Plan Review Details - Permit 09070129
Plan Review Stops For Permit 09070129
Review Stop B BUILDING (STRUCTURAL)
Rev No 8 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By shill Date   Time   Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 7 Status P Date 2009-11-17 Cont ID  
Sent By shill Date 2009-11-17 Time 11:49 Rev Time 0.00
Received By shill Date 2009-11-17 Time 11:49 Sent To  
Notes
2009-11-17 11:50:51REVISION, ADD TWO FIRE RATED DOORS TO SCOPE
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 6 Status P Date 2009-10-07 Cont ID  
Sent By shill Date 2009-10-07 Time 09:06 Rev Time 0.00
Received By shill Date 2009-10-07 Time 09:06 Sent To Z
Notes
2009-10-07 09:06:32ADDITIONAL INFORMATION FOR SIDEWALK REVISION
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 5 Status P Date 2009-10-06 Cont ID  
Sent By shill Date 2009-10-06 Time 15:41 Rev Time 0.00
Received By shill Date 2009-10-06 Time 15:41 Sent To Z
Notes
2009-10-06 15:42:03SIDEWALK REVISION - PER CONTRACTOR, MEETS REQUIREMENTS
 OF FBC11
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 4 Status F Date 2009-10-06 Cont ID  
Sent By shill Date 2009-10-06 Time 08:45 Rev Time 0.00
Received By shill Date 2009-10-06 Time 08:45 Sent To  
Notes
2009-10-06 08:47:24****CORRECTIONS****
 SUBMITTALS SUBMITTED 9/24, 9/30, 10/1
  
 SAMANTHA HILL, BUILDING PLANS EXAMINER
 561-805-6724 [email protected]
  
 FBC FLORIDA BUILDING CODE 2007 WITH 2009 SUPPLEMENTS
 FBC EB FLORIDA BUILDING CODE 2007 EXISTING BUILDING
 CODE
 FBC R FLORIDA BUILDING CODE 2007 RESIDENTIAL
 FBC* CITY OF WEST PALM BEACH AMENDMENTS TO THE FBC2004
 FAC FLORIDA ADMINISTRATIVE CODE
 FS FLORIDA STATUTE
  
 1. ALL INSPECTION REPORTS ARE TO BE PROVIDED TO THE
 INSPECTOR IN THE FIELD. PER KEN CONRAD, PLEASE SCHEDULE
 AN IN PROGRESS INSPECTION.
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2009-10-05 Cont ID  
Sent By shill Date 2009-10-05 Time 16:17 Rev Time 0.00
Received By shill Date 2009-10-05 Time 16:17 Sent To  
Notes
2009-10-05 16:18:03REVISION, SHEET S4
 PROVISO - UPDATE VALUE
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2009-08-13 Cont ID  
Sent By shill Date 2009-08-13 Time 10:47 Rev Time 0.00
Received By shill Date 2009-08-13 Time 10:41 Sent To  
Notes
2009-08-13 10:47:27RAILING SHOPS AND SGD NOA (8, 2ND FLOOR)

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2009-07-22 Cont ID  
Sent By shill Date 2009-07-22 Time 17:57 Rev Time 0.00
Received By shill Date 2009-07-22 Time 17:57 Sent To  
Notes
2009-07-22 17:58:14PROVISO
  
 1. SUBMIT RAILING SHOPS/ENGINEERING BEFORE INSTALLATION
 SUBMIT AS A REVISION; ANY DELEGATED ENGINEERING TO BE
 REVIEWED BY EOR PRIOR TO SUBMITTAL
  
  
  

Review Stop I INCOMING/PROCESSING
Rev No 8 Status N Date 2009-11-16 Cont ID  
Sent By dpalmer Date 2009-11-16 Time 14:33 Rev Time 0.00
Received By dpalmer Date 2009-11-16 Time 14:33 Sent To  
Notes
2009-11-16 14:34:38TO SH

Review Stop I INCOMING/PROCESSING
Rev No 7 Status N Date 2009-10-05 Cont ID  
Sent By dpalmer Date 2009-10-05 Time 11:06 Rev Time 0.00
Received By dpalmer Date 2009-10-05 Time 11:06 Sent To B
Notes
2009-10-05 11:06:25TO SH'S DESK

Review Stop I INCOMING/PROCESSING
Rev No 6 Status N Date 2009-10-05 Cont ID  
Sent By dpalmer Date 2009-10-05 Time 11:03 Rev Time 0.00
Received By dpalmer Date 2009-10-05 Time 11:03 Sent To B
Notes
2009-10-05 11:04:00TO SH'S DESK

Review Stop I INCOMING/PROCESSING
Rev No 5 Status N Date 2009-10-01 Cont ID  
Sent By jwitmer Date 2009-10-01 Time 08:22 Rev Time 0.00
Received By jwitmer Date 2009-10-01 Time 08:22 Sent To  
Notes
2009-10-01 08:23:02INCOMING REPORT TO S HILL

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2009-10-01 Cont ID  
Sent By rmcdouga Date 2009-09-29 Time 08:07 Rev Time 0.00
Received By rmcdouga Date 2009-09-29 Time 08:07 Sent To  
Notes
2009-10-01 08:08:32REVISION SENT TO S. HILL

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2009-09-30 Cont ID  
Sent By jgomez Date 2009-09-30 Time 10:34 Rev Time 0.00
Received By jgomez Date 2009-09-30 Time 10:34 Sent To B
Notes
2009-09-30 10:35:25SENT TO S. HILL'S DESK.

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2009-07-29 Cont ID  
Sent By lmartine Date 2009-07-29 Time 10:53 Rev Time 0.00
Received By lmartine Date 2009-07-29 Time 10:53 Sent To  
Notes
2009-07-29 10:54:06GAVE TO SAM

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2009-07-28 Cont ID  
Sent By jwitmer Date 2009-07-28 Time 14:21 Rev Time 0.00
Received By jwitmer Date 2009-07-10 Time 09:21 Sent To  
Notes
2009-07-10 09:21:41SENT TO MISC. BOX #1.

Review Stop Z ZONING
Rev No 1 Status P Date 2009-10-12 Cont ID  
Sent By jroach Date 2009-10-12 Time 19:45 Rev Time 0.00
Received By jroach Date 2009-10-12 Time 19:45 Sent To  
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved