GUIDANCE. SUBMIT REVISED ELEVATION CERTIFICATE.
  
 2. A SURVEY IS TO BE INCLUDED WITH THE ELEVATION
 CERTIFICATE, SEE ELEVATION CERTIFICATE, SECTION C.
 SUBMIT REVISED ELEVATION CERTIFICATE.
  
 3. ELEVATION CERTIFICATE, C2 E, MECHANICAL EQUIPMENT
 REQUIRED TO BE ELEVATED TO 7'6", CFR TITLE 44, SECTION
 60.3. MECHANICAL EQUIPMENT IS SHOWN AS 5.8'. THIS DOES
 NOT MEET THE NFIP REQUIREMENTS FOR SUBSTANTIAL
 IMPROVEMENTS. THE PERMIT WAS ISSUED WITH PROVISO THAT
 THE MECHANICAL PLANS INCLUDE PROPOSED ELEVATION OF
 EQUIPMENT, BUT I WAS UNABLE TO LOCATE THAT INFORMATION
 ON THE MECHANICAL PLANS SUBMITTED. PLEASE ADDRESS.
 SUBMIT REVISED ELEVATION CERTIFICATE.
  
 4. ELEVATION CERTIFICATE TO INCLUDE AN ORIGINAL
 SIGNATURE, SEE ELEVATION CERTIFICATE INSTRUCTIONS.
 SUBMIT REVISED ELEVATION CERTIFICATE.
  
 5. INCORPORATE REVISED ROOF TRUSS CONNECTOR SCHEDULE
 INTO APPROPRIATE STRUCTURAL SHEET (NOTED AS S6 ON
 ENGINEER'S LETTER). SUBMIT REVISED S6
  
 6. REVISE THE SITE PLAN TO SHOW PROPOSED CHANGES SO
 THAT SITE PLAN BUILDING FOOTPRINT WILL MATCH
 ARCHITECTURAL DRAWINGS. SUBMIT REVISED SITE PLAN.
  
 7. PROVIDE PRODUCT APPROVALS FOR FRONT DOOR (UNLESS PGT
 FRENCH DOOR WAS INSTALLED), SIDING, FAC9B72. PRODUCT
 APPROVALS TO BE REVIEWED BY DOR PRIOR TO SUBMITTAL.
 SUBMIT PRIOR TO INSTALLATION.
  
 8. SHEET A2 WAS NOT SUBMITTED WITH THIS REVISION, BUT
 IT APPEARS THAT THE FIRST FLOOR COVERED DECK IS
 AFFECTED BY THIS REVISION (CHANGE IN SIZE, LOCATION OF
 FOOTINGS). SUBMIT REVISED A2.
  
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2011-01-31 Cont ID  
Sent By shill Date 2011-01-31 Time 16:35 Rev Time 0.00
Received By shill Date 2011-01-31 Time 16:35 Sent To  
Notes
2011-01-31 16:36:14****CORRECTIONS****
 SAMANTHA HILL, BUILDING PLANS EXAMINER
 561-805-6724 [email protected]
 FBC FLORIDA BUILDING CODE 2007
 FBC R FLORIDA BUILDING CODE 2007 RESIDENTIAL
  
 1. SEE FEMA NFIP REQUIREMENTS, IF THE GARAGE IS NOT
 ELEVATED TO DFE, FLOOD OPENINGS REQUIRED FOR
 SUBSTANTIAL IMPROVEMENTS. SEE CFR TITLE 44, SEC.
 60.3(5). THIS INFORMATION IS TO BE INCLUDED ON THE
 ELEVATION CERTIFICATE, A9. ALTERNATIVELY, FLOOR CAN BE
 RAISED TO DFE (7'?6"). SEE FEMA/NFIP WEBSITE FOR
 GUIDANCE.
  
 2. A SURVEY IS TO BE INCLUDED WITH THE ELEVATION
 CERTIFICATE, SEE ELEVATION CERTIFICATE, SECTION C.
  
 3. ELEVATION CERTIFICATE, C2 E, MECHANICAL EQUIPMENT
 REQUIRED TO BE ELEVATED TO 7'6", CFR TITLE 44, SECTION
 60.3. MECHANICAL EQUIPMENT IS SHOWN AS 5.8'. THIS DOES
 NOT MEET THE NFIP REQUIREMENTS FOR SUBSTANTIAL
 IMPROVEMENTS. THE PERMIT WAS ISSUED WITH PROVISO THAT
 THE MECHANICAL PLANS INCLUDE PROPOSED ELEVATION OF
 EQUIPMENT, BUT I WAS UNABLE TO LOCATE THAT INFORMATION
 ON THE MECHANICAL PLANS SUBMITTED. PLEASE ADDRESS.
  
 4. ELEVATION CERTIFICATE TO INCLUDE AN ORIGINAL
 SIGNATURE, SEE ELEVATION CERTIFICATE INSTRUCTIONS.
  
 5. INCORPORATE REVISED ROOF TRUSS CONNECTOR SCHEDULE
 INTO APPROPRIATE STRUCTURAL SHEET (NOTED AS S6 ON
 ENGINEER'S LETTER).
  
 6. REVISE THE SITE PLAN TO SHOW PROPOSED CHANGES SO
 THAT SITE PLAN BUILDING FOOTPRINT WILL MATCH
 ARCHITECTURAL DRAWINGS.
  
 7. PROVIDE PRODUCT APPROVALS FOR FRONT DOOR (UNLESS PGT
 FRENCH DOOR WAS INSTALLED), SIDING, FAC9B72. PRODUCT
 APPROVALS TO BE REVIEWED BY DOR PRIOR TO SUBMITTAL.
  
 8. SHEET A2 WAS NOT SUBMITTED WITH THIS REVISION, BUT
 IT APPEARS THAT THE FIRST FLOOR COVERED DECK IS
 AFFECTED BY THIS REVISION (CHANGE IN SIZE, LOCATION OF
 FOOTINGS).
  

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2011-01-24 Cont ID  
Sent By rlecky Date 2011-01-24 Time 14:44 Rev Time 0.00
Received By rlecky Date 2011-01-24 Time 14:40 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status   Date 2011-02-02 Cont ID  
Sent By shill Date 2011-02-01 Time 16:10 Rev Time 0.00
Received By shill Date 2011-01-12 Time 10:59 Sent To  
Notes
2011-01-12 11:02:38SENT TO R2.

Review Stop Z ZONING
Rev No 1 Status P Date 2011-02-01 Cont ID  
Sent By astelly Date 2011-02-01 Time 16:37 Rev Time 0.00
Received By astelly Date 2011-02-01 Time 16:36 Sent To  
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved