| 2006-08-31 00:00:00 | |
| | |
| | |
| | |
| | |
| | |
| | |
| | THE VALUE ON THE APPLICATION MUST |
| | INCLUDE THE COST OF LABOR AND MATERIAL |
| | FOR THE INSTALLATION OF ALL COMPONENTS |
| | UNDER THE SCOPE OF THIS PERMIT. FBC |
| | 108.3. |
| | |
| | 1} PROVIDE A RISER DIAGRAM SHOWING |
| | ELECTRICAL CONNECTION OF ALL SERVICE AND |
| | GENERATOR EQUIPMENT. |
| | |
| | 2} THE SITE PLAN SUBMITTED DOES NOT |
| | CLARIFY THE PHYSICAL LOCATION OF THE |
| | EQUIPMENT. COMPLIANCE WITH ARTICLE 225 |
| | CANNOT BE DETERMINED. PLEASE REDRAW AND |
| | LABEL IF SEPARATE LOCATIONS. |
| | |
| | 3} THE LOAD CALCULATION EXCEEDS THE |
| | GENERATOR OUTPUT. SEE 702.5, CAPACITY |
| | AND RATING. |
| | AN OPTIONAL STANDBY SYSTEM SHALL HAVE |
| | ADEQUATE CAPACITY AND RATING FOR THE |
| | SUPPLY OF ALL EQUIPMENT INTENDED TO BE |
| | OPERATED AT ONE TIME. OPTIONAL STANDBY |
| | SYSTEM EQUIPMENT SHALL BE SUITABLE FOR |
| | THE MAXIMUM AVAILABLE FAULT CURRENT AT |
| | ITS TERMINALS. THE USER OF THE OPTIONAL |
| | STANDBY SYSTEM SHALL BE PERMITTED TO |
| | SELECT THE LOAD CONNECTED TO THE SYSTEM. |
| | |
| | 4} THERE MUST BE A DISCONNECT FROM THE |
| | GENERATOR WHERE THE CONDUCTORS ENTER THE |
| | BUILDING. IF ALL DISCONNECTS CANNOT BE |
| | GROUPED PER 230.72, SEE THAT ALL |
| | ARTICLES FROM 225.31 THROUGH 225.39, ARE |
| | COMPLIED WITH. |
| | |
| | 5} PROVIDE MANUFACTURERS |
| | SPECIFICATIONS/RECOMMENDATION, REGARDING |
| | CLEARANCES. |
| | |
| | 6} PROVIDE SPECIFICATIONS FOR THE |
| | TRANSFER SWITCH. |
| | |
| | 7} THE PERSON TAKING RESPONSIBILITY FOR |
| | THE PLAN/DRAWINGS, SHALL PRINT AND SIGN |
| | THEIR NAME ON THE SHEETS THEY DRAW. |
| | PLEASE DO THIS PRIOR TO RESUBMITTING. |
| | |
| | BILL TROBAUGH |
| | ELECTRICAL PLAN REVIEW |
| | 561/805-6718 |
| | [email protected] |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |