| Plan Review Stops For Permit 06100663 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
3 |
Status |
P |
Date |
2007-05-01 |
|
|
Cont ID |
|
| Sent By |
lmartine |
Date |
2007-05-01 |
Time |
15:10 |
Rev Time |
0.00 |
| Received By |
lmartine |
Date |
2007-05-01 |
Time |
15:10 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
2 |
Status |
P |
Date |
2007-02-20 |
|
|
Cont ID |
|
| Sent By |
rnuquist |
Date |
2007-02-20 |
Time |
18:57 |
Rev Time |
0.00 |
| Received By |
rnuquist |
Date |
2007-02-20 |
Time |
18:57 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
P |
Date |
2006-11-05 |
|
|
Cont ID |
|
| Sent By |
rnuquist |
Date |
2006-11-05 |
Time |
18:37 |
Rev Time |
0.00 |
| Received By |
rnuquist |
Date |
2006-11-05 |
Time |
18:37 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
5 |
Status |
N |
Date |
2007-04-25 |
|
|
Cont ID |
|
| Sent By |
adarroug |
Date |
2007-04-25 |
Time |
13:23 |
Rev Time |
0.00 |
| Received By |
adarroug |
Date |
2007-04-25 |
Time |
13:23 |
Sent To |
Z |
|
| Notes |
| 2007-04-25 13:23:22 | TO "Z' BOX/RESUB |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
4 |
Status |
N |
Date |
2007-01-29 |
|
|
Cont ID |
|
| Sent By |
adarroug |
Date |
2007-01-29 |
Time |
19:03 |
Rev Time |
0.00 |
| Received By |
adarroug |
Date |
2007-01-29 |
Time |
19:03 |
Sent To |
B |
|
| Notes |
| 2007-01-29 19:04:02 | TO "LMARTINEZ" DESK/RESUB |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
3 |
Status |
N |
Date |
2007-01-17 |
|
|
Cont ID |
|
| Sent By |
adarroug |
Date |
2007-01-17 |
Time |
11:09 |
Rev Time |
0.00 |
| Received By |
adarroug |
Date |
2007-01-17 |
Time |
11:09 |
Sent To |
Z |
|
| Notes |
| 2007-01-17 11:10:03 | TO "Z" BOX/RESUB--NEW SHEETS FOR "BLDG" |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
2 |
Status |
N |
Date |
2006-10-31 |
|
|
Cont ID |
|
| Sent By |
adarroug |
Date |
2006-10-31 |
Time |
09:06 |
Rev Time |
0.00 |
| Received By |
adarroug |
Date |
2006-10-31 |
Time |
09:06 |
Sent To |
B |
|
| Notes |
| 2006-10-31 09:06:40 | TO "MISC" BOX#2 |
|
|
| Review Stop |
I |
INCOMING/PROCESSING |
| Rev No |
1 |
Status |
N |
Date |
2006-11-05 |
|
|
Cont ID |
|
| Sent By |
rnuquist |
Date |
2006-11-05 |
Time |
18:37 |
Rev Time |
0.00 |
| Received By |
rnuquist |
Date |
2006-10-20 |
Time |
13:49 |
Sent To |
|
|
| Notes |
| 2006-10-20 13:49:22 | TO "Z" BOX |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
3 |
Status |
P |
Date |
2007-04-30 |
|
|
Cont ID |
|
| Sent By |
eschneid |
Date |
2007-04-30 |
Time |
16:15 |
Rev Time |
0.00 |
| Received By |
eschneid |
Date |
2007-04-30 |
Time |
16:15 |
Sent To |
I |
|
| Notes |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
2 |
Status |
F |
Date |
2007-01-26 |
|
|
Cont ID |
|
| Sent By |
mmclean |
Date |
2007-01-26 |
Time |
10:31 |
Rev Time |
0.00 |
| Received By |
mmclean |
Date |
2007-01-26 |
Time |
10:31 |
Sent To |
I |
|
| Notes |
| 2007-01-26 10:35:56 | DENIED, | | | 1. PLEASE CLARIFY IF THE COMPLETE PROPERTY WILL BE | | | RE-PAVED (EXISTING BUILDING AND PARCEL 2). | | | 2. NEED TO CALCULATE THE BUILDING REQUIRED PARKING AS | | | PER CODE FOR EACH USE WILL STILL MEET THE REQUIRED | | | PARKING. (SEC 94-486 TABLE XV-6.) | | | 3. SITEPLAN CALCULATION SHOWS THA THE PARKING WILL BE | | | LESS THAN WHAT IS APPROVED. | | | 4. SITEPLAN SHALL PROVIDE THE TOTAL COUNT OF ALL | | | PARKING AT LOCATION (AS APPROVED). | | | 5. PROPERTY SHALL PROVIDE A UNITY OF TITLE FOR THE | | | OUTPARCEL 2 (PIZZA HUT),WHICH WAS ILLEGALLY | | | SUB-DIVIDED. | | | PLEASE CALL ERIC SCHEEIDER, PRINCIPAL PLANNER 822-1435 | | | | | | | | | MICHELLE MCLEAN | | | ZONING TECHNICIAN | | | 805-6720 |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
F |
Date |
2006-10-28 |
|
|
Cont ID |
|
| Sent By |
mmclean |
Date |
2006-10-28 |
Time |
13:08 |
Rev Time |
0.00 |
| Received By |
mmclean |
Date |
2006-10-28 |
Time |
13:08 |
Sent To |
I |
|
| Notes |
| 2006-10-28 13:17:49 | DENIED, | | | 1. PLEASE SUBMIT A COPY OF SURVEY FOR THE PROPERTY. 2. | | | THE SITEPLANS SUBMITTED DO NOT PROVIDE THE DIMESNION OF | | | THE LOT. | | | 3. PLEASE PROVIDE THE TOTAL SQUARE FOOTAGE OF THE | | | EXISTING STRUCTURE. | | | 4. PLEASE PROVIDE THE TOTAL PARKING COUNT THAT WAS | | | APPROVED FOR THE LOCATION. | | | 5. PLEASE PROVIDE PLANS THAT SHOWING THE EXISTING | | | PARKING. | | | 6. PLEASE SHOW THE LOCATION OF THE HANDICAP PARKING | | | (COUNT) | | | | | | PARKING MUST BE DOUBLE STRIPPED TO CITY CODE. | | | | | | | | | MICHELLE MCLEAN | | | ZONING TECHNICIAN | | | 805-6720 |
|
|