Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2008-04-01 Cont ID  
Sent By shill Date 2008-04-01 Time 18:36 Rev Time 0.00
Received By shill Date 2008-04-01 Time 18:36 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2008-03-24 Cont ID  
Sent By shill Date 2008-03-24 Time 16:44 Rev Time 0.00
Received By shill Date 2008-03-24 Time 16:43 Sent To  
Notes
2008-03-24 16:51:17****CORRECTIONS****
  
 SAMANTHA HILL, BUILDING PLANS EXAMINER
 561-805-6724 [email protected]
  
 FBCFLORIDA BUILDING CODE 2004
 FBC EBFLORIDA BUILDING CODE 2004 EXISTING BUILDING
 CODE
 FBC RFLORIDA BUILDING CODE 2004 RESIDENTIAL
 FBC* CITY OF WEST PALM BEACH AMENDMENTS TO THE FBC2004
  
 FAC FLORIDA ADMINISTRATIVE CODE
 FSFLORIDA STATUTE
  
 1.CONCRETE/BLOCK IS SPECIFIED ON THE INSTALLATION
 SCHEDULE; DOES THIS MEAN CONCETE ON THE TOP, CBS ON THE
 BOTTOM, OR CONCRETE BLOCK BOTH TOP AND BOTTOM?
  
 2.SEE OPENING 6.11" SPACING IS REQUIRED FOR SPANS
 BETWEEN 5'8" AND 8', BLOCK SUBSTRATE.12" IS SPECIFIED
 ON THE INSTALLATION SCHEDULE.PLEASE REVISE AND CHECK
 ALL OPENINGS AS THIS COMMENT APPLIES TO OTHER
 OPENINGS.
  
 3.TWO SETS OF DESIGN PRESSURE ENGINEERING WERE
 SUBMITTED.NONE ARE REQUIRED FOR BUILDINGS UNDER
 60FEET, BUT IF YOU WISH TO USE ENGINEERING THAT IS
 ACCEPTABLE BUT PLEASE ONLY SUBMIT ONE SET, AND CHECK
 THE INSTALLATION SCHEDULE TO ENSURE THAT THE DESIGN
 PRESSURES SPECIFIED ARE CONSISTENT WITH THE
 ENGINEERING.
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2008-03-10 Cont ID  
Sent By shill Date 2008-03-10 Time 15:22 Rev Time 0.00
Received By shill Date 2008-03-10 Time 15:22 Sent To  
Notes
2008-03-10 15:23:28****CORRECTIONS****
 SAMANTHA HILL, BUILDING PLANS EXAMINER
 561-805-6724 [email protected]
 FBC FLORIDA BUILDING CODE 2004
 FBC R FLORIDA BUILDING CODE 2004 RESIDENTIAL
  
 1.COMPLETE THE ATTACHED INSTALLATION SCHEDULE OR
 PROVIDE ALL INFORMATION TO SHOW CODE COMPLIANCE IN
 ANOTHER FORMAT, FBC*106.TWO SETS REQUIRED.
 HTTP://WWW.CITYOFWPB.COM/CONSTRUCTION/PDF/SCHEDULE_FOR_
 INSTALLATION.PDF
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2008-03-14 Cont ID  
Sent By adarroug Date 2008-03-14 Time 15:16 Rev Time 0.00
Received By adarroug Date 2008-03-14 Time 15:16 Sent To B
Notes
2008-03-14 15:16:59TO "SHILL" DESK/RESUB

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2008-03-10 Cont ID  
Sent By shill Date 2008-03-10 Time 15:23 Rev Time 0.00
Received By shill Date 2008-03-07 Time 08:53 Sent To  
Notes
2008-03-07 08:53:17TO "MISC" BOX#1