Plan Review Details - Permit 09090070
Plan Review Stops For Permit 09090070
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2009-09-22 Cont ID  
Sent By tmoore Date 2009-09-22 Time 17:00 Rev Time 0.00
Received By tmoore Date 2009-09-22 Time 16:13 Sent To  
Notes
2009-09-22 16:13:19ALL PRE-DEMO REQUIREMENTS ARE NOW COMPLETE.

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2009-09-03 Cont ID  
Sent By tmoore Date 2009-09-03 Time 16:23 Rev Time 0.00
Received By tmoore Date 2009-09-22 Time 16:11 Sent To  
Notes
2009-09-03 16:23:31ITEMS MISSING THAT MUST BE IN HAND BEFORE DEMO PERMIT
 CAN BE ISSUED.
  
 1) ELECTRICAL UTILITY RELEASE CONFIRMATION. LETTER OR
 RELEASE FORM SIGNED BY F.P.L.
  
 2) SEWER LATERAL CAPPING MUST BE PERMITED, INSPECTED,
 AND PASSED PRIOR TO DEMO PERMIT BEING ISSUED. THIS IS A
 TURN AROUND PLUMBING PERMIT.
  
 3) ENGINEERING REVIEW MUST BE COMPLETED FOR COMMERCIAL
 DEMOLITION INCLUDING,
 A) STORMWATER POLLUTION PREVENTION PLAN.
 B) RIGHT OF WAY PERMIT IF SIDEWALK OR STREET WILL BE
 CLOSED.
 ENGINEERING CONTACT IS BRIAN MOREE @ (561) 494-1040
  
 4) DOCUMENTATION FROM A LICENSED EXTERMINATOR
 COMFIRMING THAT THE BUILDING IS FREE OF RODENTS.
  
 PLEASE CALL TOM MOORE @ 805-6669 WITH ANY QUESTIONS.

Review Stop ENG ENGINEERING CSD
Rev No 1 Status P Date 2009-09-08 Cont ID  
Sent By mgonzale Date 2009-09-08 Time 08:32 Rev Time 3.00
Received By mgonzale Date 2009-09-08 Time 08:31 Sent To  
Notes
2009-09-08 08:32:07ENGINEERING DEPT HAS BEEN SATIFIED WITH LAND
 STABILIZATION BOND.
  
  
  
  

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2009-09-21 Cont ID  
Sent By lmartine Date 2009-09-21 Time 14:31 Rev Time 0.00
Received By lmartine Date 2009-09-21 Time 14:31 Sent To  
Notes
2009-09-21 14:32:57********************EXPEDITED********************
 GAVE TO TOM MOORE