Plan Review Details - Permit 06110750
Plan Review Stops For Permit 06110750
Review Stop B BUILDING (STRUCTURAL)
Rev No 4 Status P Date 2007-11-19 Cont ID  
Sent By kconrad Date 2007-11-19 Time 18:05 Rev Time 0.00
Received By kconrad Date 2007-11-19 Time 17:35 Sent To  
Notes
2007-11-20 19:35:57REVIEWED REQUESTED PRECAST PILE INSTALLATION RECORDS
 AND ENGINEERING CERTIFICATION LETTERS.

Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2007-07-12 Cont ID  
Sent By jwitmer Date 2007-07-12 Time 15:53 Rev Time 1.11
Received By jwitmer Date 2007-07-12 Time 15:53 Sent To ENG
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2007-03-02 Cont ID  
Sent By jwitmer Date 2007-03-02 Time 13:35 Rev Time 2.22
Received By jwitmer Date 2007-03-01 Time 16:51 Sent To PC
Notes
2007-03-02 13:49:52BUILDING PLAN REVIEW
 PERMIT: 06110750
 ADD: 4300 N FLAGLER DR
 CONT: CENTEX
 TEL: (954)605-1010
  
 FL BLD CODE= 2004 FLORIDA BUILDING CODE
 W/ 2006 FBC REVISIONS
 * WEST PALM BEACH AMENDMENTS
  
 REVIEW
 ACTION: DENIED
  
 1)--- VERY IMPORTANT STATEMENT ---
 PLEASE DO NOT IGNORE!
 WHEN RESUBMITTING PLANS PLEASE INDICATE
 THE REVISION & REMOVE & REPLACE ANY
 PAGES AS NECESSARY. A TRANSMITTAL LETTER
 LISTING THE ORIGINAL REVIEW COMMENT NUM-
 BER, WITH A DESCRIPTION OF THE REVISION
 MADE, IDENTIFYING THE SHEET OR SPECIFICA
 TION PAGE WHERE THE CHANGES CAN BE FOUND
 WILL HELP TO EXPEDITE YOUR PERMIT. THANK
 YOU FOR YOUR ANTICIPATED COOPERATION.
  
 2 ) FL S S 713.13/ 105.8*
 NOTICE OF COMMENCEMENT, TO BE FILED
 WITH THE CLERK OF THE COURT BEFORE A
 PERMIT WILL BE ISSUED. NOTE: 713.13(2)
 IF THE WORK DESCRIBED IN THE NOTICE OF COMMENCEMENT IS
 NOT ACTUALLY COMMENCED
 WITHIN 90 DAYS AFTER THE RECORDING
 THEREOF, SUCH NOTICE IS NULL & VOID.
  
 3A)105.1* WORK THAT REQUIRES A PERMIT.
 CITY CODE SEC. 54-292. PROJECTING STRUCTURES.
 IT SHALL BE UNLAWFUL FOR ANY PERSON TO ERECT ANY
 STRUCTURE OR PORTION THEREOF IN OR OVER THE WATERS OF
 LAKE WORTH, WITHIN THE CITY, ON PILINGS OR PILLARS,
 EXCEPT PROPERLY APPROVED MARINE DOCKS AND ACCESSORIES,
 STRUCTURES AND APPURTENANCES THERETO, SEAWALLS,
 BREAKWATERS, BULKHEADS, BRIDGES AND CAUSEWAYS. (CODE
 1979, / 16-39)
  
  
 3B) WORKING WITHOUT A PERMIT SEE FEE SCHEDULE
 4X PERMIT FEE WORKING WITH OUT THE BENIFET OF A
 PERMIT.
 FEES ARE TO BE PAID BEFORE SUBMITTAL FOR REVIEW. NEXT
 REVIEW WILL NOT BE COMPLETED UNTILS FEES ARE PAID.
  
