Plan Review Details - Permit 09080354
Plan Review Stops For Permit 09080354
Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2009-10-06 Cont ID  
Sent By shill Date 2009-10-06 Time 08:23 Rev Time 0.00
Received By shill Date 2009-10-06 Time 08:23 Sent To  
Notes
2009-10-06 08:23:47REVISED INSTALLATION SCHEDULE
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2009-09-16 Cont ID  
Sent By shill Date 2009-09-16 Time 13:50 Rev Time 0.00
Received By shill Date 2009-09-16 Time 13:50 Sent To  
Notes
2009-09-16 14:08:01****CORRECTIONS****
 REVISION #1
 SAMANTHA HILL, BUILDING PLANS EXAMINER
 561-805-6724 [email protected]
 FBC FLORIDA BUILDING CODE 2007
 FBC R FLORIDA BUILDING CODE 2007 RESIDENTIAL
  
 1. SEE PRODUCT APPROVAL; 72PSF ROW MUST BE USED DUE TO
 DESIGN PRESSURE OF -66PSF. C3, MASONRY, REQUIRES 5"
 ANCHOR SPACING FOR PANELMATE, OPENING LESS THAN 6'.
  
 2. PANELMATE, MASONRY SUBSTRATE, SPAN OVER 6' IS NOT
 ALLOWED (SEE OPENING 13). CHECK ALL.
  
 3. FOR PANELS INSTALLED HORIZONTALLY, SUBSTRATE SHOULD
 BE "CONCRETE BLOCK," NOT "CONCRETE." FILLED CONCRETE
 BLOCK DOES NOT MEET THE STRENGTH REQUIREMENTS OF
 CONCRETE SUBSTRATE. IT IS DIFFICULT TO DETERMINE WHAT
 YOU ARE SPECIFYING AS SUBSTRATE; THE COLUMN STATES
 "CONCRETE MASONRY." THERE ARE TWO SUBSTRATES; TOP AND
 BOTTOM (INSTALLED VERTICALLY) OR LEFT AND RIGHT
 (INSTALLED HORIZONTALLY). FOR OPENINGS INSTALLED
 VERTICALLY, DOES "CONCRETE MASONRY" MEAN CONCRETE ON
 THE TOP, MASONRY ON THE BOTTOM? OR ARE ALL SUBSTRATES
 MASONRY? IF THIS MEANS CONCRETE TOP, MASONRY BOTTOM,
 WHAT DOES THIS MEAN FOR PANELS INSTALLED HORIZONTALLY?
  
 DUE TO THE FACT THAT ITEM #3 WAS NOT MENTIONED IN THE
 FIRST REVIEW, FOR THIS PERMIT ONLY THE REVISED
 INSTALLATION SCHEDULE WILL BE ACCEPTED VIA EMAIL
 (PREFERABLE) OR FAX, 561-805-6731.
  
 THE INSTALLATION SCHEDULE FORM IS AVAILABLE ON THE
 INTERNET AT HTTP://WWW.CITYOFWPB.COM/CONSTRUCTION/PDF/S
 CHEDULE_FOR_INSTALLATION.PDF

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2009-08-18 Cont ID  
Sent By shill Date 2009-08-18 Time 10:55 Rev Time 0.00
Received By shill Date 2009-08-18 Time 10:55 Sent To  
Notes
2009-08-18 10:56:33PROVISO - SUBMIT REVISION, REVISE INSTALLATION SCHEDULE
 TO DESIGN TO EXPOSURE C PRESSURES FBC R301

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2009-09-15 Cont ID  
Sent By kstevens Date 2009-09-15 Time 17:56 Rev Time 0.00
Received By kstevens Date 2009-09-15 Time 17:56 Sent To  
Notes
2009-09-15 17:56:51SENT TO SHILL.