| 2007-06-28 13:59:05 | PLANNING AND ZONING **FAILED** |
| | |
| | 1. PROVIDE RESPONSES TO COMMENTS IN WRITING. |
| | |
| | 2. THE TABULATION NECESSARY FOR THE EVALUATION OF |
| | COMPLIANCE WITH ARTICLE XIV IS NOT COMPLETE (I.E. THE |
| | TABULATION DISPLAYING STATISTICAL REQUIREMENTS TO |
| | SATISFY THE XERISCAPE POINT SYSTEM AND ITS ACCOMPANYING |
| | POINT ALLOCATION). REVISE ACCORDINGLY. |
| | |
| | 3. THE CALCULATION USED TO DETERMINE THE % OF TOTAL NEW |
| | LANDSCAPED AREA AND % OF TOTAL REQUIRED LANDSCAPED AREA |
| | SHOULD BE BASED ON THE TOTAL OPEN SPACE AREA WHICH DOES |
| | NOT INCLUDE THE EXISTING BUILDING SQUARE FOOTAGE. |
| | REVISE ACCORDINGLY. |
| | |
| | 4. THE CALCULATION USED TO DETERMINE THE % OF TOTAL |
| | IMPERVIOUS SURFACE AREA AND % OF TOTAL REQUIRED |
| | IMPERVIOUS SURFACE AREA SHOULD BE BASED ON THE TOTAL |
| | LOT AREA. CLARIFY ACCORDINGLY. |
| | |
| | 5. ON SHEET SP-1 IN THE INFORMATIONAL TABLE THE |
| | REQUIRED LANDSCAPE MATERIAL SHALL BE LISTED, I.E. TREE |
| | REQUIREMENT (1 PER 1600 SF OF OPEN SPACE AREA). |
| | |
| | 6. PROVIDE STANDARD CITY DETAILS OF PARKING (I.E. |
| | HANDICAPPED SPACE). |
| | |
| | 7. ACCORDING TO ALAN BARATTA, LANDSCAPE PLANNER, FICUS |
| | BENJAMINA IS NOT THE APPROPRIATE PLANT MATERIAL. SEA |
| | GRAPE, COCO PLUM, OR PHITOCARPUS IS MORE APPROPRIATE. |
| | PLEASE CONTACT ALAN BARATTA (561) 822-1462 WITH ANY |
| | QUESTIONS. |
| | |
| | FOR ANY ADDITIONAL INFORMATION OR QUESTIONS YOU MAY |
| | CONTACT: |
| | |
| | JULIA BABCOCK |
| | PLANNER |
| | OFFICE: (561) 822-1442 |
| | EMAIL: [email protected] |