 W P B ADMINISTRTIVE CODE 108.2
 SCHEDULE OF PERMIT FEES. ON BUILDINGS, STRUCTURES,
 ELECTRICAL,
 GAS, MECHANICAL, AND PLUMBING SYSTEMS OR ALTERATIONS
 REQUIRING
 A PERMIT,A FEE FOR EACH PERMIT SHALL BE PAID AS
 REQUIRED,
 IN ACCORDANCE WITH THE SCHEDULE ESTABLISHED BY THE
 APPLICABLE GOVERNING AUTHORITY.
  
 4) 2ND REQUEST,THE ISSUANCE OF PERMIT 50-0162161-006
 FROM THE DEPARTMENT OF ENVIROMENTAL PROTECTION INCLUDES
 A) DREDGING APPROXIMATELY 156,000 CUBIC YDS OF
 MATERIAL,
 ( APPROXIMATELY 80,00- CUBIC YDS OF SOVEREIGN
 MATERIAL)PAGE 3 OF THIS REPORT INDICATES YOUR PROJECT
 HAS BEEN REVIEWED FOR COMPLIANCE WITH A STATE
 PROGRAMMATIC GENERALPERMIT. AS SHOWN ON THE ATTACHED
 DRAWINGS, THE PROPOSED PROJECT IS "NOT" CONSISTANT WITH
 THE SPGP PROGRAM. A COPY OF YOUR APPLICATION HAS BEEN
 SENT TO THE CORPS WHO MAY REQUIRE A SEPERATE PERMIT.
 FOR FURTHER INFORMATION, CONTACT THE CORPS DIRECTLY.
 PLEASE COMPLY WITH THIS REQUIREMEENT.
  
 REQUIRED APPROVAL FROM OTHER GOVERNMENTAL AGENCIES:
 CITY CODE:
 SEC. 94-378. SHORELINE MANAGEMENT.
 (A)DOCKS, MARINAS, ETC.
 (1)NEW BOAT BASINS, MARINAS, DOCKS AND OTHER MOORING
 FACILITIES ARE PROHIBITED UNLESS APPROVED BY THE
 APPROPRIATE GOVERNMENTAL AGENCIES, SUCH AS THE U.S.
 ARMY CORP OF ENGINEERS, STATE DEPARTMENT OF
 ENVIRONMENTAL REGULATION, STATE DEPARTMENT OF NATURAL
 RESOURCES, BOARD OF TRUSTEES OF THE INTERNAL
 IMPROVEMENT TRUST FUND, AND THE SOUTH FLORIDA WATER
 MANAGEMENT DISTRICT.
 (2)IN NO EVENT SHALL ANY NEW BOAT BASIN, MARINA,
 DOCK, OR ANY OTHER STRUCTURE BE APPROVED WHICH WOULD
 CONSTRICT WATER CIRCULATION IN LAKE WORTH.
 (B)SHORELINE STABILIZATION.
 (1)WITHIN A PROPOSED DEVELOPMENT IN THE COASTAL
 AREA, THERE SHALL BE NO NET LOSS OF ANY MARINE OR
 TERRESTRIAL HABITAT, OR NATIVE SHORELINE VEGETATION
 THAT ARE IDENTIFIED IN THE EXISTING NATURAL RESOURCES
 SECTION OF THE CONSERVATION ELEMENT OF THE
 COMPREHENSIVE PLAN AND DISPLAYED ON THE VEGETATIVE
 COVER AND WILDLIFE HABITATS MAP AT FIGURE 11-3 OF THAT
 ELEMENT.
 (2)WITHIN A PROPOSED DEVELOPMENT, NATURAL SHORELINE
 LACKING WETLAND VEGETATION SHALL BE PLANTED WITH
 WETLANDS VEGETATION IN ORDER TO MINIMIZE POTENTIAL
 FLOOD DAMAGE, STABILIZE THE SHORELINE, AND TRAP
 SEDIMENTS AND OTHER NONPOINT SOURCE POLLUTANTS. (3)
 SHORELINE HARDENING STRUCTURES MAY BE USED ONLY IF
 EROSION IS A THREAT TO LIFE AND PROPERTY AND THE USE OF
 VEGETATION HAS FAILED TO STABILIZE THE SHORELINE. (4)
 NEW SHORELINE HARDENING STRUCTURES OR REPLACEMENT OF
 ANY EXISTING BULKHEADS SHALL CONSIST OF OR INCLUDE
 SLOPING STRUCTURES OF RIP-RAP OR PERMEABLE MATERIALS
 COMBINED WITH VEGETATION.
 (CODE 1979, / 33-147)
  
