Plan Review Stops For Permit 09120062
Review Stop G GAS REVIEW
Rev No 2 Status P Date 2009-12-14 Cont ID  
Sent By kstevens Date 2009-12-14 Time 17:19 Rev Time 0.00
Received By kstevens Date 2009-12-14 Time 17:18 Sent To  
Notes
2009-12-14 17:20:04GAS REVISION OK -- SHT P1-103 GAS RISER DIAGRAM AND GAS
 REGULATORS.

Review Stop G GAS REVIEW
Rev No 1 Status F Date 2009-12-08 Cont ID  
Sent By kstevens Date 2009-12-08 Time 08:25 Rev Time 0.00
Received By kstevens Date 2009-12-08 Time 08:25 Sent To  
Notes
2009-12-08 08:41:10DENIED
 REFERENCE:
 FBC-2004 FUEL GAS
  
 1. SHT P1-103 GAS ISOMETRIC 2-1/2" GAS LINE REQUIRED TO
 EACH GB1 @ 1300 MBH PER TABLE 402.4(2).
  
 2. SHT P1-103 GAS ISOMETRIC. PLEASE VERIFY ALL CUT
 SECTION MEASUREMENTS. THE REVISION DOES NOT SHOW A
 LENGTH FROM THE BRANCH LINE FOR GWH1 TO THE 1 INCH
 ELBOW TO THE OFFSET TO THE DRYER AND SHOWS 80 FEET FROM
 THE ELBOW TO THE DROP AT THE DRYER AND NO DROP LENGTH
 TO THE DRYER. THE LENGTHS APPEAR TO BE CORRECT ON THE
 PREVIOUS REVISION, 74' - 22' & 10'. HAVE THESE LENGTHS
 CHANGED? ALSO THE LENGTH TO THE GWH1 FROM THE GAS MAIN
 TO THE DROP IS SHOWN AS 23 FEET BUT SCALES OUT TO ABOUT
 6 FEET MAX. PLEASE CLARIFY.
  
 3. THE FIELD INSPECTOR HAS INFORMED ME THAT THE METER
 LOCATION HAS CHANGED AS WELL AS THE PIPING TO THE DRYER
 CHANGED TO RUN DOWN THE CORRIDOR. PLEASE VERIFY AND IF
 SO THESE CHANGES SHALL BE INDICATED ON THE REVISION FOR
 THE ISOMETRIC RISER DIAGRAM AND THE FLOOR PLAN.
 SECTIONS 106.1.1 & 401.1. IF THE METER LOCATION HAS
 CHANGED, THIS MAY LENGTHEN THE TOTAL DEVELOPED LENGTH
 AND MAY CALL FOR INCREASED PIPE SIZES DEPENDING ON THE
 DISTANCE TO THE MOST REMOTE APPLIANCE FROM THE METER.
  
 WHEN RESUBMITTING PLANS PLEASE INDICATE
 THE REVISION & REMOVE & REPLACE ANY
 PAGES AS NECESSARY. A TRANSMITTAL LETTER
 LISTING THE ORIGINAL REVIEW COMMENT NUMBER,
 WITH A DESCRIPTION OF THE REVISION MADE,
 IDENTIFYING THE SHEET OR SPECIFICATION
 PAGE WHERE THE CHANGES CAN BE FOUND
 WILL HELP TO EXPEDITE YOUR PERMIT. REMOVE
 ALL VOID SHEETS FROM ALL PLANS AND PLACE
 ONE SET OF THEM LOOSELY ON TOP OF THE
 COLLATED PLANS TO BE REVIEWED.
 THANK YOU FOR YOUR ANTICIPATED COOPERATION.
  
 REVIEW BY KEN STEVENS
 (561) 805-6721
 FAX (561) 805-6731
 E-MAIL [email protected]
  

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2009-12-08 Cont ID  
Sent By kstevens Date 2009-12-08 Time 08:52 Rev Time 0.00
Received By kstevens Date 2009-12-02 Time 16:50 Sent To  
Notes
2009-12-03 16:51:17GAVE TO KEN
 ******************EXPEDITED*********************
  

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2009-12-07 Cont ID  
Sent By rregueir Date 2009-12-07 Time 18:07 Rev Time 0.00
Received By rregueir Date 2009-12-07 Time 17:56 Sent To P
Notes
2009-12-07 17:57:50REVISED M2-101 DELTA 10, M4-101 DELTA 7, M5-103 DELTA 8

Review Stop P PLUMBING
Rev No 1 Status P Date 2009-12-08 Cont ID  
Sent By kstevens Date 2009-12-08 Time 09:22 Rev Time 0.00
Received By kstevens Date 2009-12-08 Time 09:22 Sent To  
Notes
2009-12-08 09:23:24REVISION OK -- SHT P1-105 REV. #8.