| 2008-08-01 16:29:46 | RESIDENTIAL (R3) SHUTTERS BUILDING REVIEWCHECKLIST. |
| | REVIEW UNDER FBC 2004 WITH 2007 REVISIONS. |
| | |
| | 1- ACCORDING TO PERMIT APPLICATION DESCRIPTION, THERE |
| | ARE TWO SLIDING GLASS DOORS THAT WILL RECEIVE STORM |
| | PANELS TOO. OPENING SIZES SHOWN ON THE INSTALLATION |
| | SCHEDULE DON'T REFLECT ANY BIG OPENIGS FOR SLIDING |
| | GLASS DOORS. REVISE/CLARIFY AS REQUIRED.ALL OPENINGS |
| | CORRESPOND TO WINDOW OPENINGS. |
| | |
| | 2-NEED RECORDED NOTICE OF COMMENCEMENT AS REQUIRED BY |
| | SEC. 713.13FLORIDA STATUTE. |
| | |
| | 3- CLEARLY MARK ON SHUTTER DRAWINGS SPECIFIC MOUNTING |
| | CONDITIONS (EG: DIRECT MOUNT OR BUILT OUT)TO VERIFY |
| | COMPLIANCE WITH MINIMUM PANEL LENGTH AS REQUIRED BY |
| | TABLE 2ONSHEET 6 OF 6 OF DRAWING 05-329 SUBMITTED. |
| | OTHERWISE COMPLETE ENGINEERING WILL BE REQUIRED. SEE |
| | TABLE 2 NOTE ON SHEET 6 OF 6. |
| | |
| | 4- REVISE SHUTTER SPAN SIZE SHOWN ON INSTALLATION |
| | SCHEDULE.IF SHUTTERS ARE GOING TO BE INSTALLED WITH |
| | 3" MIN. EDGE DISTANCE, THEN SIZE OF PANELS SHOWN ON |
| | SHUTTER SPAN COLUMNNEED TO BE REVISED.IT CAN'T BE |
| | JUST 6" LONGER THAN THE OPENING.NEED TO CONSIDER THE |
| | STUCCO THICKNESS AND LOCATION OF ANCHOR ON THE STORM |
| | PANEL WHENSPECIFYING THE PANEL OVERALL LENGTH. |
| | |
| | JULIO GOMEZ |
| | BUILDING PLANS EXAMINER |
| | (561)805-6712 |