 BUILDING PLAN REVIEW
 JIM WITMER C. B. O.
  
 TEL: (561)805-6715
 FAX: (561)659-8026
 E-MAIL: [email protected]

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2007-01-08 Cont ID  
Sent By jwitmer Date 2007-01-08 Time 11:49 Rev Time 3.33
Received By jwitmer Date 2007-01-08 Time 11:49 Sent To  
Notes
2007-01-08 12:43:45BUILDING 06110750
 ADD: 4300 N FLAGLER DRIVE
 CONT: CENTEX
 TEL: (561)841-5034
  
  
 FL BLD CODE= 2004 FLORIDA BUILDING CODE
 * WEST PALM BEACH AMENDMENTS
  
 1STREVIEW
 ACTION: DENIED
  
  
 1)--- VERY IMPORTANT STATEMENT ---
 PLEASE DO NOT IGNORE!
 WHEN RESUBMITTING PLANS PLEASE INDICATE
 THE REVISION & REMOVE & REPLACE ANY
 PAGES AS NECESSARY. A TRANSMITTAL LETTER
 LISTING THE ORIGINAL REVIEW COMMENT NUM-
 BER, WITH A DESCRIPTION OF THE REVISION
 MADE, IDENTIFYING THE SHEET OR SPECIFICA
 TION PAGE WHERE THE CHANGES CAN BE FOUND
 WILL HELP TO EXPEDITE YOUR PERMIT. THANK
 YOU FOR YOUR ANTICIPATED COOPERATION.
  
 2 ) FL S S 713.13/ 105.8*
 NOTICE OF COMMENCEMENT, TO BE FILED
 WITH THE CLERK OF THE COURT BEFORE A
 PERMIT WILL BE ISSUED. NOTE: 713.13(2)
 IF THE WORK DESCRIBED IN THE NOTICE OF COMMENCEMENT IS
 NOT ACTUALLY COMMENCED
 WITHIN 90 DAYS AFTER THE RECORDING
 THEREOF, SUCH NOTICE IS NULL & VOID.
  
 3A)105.1* WORK THAT REQUIRES A PERMIT.
 CITY CODE SEC. 54-292. PROJECTING STRUCTURES.
 IT SHALL BE UNLAWFUL FOR ANY PERSON TO ERECT ANY
 STRUCTURE OR PORTION THEREOF IN OR OVER THE WATERS OF
 LAKE WORTH, WITHIN THE CITY, ON PILINGS OR PILLARS,
 EXCEPT PROPERLY APPROVED MARINE DOCKS AND ACCESSORIES,
 STRUCTURES AND APPURTENANCES THERETO, SEAWALLS,
 BREAKWATERS, BULKHEADS, BRIDGES AND CAUSEWAYS. (CODE
 1979, ? 16-39)
  
  
 3B) WORKING WITHOUT A PERMIT SEE FEE SCHEDULE
 4X PERMIT FEE WORKING WITH OUT THE BENIFET OF A
 PERMIT.
  
 W P B ADMINISTRTIVE CODE 108.2
 SCHEDULE OF PERMIT FEES. ON BUILDINGS, STRUCTURES,
 ELECTRICAL,
 GAS, MECHANICAL, AND PLUMBING SYSTEMS OR ALTERATIONS
 REQUIRING
 A PERMIT,A FEE FOR EACH PERMIT SHALL BE PAID AS
 REQUIRED,
 IN ACCORDANCE WITH THE SCHEDULE ESTABLISHED BY THE
 APPLICABLE GOVERNING AUTHORITY.
  
 4) REQUIRED APPROVAL FROM OTHER GOVERNMENTAL AGENCIES:
 CITY CODE:
 SEC. 94-378. SHORELINE MANAGEMENT.
 (A)DOCKS, MARINAS, ETC.
 (1)NEW BOAT BASINS, MARINAS, DOCKS AND OTHER MOORING
 FACILITIES ARE PROHIBITED UNLESS APPROVED BY THE
 APPROPRIATE GOVERNMENTAL AGENCIES, SUCH AS THE U.S.
 ARMY CORP OF ENGINEERS, STATE DEPARTMENT OF
 ENVIRONMENTAL REGULATION, STATE DEPARTMENT OF NATURAL
 RESOURCES, BOARD OF TRUSTEES OF THE INTERNAL
 IMPROVEMENT TRUST FUND, AND THE SOUTH FLORIDA WATER
 MANAGEMENT DISTRICT.
 (2)IN NO EVENT SHALL ANY NEW BOAT BASIN, MARINA,
 DOCK, OR ANY OTHER STRUCTURE BE APPROVED WHICH WOULD
 CONSTRICT WATER CIRCULATION IN LAKE WORTH.
 (B)SHORELINE STABILIZATION.
 (1)WITHIN A PROPOSED DEVELOPMENT IN THE COASTAL
 AREA, THERE SHALL BE NO NET LOSS OF ANY MARINE OR
 TERRESTRIAL HABITAT, OR NATIVE SHORELINE VEGETATION
 THAT ARE IDENTIFIED IN THE EXISTING NATURAL RESOURCES
 SECTION OF THE CONSERVATION ELEMENT OF THE
 COMPREHENSIVE PLAN AND DISPLAYED ON THE VEGETATIVE
 COVER AND WILDLIFE HABITATS MAP AT FIGURE 11-3 OF THAT
 ELEMENT.
 (2)WITHIN A PROPOSED DEVELOPMENT, NATURAL SHORELINE
 LACKING WETLAND VEGETATION SHALL BE PLANTED WITH
 WETLANDS VEGETATION IN ORDER TO MINIMIZE POTENTIAL
 FLOOD DAMAGE, STABILIZE THE SHORELINE, AND TRAP
 SEDIMENTS AND OTHER NONPOINT SOURCE POLLUTANTS. (3)
 SHORELINE HARDENING STRUCTURES MAY BE USED ONLY IF
 EROSION IS A THREAT TO LIFE AND PROPERTY AND THE USE OF
 VEGETATION HAS FAILED TO STABILIZE THE SHORELINE. (4)
 NEW SHORELINE HARDENING STRUCTURES OR REPLACEMENT OF
 ANY EXISTING BULKHEADS SHALL CONSIST OF OR INCLUDE
 SLOPING STRUCTURES OF RIP-RAP OR PERMEABLE MATERIALS
 COMBINED WITH VEGETATION.
 (CODE 1979, ? 33-147)
  
 BUILDING PLAN REVIEW
 JIM WITMER C. B. O.
  
 TEL: (561)805-6715
 FAX: (561)659-8026
 E-MAIL: [email protected]

Review Stop ENG ENGINEERING CSD
Rev No 4 Status P Date 2007-08-30 Cont ID  
Sent By rchokshi Date 2007-08-30 Time 10:35 Rev Time 0.00
Received By rchokshi Date 2007-08-30 Time 10:35 Sent To  
Notes
***NONE***

Review Stop ENG ENGINEERING CSD
Rev No 3 Status F Date 2007-07-13 Cont ID  
Sent By rchokshi Date 2007-07-13 Time 09:29 Rev Time 0.00
Received By rchokshi Date 2007-07-13 Time 08:40 Sent To  
Notes
2007-07-13 09:29:18***FAILED**** PLEASE PROVIDE THE FOLLOWING:
  
 1. PLEASE PROVIDE A COPY OF NOTICE OF INTENT (NOI).
 PLEASE APPLY AT FDEP, NPDES STORMWATER SECTION FOR
 NOI.
 YOU CAN GET NOI INFO FROM
 WWW.DEP.STATE.FL.US/WATER/STORMWATER/NPDES/
 NOTICE OF INTENT DEP FORM 62-621.300(4)(B),
 EFFECTIVE MAY 1, 2003
 2. THE COPY OF E-MAIL YOU SUBMITTED FROM CORPS OF
 ENGINEERS(ARMY)IS NOT CLEAR, SAYS ONLY FOR "TRAVEL
 HOIST PIERS ....".YOU ALSO SENT USA COPY OF FDEP
 PERMIT #50-0162161-006, PAGE 1, PARA A)SAYS YOU ARE
 DREDGING APPROX 156,000 CUBIC YARDS OF MATERIAL ETC,
 PAGE 1,PARA B) SAYS DOCK WILL BE RECOFIGURED & REPLACED
 WITH APPROX 99,360 SQUARE FEET OF FLOATING DOCK,ETC.
 PAGE 3, APPROX7TH PARAGRAPH SAYS PROPOSED PROJECT IS
 NOT CONSISTENT WITH STATE PROGRAMMATIC GENERAL PERMIT
 (SPGP), MAY REQUIRE A SEPARATE PERMIT FROM ARMY CORP OF
 ENGINEERS. DRAWING SHEET S3, TOP LEFT SAYS "NEW
 FLOATING DOCKS (BY OTHERS), (TYP)".THEREFORE, WE
 CONCLUDE THATPLEASE GET AN OFICIAL LETTER (NOT
 E-MAIL) FROM ARMY CORPS OF ENGINEERS THAT YOU NEED A
 PERMIT OR YOU DO NOT NEED A PERMIT.
 3. ACCORDING TO MANNY G. OF 45TH STREET, ENGINEERING,
 YOU WERE SUPPOSED TO TAKE VIDEO SHOWING THE PRE & POST
 CONDITION OF STORM PIPE GOING THRU THE SEA-WALL. YOU
 HAVE NOT TAKEN VIDEO YET.ALSO, ACCORDING TO MANNY,
 YOU WERE GOING TO TURN IN THIS STORM PIPE TO CITY,
 THAT HAS NOT HAPPENED YET. YOU NEED TO WORK WITH MANNY
 G. TO RESOLVE THIS ISSUE.
 4. PLEASE SHOW ON DRAWINGS THE POLLUTION PREVENTION
 DETAILS,TURBIDITY CONTROL PLANS, PLANS MUSTSHOW SILT
 FENCE AROUND THE SITE & CATCH BASINS PER FDEP.HEIGHT
 OF SILT FENCE & TURBIDITY CONTROL SHOULD BE HIGH ENOUGH
 PER FDEP TO STOP DUST & PARTICLES.
  
 PLEASE RESPOND EACH ITEM IN DETAIL TO EXPEDITE YOUR
 PERMITTING PROCESS. WHEN YOU RESUBMIT PLEASE SEND FDEP
 PERMIT ALONG WITH OTHER SUPPORTING DOCUMENTS.
  
 RASIK CHOKSHI805-6723

Review Stop ENG ENGINEERING CSD
Rev No 2 Status F Date 2007-03-02 Cont ID  
Sent By rchokshi Date 2007-03-02 Time 11:39 Rev Time 0.00
Received By rchokshi Date 2007-03-02 Time 11:04 Sent To  
Notes
2007-03-02 11:39:42RESPONSE TO YOUR REPLY(CENTEX CONSTRUCTION DOCU REVIEW
 RESPONSE) OF 1/31/07:
  
 1. IN YOUR RESPONSE LETTER YOU SAID DEPERPERMIT#
 50-0162161-004, IT APPEARS THAT IT MAY BE
 50-0162161-006.
 2.GREENBERG/TRAURIG'S LETTER OF 12/6/06, ARE THEY
 AUTHORIZED AGENTFOR ARMY CORP OF ENGINEERS? WE NEED A
 DIRECT APPROVAL OR PERMIT NOT NEEDEDLETTER FROM ARY
 CORP OF ENGINEERS.
 3. PERMIT # 05110729 IS FOR DIFFERNT PURPOSE, LET US
 FINISH THIS JOB !
 4. PLEASE ANSWER ALSO, ALL MY QUESTIONS REPORTED ON
 1/18/07 COMMENTS REV 1. TO EXPEDITE YOUR PERMIT.
  
 PLEASE RESPONSE EACH ITEM ADDRESSED IN TODAY'S REVISION
 AND 1/18/07 REV1 TO EXPEDITE YOUR PERMITTING PROCESS.
  
 RASIK CHOKSHI 805-6723

Review Stop ENG ENGINEERING CSD
Rev No 1 Status F Date 2007-01-18 Cont ID  
Sent By rchokshi Date 2007-01-18 Time 13:45 Rev Time 0.00
Received By rchokshi Date 2007-01-18 Time 11:38 Sent To  
Notes
2007-01-18 13:45:17PLEASE PROVIDE FOLLOWING INFO:
 1. YOU NEED AN APPROVAL PERMIT FROM U.S ARMY CORPS. OF
 ENGINEERS, FOR DOCKS, WATER WAYS,AND ALSO FROM FDEP &
 DERM
 2. PLEASE SHOW STANDARDS NOTES OF CITY OF WPB ON
 DRAWINGSFOR SIDEWALK WIDTH , ITS SLOPE, DRIVEWAY,
 PARKING, HANDICAP PARKING, PAINTPER CITY CODES ETC.,,
 MUST MEET PER ADA,,ETC.,
 3. PLEASE SHOW ON DRAWINGSDUMPSTER & ITS ENCLOSURE
 DETAILS PER CITY OF WPB, &LOCATION ON DWG, LOCATION
 MUST BE ACCESSIBLE FOR PICKUP TRUCK.
 4. FIRST FLOOR ELEVATION, CENTER LINE OF ROAD ,
 SIDEWALK ELEVATION MUST MEET FL BLDG CODE, PLEASE SHOW
 ON THE DRAWINGS.
 5. PLEASE PROVIDE A COPY OF SFWMD PERMIT, & GEO TECH
 REPORTS.,
 6.PLEASE SHOW STORM WATER QUALITY CALCULATIONS, WHAT
 CRITERIA YOU ASSUMEDFOR RUNOFF CAL.,, LIKE 1" OVER
 ENTIRE SITE OR2.5"CRITERIA, ?PERVIOUS AREA, LIKE
 GREEN, LAKES, IF ANY. ETC,IMPERVIOUS AREA CAL.,
 7. WHAT IS THE SITE AREA, YOU ARE DEVELOPING FOR THIS
 PROJECT ONLY ? SO, WE CAN CHECK PERVIOUS, IMPERVIOUS
 CAL.
 8. HOW YOU CONNECT TO THE STORM WATER PIPES IN YOUR
 SITE? ITS DETAILS.PLEASE SHOW ALL STORM WATER PIPES
 AROUND YOUR SITE SO, WE CANSEE THE BEST PIPE TO
 CONNECT WITH THE STORM WATERFROM ALL OTHER STORM
 WATER PIPES. PLEASE SHOW DETAIL OF THE CONTROL
 STRUCTURES WITH ELEVATIONS, NOTCHES, BLEEDING
 ELEVATION, ETC DID YOU USE EXFILTRATION TRENCH ? 9.
 POLLUTION PREVENTION DETAILS,CLOTHES USED FOR SILT
 ETC., PLANS SHOWING SILT FENCE AROUND THE SITE
 10. WATER & SEWER PLANS MUST BE APPROVED FROM 45TH
 STREET (MANNY G.), UTILITY DEPT BEFORE WE APPROVED 11.
 ALSO PLEASE SHOW ALL CATCH BASINS NEAREST,AROUND YOUR
 SITE FOR STORM WATER DRAIN.
  
 PLEASE RESPOND EACH ITEM IN DETAIL TO EXPEDITE YOUR
 PERMITTING PROCESS
  
 RASIK CHOKSHI805-6723

Review Stop I INCOMING/PROCESSING
Rev No 7 Status N Date 2007-10-26 Cont ID  
Sent By adarroug Date 2007-10-26 Time 10:01 Rev Time 0.00
Received By adarroug Date 2007-10-26 Time 10:01 Sent To B
Notes
2007-10-26 10:01:40TO "JWITMER" DESK/SUBMITTAL

Review Stop I INCOMING/PROCESSING
Rev No 6 Status N Date 2007-09-06 Cont ID  
Sent By adarroug Date 2007-09-06 Time 11:35 Rev Time 0.00
Received By adarroug Date 2007-09-06 Time 11:35 Sent To  
Notes
2007-09-06 11:36:12REVISION SUBMITTED UNDER WRONG PERMIT#.PLEASE SEE
 PERMIT#06081925

Review Stop I INCOMING/PROCESSING
Rev No 5 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time 0.00
Received By adarroug Date 2007-09-06 Time 11:27 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2007-08-27 Cont ID  
Sent By adarroug Date 2007-08-27 Time 14:57 Rev Time 0.00
Received By adarroug Date 2007-08-27 Time 14:57 Sent To ENG
Notes
2007-08-27 14:58:17TO "ENG" BOX/RESUB

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2007-06-05 Cont ID  
Sent By adarroug Date 2007-06-05 Time 15:01 Rev Time 0.00
Received By adarroug Date 2007-06-05 Time 15:01 Sent To  
Notes
2007-06-18 09:14:40TO "COMM" BD#52
2007-06-05 15:01:51WAITING FOR "COMM" BD

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2007-02-06 Cont ID  
Sent By adarroug Date 2007-02-06 Time 16:16 Rev Time 0.00
Received By adarroug Date 2007-02-06 Time 16:16 Sent To  
Notes
2007-02-13 14:44:01TO "COMM" BD#58
2007-02-06 16:16:23WAITING FOR "COMM" BD

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2007-01-25 Cont ID  
Sent By adarroug Date 2007-01-25 Time 09:12 Rev Time 0.00
Received By adarroug Date 2006-11-29 Time 18:05 Sent To  
Notes
2006-12-07 09:59:59TO "COMM" BD#49
2006-11-29 18:05:30WAITING FOR "COMM" BOARD

Review Stop Z ZONING
Rev No 3 Status P Date 2007-06-18 Cont ID  
Sent By jroach Date 2007-06-18 Time 21:15 Rev Time 0.00
Received By jroach Date 2007-06-18 Time 21:15 Sent To  
Notes
2007-06-18 21:16:46***PROVISO***
  
 1) PERMIT ISSUED FOR CONSTRUCTION OF THE BULKHEAD AND
 TRAVEL LIFT PIERS ONLY, AS PROVIDED IN LETTER FROM
 WILLIAM COTTLE, PROJECT MANAGER, TO JIM WITMER, DATED
 APRIL 2, 2007.
  
 QUESTIONS/COMMENTS, CONTACT JOHN ROACH, SENIOR PLANNER,
 AT (561) 822-1435.

Review Stop Z ZONING
Rev No 2 Status P Date 2007-02-25 Cont ID  
Sent By jroach Date 2007-02-25 Time 18:05 Rev Time 0.00
Received By jroach Date 2007-02-25 Time 18:05 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2007-01-25 Cont ID  
Sent By jroach Date 2007-01-25 Time 08:56 Rev Time 0.00
Received By jroach Date 2007-01-25 Time 08:55 Sent To  
Notes
***NONE***